36C10B19Q0193 A0001 36C10B19Q0193 - Questions _ Answers 2-19-19.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C10B19Q0193-A0001001.pdf | ||
| 36C10B19Q0193-A0001000.docx | DOCX document | |
| 36C10B19Q0193-000.docx | DOCX document | |
| 36C10B19Q0193-001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Integrated Master Schedule (IMS) Support
Request for Quote (RFQ) 36C10B19Q0193
Questions and Answers
February 19, 2019
Note: The answers provided below are for informational purposes, to assist potential offerors in preparing quotes, and such answers do not themselves constitute an amendment to the RFQ. Where questions and answers necessitated such an amendment, such changes have been or will be incorporated into a formal amendment to the RFQ. To the extent that any answers provided below conflict in any way with the RFQ and any Amendments, the final RFQ takes precedence and the terms and conditions contained in the final solicitation control.
# Section Question Answer
1. General Are these services are currently being performed by a contractor? If so, please provide the incumbent name as well as the contract number.
There is no incumbent for this effort.
2. General It’s fairly difficult to discern the LOE from the
PWS. 25 projects is a good start, but it’s not clear how much effort is on the contractor for the data input.
The Government has provided an estimated level of effort. See the table below the Q&A. This information is a Government estimate only. Quoters shall bid a level of effort commensurate to their approach.
3. General Clarification on the request concerning the system that will be implemented. Is the system
Cerner?
The IMS procurement is a consolidation of existing schedules from varying VA OIT subprojects supporting programs, which may include Electronic
Health Record Modernization (EHRM).
See Amendment A00001.
4. Section B.5, Performance Work Statement
(PWS) 1.0, Background
The government indicated the following, "Provide a day-to-day tool for executing the
OIT Program with proper sequencing." Did the Government intend to say OIT
Organization? Or OTI Program?
OTI Program. See Amendment A00001.
5. Section B.5, PWS Task 5.2, IMS Analysis Will the contractor be expected to work with directly with all 25 project teams to develop inputs? Or will the project teams provide
The Contractor shall interface with all Project
Managers. Project Managers will provide updates to their individual schedules that will make up the IMS.
updates into the IMS directly once the IMS is in place?
6. Section B.5, PWS Task 5.3, IMS
Dashboard
How many of the projects are using Primavera
vs. MS Project?
All existing projects are built with MS Project.
7. Section B.5, PWS Task 5.3, IMS
Dashboard
Does a project dashboard exist for reference, or is this a complete new build?
There is no existing dashboard.
8. Section B.5, PWS Task 5.3, IMS
Dashboard
The Dashboard is assumed to need to run in the VA environment with VA equipment on
VA servers. Can you describe:
• The current version of MS Project VA supports – including enterprise versions.
• The current version of MS SharePoint
VA has available
• Data visualization tools (Tableau, PowerBI, etc.) VA has licensed
• Availability of GFE, and how many
GFE computers are expected
If the dashboard is anticipated to be built and run from contractor equipment, please advise.
For current versions of MS Project and SharePoint please reference the VA Technical Reference Model
(TRM) at https://www.oit.va.gov/services/trm/.
Furthermore, please note that the Dashboards developed for other OTI efforts are typically developed using MS SharePoint. However, other software identified in the VA TRM are acceptable.
See PWS Section 6.6 Government Furnished Property for GFE.
9. Section E.8, Basis for Award, Quote
Submission Instructions
Page 75 of the solicitation includes instructions for Quoter's responses including:
"3) All documents are single-spaced, 12-point
Times New Roman font, with a minimum of
1-inch margins..." Would the Government please allow for 10-point Times New Roman font in tables?
The Government will allow 10-point Times New
Roman font for tables.
https://www.oit.va.gov/services/trm/
Estimated Level of Effort
Task Labor category Base Labor
Hours
Option 1
Labor Hours
Option 2
Labor Hours
5.1 Project Management Program Manager 320 200 200
Administrative Assistant 480 480 480
5.2 IMS Analysis Scheduler, Senior 440 616 880
Scheduler 480 672 960
5.3 IMS Dashboard Program Manager 80 20 20
Scheduler, Senior 160 160 160
Administrative Assistant 160 40 40
5.4 IMS Support Scheduler, Senior 1320 1848 2640
Scheduler 480 672 960
Total 3,920 4,708 6,340
***This information is a Government estimate only. Quoters shall bid a level of effort commensurate to their approach.