36C24219B0010-0001000.docx

DOCX document 19 KB Posted

Attached to
528A6-17-602 BRIDGE REHABILITATION Federal contract opportunity
Solicitation number
36C24219B0010
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

36C24219B0010 0001 36C24219B0010 0001.docx

View the file

Other files for this federal contract opportunity

Other files attached to 528A6-17-602 BRIDGE REHABILITATION, newest first.
File Type Posted
36C24219C0097-000.docx DOCX document
36C24219B0010-002.pdf PDF
36C24219B0010-003.pdf PDF
36C24219B0010-000.docx DOCX document
36C24219B0010-001.docx DOCX document
36C24219B0010.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 02-19-2019 528A6-17-602 00242 Network Contracting Office 2 Bath VA Medical Center 76 Veterans Avenue Bath

NY

14810 00242 Same as Block 6

To all Offerors/Bidders

36C24219B0010 02-19-2019

X X X

See attached pages for question and answers

MARK D. SIMONSON

Contracting Officer

CONTINUATION PAGE

1. Please provide a control joint detail and layout for the fixed end of the bridge.

There are no control joints required in the design for the new concrete deck.

2. Please provide details and intent regarding concrete removal around and under bridge bearings and associated anchors.

Details and design intent at show on drawings SB401, SB402, and SB501. The intent of hatched areas shown on drawings SB401 and SB402 is to show the limits of repair areas. It is not the intent to have every hatched area shown on drawings SB401 and SB402 replaced. It is not the intent of the design to jack and lift the bridge in order to replace bearing pedestals.

3. Please confirm that the bridge is free of lead paint as was discussed in the pre-bid walk through.

None of the specimens sampled were positive for lead.

4. When then deck load is removed from the span and deflection occurs will local utility owners coordinate / be responsible for leaks etc.

• Water main.

• Sanitary Sewer main.

• Gas main.

Per notation on the drawings, the contractor is responsible for temporary supports of utilities to prevent deflection. See reconstruction notes on drawing GI002, drawing S-105, detail 1, and drawings SB401 and SB402.

5. Will local utilities be responsible for replacing hangers and supports if required

• Water main.

• Sanitary Sewer main.

• Gas main.

• Electric

• Telephone Per reconstruction notes on drawing GI002, the contractor will be responsible for repairing or replacing any hangars or supports that are required to be replaced.

6. Will the engineer supply / calculate deflection tables for the screed rail setup?

There is a note on drawing S-103, detail 3 that addresses approximate deflection due to dead load. The contractor is welcome to hire an engineer to perform that task for their equipment.

7. Are there any DBE, MBE, or WBE requirements on the contract?

DBE, MBE, or WBE requirements will be noted in the RFP and/or contract documents provided by Bath VAMC.

8. Are there any work force EEO requirements on the contract?

EEO requirements will be noted in the RFP and/or contract documents provided by Bath VAMC.

9. Are there any permits required to perform the Bridge Rehabilitation (SWIPP, DEC, etc…)?Whom is responsible to obtain said permits?

All of the work is above the high water of the bridge and there is no earthwork being performed.

Encorus does not believe a DEC permit is required in this case. The contractor should be able to perform all of the work under a US ACE Nationwide Permit, 3. Maintenance. As long as that permit is followed during construction, the contractor is in compliance. The website is here:

http://www.lrb.usace.army.mil/Missions/Regulatory/nationwide-Permits/ The Maintenance Permit is here:

http://www.lrb.usace.army.mil/Portals/45/docs/regulatory/NWP/2017NWP/2017_NWP- 3.pdf?ver=2017-03-27-160907-737 The bridge is located in a 100-year flood zone. However, the construction is not impacting the water flow in any way. That being said, the Bath VAMC and US ACE should be notified by the contractor prior to the start of work.

10. Are there any restrictions on when the Bridge can be closed (Memorial Day, 4th of July) or when the Bridge needs to be re-opened (Veterans Day)?

Work May begin anytime prior to Memorial Day but it must remain open to traffic until Memorial Day is past

11. Will there be time between Award and Notice to Proceed to prepare / review / approve the demolition plan, steel repair shop drawings, etc…?

Available time is up to the contractor to coordinate. Encorus will work diligently to keep review and approval time of submittals to minimize impact on the schedule.

12. Notice to Proceed plus 120 calendar days to complete the Rehabilitation of the Bridge is very tight. Can the duration be extended?

The contract period will be 150 days

13. Has all the lead paint been remediated from the existing bridge structure?

None of the specimens sampled were positive for lead.

14. There is not sufficient room to perform the prescribed concrete repairs to the existing abutments behind Floor Beams F80 and F87. How do we proceed?

The intent of hatched areas shown on drawings SB401 and SB402 is to show the limits of repair areas. The concrete backwall is not to be removed and replaced and no earthwork or excavation is being performed as part of this project.

15. Specification Section 01 45 29 requires the GC to provide construction materials inspection, both on site and offsite at our material suppliers and fabricators. Do we need to include cost for Concrete Batch Plant inspection, Rebar Mill inspections, Structural Steel Fabrication plant inspection, etc… or do we simply need to supply a field concrete inspection (slump, air, temperature, cylinders), field structural steel inspect (SIP welds, stud welds, bolted connections)?

Yes. Include cost for plant, mill, and shop inspection as well as field inspection.

16. Is the VA retaining a Construction Inspection agency to perform the daily inspections outlined above?

The Bath VA Engineers will be the oversite of the project.

17. The contract drawings indicate a 4” yellow paint stripe is required, Specification Section 32 17 23 indicates that the pavement marking will be epoxy. Which is correct (paint)?

The specification 32 17 23 is correct. The pavement marking should be epoxy.

1. Please confirm the thickness of the steel gusset plate repair sections.

Detail 5 on drawing S-104 are intended to show typical detail arrangements. Thickness of steel gusset plate repairs are noted on drawing S-105.

2. Plan sheets SB401 & SB 402 show concrete repairs to the bridge seat areas. Is the intent for the contractor to perform structural lifting or jacking to support the bridge while the concrete is removed and repaired?

The intent of hatched areas shown on drawings SB401 and SB402 is to show the limits of repair areas. It is not the intent to have every hatched area shown on drawings SB401 and SB402 replaced. It is not the intent of the design to jack and lift the bridge in order to replace bearing pedestals.

2. Please confirm which end of the bridge is fixed and which end is expansion.

Fixed and expansion bearings are noted on drawing S-101.

4. Plan sheet S105 detail 4 calls for repair of the outboard members. Detail 6 appears to indicate that the repairs will be done on both the inboard and outboard sides of the truss. Please confirm.

Confirmed. Detail 4 and 6 on drawing S-105 is intended to show that both channels are corroded and require repair within the outboard truss member.

5. How many days of wet cure and how many days of dry cure will be required for the new deck?

Curing requirements are noted in Specification 033000 Cast-In-Place Concrete.

6. Is the new deck and sidewalk to be sealed with penetrating sealer?

The new deck and sidewalk are to receive a protective sealer. The limits of protective sealing are shown in Detail 2 on drawing S-101.

7. Please consider extending the contract work duration by 30 days to allow for concrete cure time.

The contract period will be 150 days