3699934_CDRL1_REPORT.pdf

PDF 98 KB Posted

Attached to
Support Turbine Com Federal contract opportunity
Solicitation number
SPRTA1-24-Q-0078
Issued by
Defense Logistics Agency Aviation

About this file

This document contains two Contract Data Requirements Lists (CDRLs) related to a federal solicitation. The CDRLs require a contractor to submit a First Article Qualification Test Plan and Procedures, including a list of drawing dimensions and tolerances to be verified, plans for non-destructive inspections, visual inspections, and material property verification. The contractor must also describe processes for verifying sources of manufacturing and forging. The test plan is due 30 days from contract award. Additionally, the contractor must submit a Test/Inspection Report satisfying all test plan requirements, including part dimensions and sources of manufacturing. The report is due 120 days from government approval of the test plan. Both CDRLs require ISO-10149 compliant electronic submission to the Defense Logistics Agency Aviation for a solicitation to provide Support Turbine Components.

View the file

Other files for this federal contract opportunity

Other files attached to Support Turbine Com, newest first.
File Type Posted
3707495_PKGRQMT_REPORT.pdf PDF
3707496_TRNSPDATA_REPORT.pdf PDF
SPRTA124Q0078.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188(1 Data Item)

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188).

Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER X

D. SYSTEM / ITEM

F100/ P/N: 4084713

E. CONTRACT / PR NO.

FD20302301581

F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

First Article Qualification Test Plan and Procedures

3. SUBTITLE

NSN: 2840-01-446-6205NZ NOUN:TURBINE

COMPONENT SUPPORT

4. AUTHORITY

DI-NDTI-81307A

(Data Acquisition Document No.) 5. CONTRACT REFERENCE

N/A

6. REQUIRING OFFICE

AFLCMC/LPSAA

7. DD 250 REQ

SD

8. APP CODE

N/A

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

1 XTIME

11. AS OF DATE

SEE BLOCK 16

12. DATE OF FIRST

SUBMISSION

SEE BLOCK 16

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

a. ADDRESSEE

Draft Final

ReproReg

b. COPIES

14. DISTRIBUTION

16. REMARKS

Hobbs, Carly RNAME: 23 MAY 2023DATE:

Block 9: DIST STATEMENT REQUIRED: Distribution Statement A: Approved for public release; distribution is unlimited. Controlling DoD office is 848 SCMG/421 GUEA.

Disposal and destruction notices: Dispose of by putting it in a recycle container or regular trash receptacle.

Block 14: Deliveries shall be submitted on ISO-10149 compliant CD-ROM in Adobe Acrobat Portable Document Format.

Contractor must provide a plan to ensure that all drawing requirements are met on each first article. The plan should include the equipment and facilities utilized to verify all drawing requirements. As a minimum, the following information is required.

a. A list of all drawing dimension, tolerances and the equipment utilized to verify each dimension. An actual drawing should be submitted to correlate with the dimension list.

b. A plan to verify that all non-destructive inspections are met.

c. A plan to verify that all visual inspection requirements are met.

d. A plan to verify material properties to include mechanical properties, metallurgical properties and chemical compositions.

e. A plan to verify that all significant manufacturing processes are performed by sources that are currently approved/ certified by the OEM (P&W) or the CEA (AFLCMC/LPSAA).

f. A plan to verify that all forging or casting sources are currently approved/certified by the OEM (P&W) or the CEA (AFLCMC/LPSAA) if applicable. Guidelines for first article test plans are contained within LPF-QAR-003, attached.

A government representative must coordinate on the first article test plan. The first article test plan shall be received 30 calendar days from the date of contract.

Contractor will include any QAR findings relative to the test report with the final test report submitted to

AFLCMC/LZPED.

COORDINATORS:

AFLCMC/LZPED

3001 Staff Dr, Ste 1AB 85A Tinker AFB, OK 73145-3041 Attn: FA Monitor

0 2 0

0 2 015. TOTAL

G. PREPARED BY

Hobbs, Carly R

421 SCMS / GUMAA

405-582-5971

H. DATE

23 MAY 2023

I. APPROVED BY

//ELECTRONICALLY SIGNED//

Ashford, Holden A

AFLCMC / LPSBE 405-734-8773 / 884-8773

J. DATE

23-MAY-23

Page 1 of 2DD FORM 1423-1, FEB 2001 Version 1Generated by PRPS using Jasper Reports on 26 Jun 2023

PREVIOUS EDITION MAY BE USED.

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188(1 Data Item)

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER X

D. SYSTEM / ITEM

F100/ P/N: 4084713

E. CONTRACT / PR NO.

FD20302301581

F. CONTRACTOR

1. DATA ITEM NO.

A002

2. TITLE OF DATA ITEM

Test/Inspection Report

3. SUBTITLE

NSN: 2840-01-446-6205NZ NOUN:TURBINE

COMPONENT SUPPORT

4. AUTHORITY

DI-NDTI-80809B/T

(Data Acquisition Document No.) 5. CONTRACT REFERENCE

N/A

6. REQUIRING OFFICE

AFLCMC/LPSAA

7. DD 250 REQ

SD

8. APP CODE

N/A

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

1 XTIME

11. AS OF DATE

SEE BLOCK 16

12. DATE OF FIRST

SUBMISSION

SEE BLOCK 16

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

a. ADDRESSEE

Draft Final

ReproReg

b. COPIES

14. DISTRIBUTION

16. REMARKS

Hobbs, Carly RNAME: 23 MAY 2023DATE:

Block 9: Distribution Statement A: Approved for public release; distribution is unlimited. Controlling DoD office is 848

SCMG/421 GUEA.

Disposal and destruction notices: Dispose of by putting it in a recycle container or regular trash receptacle.

Block 14: Deliveries shall be submitted on ISO-10149 compliant CD-ROM in Adobe Acrobat Portable Document Format.

Contractor format acceptable unless otherwise defined by applicable Data Item Description (DID).

The first article test report shall satisfy all requirements in the first article test plan. All drawing requirements must be satisfied including dimensions, visual inspections, non-destructive inspections (NDIs), manufacturing processes and material requirements. The test report shall indicate that any sources used to perform significant manufacturing processes are approved/certified by the OEM (P&W) or the CEA (AFLCMC/LPSAA).

A copy of the part process sheets shall be provided also. A government representative must coordinate on the test report.

Guidelines for the test reports are contained within LPF-QAR-003 Rev E, attached.

The first article test reports shall be received at OC-ALC/ENRS 120 calendar days from the date of government approval of test plan.

Contractor will include any QAR findings relative to the test report with the final test report submitted to

AFLCMC/LZPED.

COORDINATORS:

AFLCMC/LZPED

3001 Staff Dr, Ste 1AB 85A Tinker AFB, OK 73145-3041 Attn: FA Monitor

0 2 0

0 2 015. TOTAL

G. PREPARED BY

Hobbs, Carly R

421 SCMS / GUMAA

405-582-5971

H. DATE

23 MAY 2023

I. APPROVED BY

//ELECTRONICALLY SIGNED//

Ashford, Holden A

AFLCMC / LPSBE 405-734-8773 / 884-8773

J. DATE

23-MAY-23

Page 2 of 2DD FORM 1423-1, FEB 2001 Version 1Generated by PRPS using Jasper Reports on 26 Jun 2023

PREVIOUS EDITION MAY BE USED.

File details come from the government source that posted it. Updated .