Text version

Performance Work Statement

FOR

Uninterrupted Power Supply (UPS) Modular Power Revitalization Service (MPRS)

AT THE

U.S. Army Acquisition, Logistics and Technology Enterprise Systems & Services (ALTESS) Project Office Radford Army Ammunition Plant, Radford, VA

17 November 2020 General Information

1. GENERAL: This is a services contract to perform Modular Power Revitalization Services (MPRS) WMPRS520-MP-520 for one (1) Schneider Electric Symmetra PX 500kW IO Frame with Right Mounted Maintenance Bypass and Distribution (S/N: QD1422120004). Revitalization services to include scheduling upgrade (installation) to 7 x 24 for MPRS WUPGMPRS7x24-MP-00. Services to be performed at PD ALTESS in Radford, VA.

The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the requested function at PD ALTESS, Radford VA 24143 as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.1.1 Contractor shall:

· Provide Schneider Electric CPCS trained/certified technicians

· Provide Movement of new/disposed components to and from service location(s)

· Confirmation of ordering, shipping of new/used components to and from site.

· Arrive on site as scheduled, coordinating the service delivery and any special requirements, with the appointed ALTESS government representative.

· Provide all documentation from installation to disposal to include any warranty and/or system inspections performed prior to departure from site.

1.2 Background: During maintenance servicing of ALTESS APC’s, ALTESS facility operation technicians identified one (1) Schneider Electric Symmetra PX 500kW IO Frame with Right Mounted Maintenance Bypass and Distribution (S/N: QD1422120004) system that has become end of service life. This unit provides uninterrupted power to the IT load within the ALTESS data center, which is consider vital to data center operations. To bring the APC back to fully mission capable, ALTESS facility managers are requesting Modular Power Revitalization Services (MPRS) with scheduling upgrade to 7x24 for MPRS. This service will replace components and internal equipment to revitalize the APC to like new status, which gives the equipment an extended life. Revitalization would not only provide uninterrupted power, but ensure the UPS system maintain continual operations in the event of a loss of power to the data center. This APC is a critical part in maintaining power to vital operational systems that ensure ALTESS and Army mission can maintain full capabilities around-the-clock.

1.3 Objectives: The objectives of the service is to perform Modular Power Revitalization Services (MPRS) WMPRS520-MP-520 for one (1) Schneider Electric Symmetra PX 500kW IO Frame with Right Mounted Maintenance Bypass and Distribution (S/N: QD1422120004). Revitalization services to include scheduling upgrade (installation) to 7 x 24 for MPRS WUPGMPRS7x24-MP-00. Services to be performed at PD ALTESS in Radford, VA.

1.4 Scope: The contractor shall furnish all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items to perform non-personal services necessary to perform battery replacement for PD ALTESS at building 450, Radford, VA.

1.5 Period of Performance: The period of performance shall be upon contract award for four (4) months.

1.6 General Information

1.6.1 Quality Control: The contractor shall ensure that work complies with the requirement of the contract and this PWS. A formal Quality Control Plan is not needed for this contract. Surveillance and inspection will be conducted by the Government. Any deficiencies found shall be corrected in a timely manner.

1.6.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.6.3 Recognized Holidays: The Contractor is not required to perform work on the following Federal holidays:

New Year’s DayLabor Day
Martin Luther King Jr.’s BirthdayColumbus Day
President’s DayVeteran’s Day
Memorial DayThanksgiving Day
Independence DayChristmas Day

1.6.4 Hours of Operation: The contractor is responsible for conducting business between the hours of 7:00 am – 4:00 pm, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, weather, or similar Government directed facility closings. Work expected to be performed outside of these hours must be approved by the Government at least one week in advance. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.6.5 Place of Performance: Work under this contract will be performed at the Radford Army Ammunition Plant (RFAAP), ALTESS building 450 and associated areas in Radford, VA 24143.

1.6.6 Type of Contract: The government intends to award a Firm Fixed Price (FFP) contract.

1.6.7 Security Requirements: All contractor and service personnel visiting RFAAP must have US citizenship and provide one form of valid photo ID for entrance onto RFAAP. All personnel will require an escort at all times.

All contractor and service personnel providing a recurring service to the RFAAP installation are required to obtain a RFAAP badge. In order to obtain a RFAAP badge the contractor shall submit and obtain a favorable nationwide formal background investigation for the personnel. This background investigation must be from a state agency or licensed background firm and not a computer search. Contractor personnel cannot have any adjudication actions (parole, probation, or open case files) within the past 5 years or they will not be able to obtain a RFAAP badge and access to the installation shall be denied. The investigation shall be submitted to RFAAP security personnel though the contracting official. The RFAAP Security Office shall then, upon validation of the favorable investigation, provide the RFAAP badge. The personnel receiving a RFAAP badge shall be required to carry the badge with them at all times while on the installation and secure the badge out of sight when not on the installation. Cell phones, cameras, PDA and electronic devices are not allowed on the installation without prior approval.

Contractors not requiring a RFAAP badge must obtain a visitor’s badge at the Visitor Station located at the entrance to the RFAAP facility. This badge must be worn at all times and be plainly visible.

Contractor personnel performing work under this contract must possess and abide by the security requirements at the time of proposal submission, and must maintain the level of security required for the life of the contract.

1.6.7.1 PHYSICAL Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secure.

1.6.7.2.1. In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor.

1.6.7.2.2. The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.

1.6.8 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.6.9 Contracting Officer Representative (COR): The COR, if needed for this contract, will perform duties as specified in the Contracting Officer’s COR Letter of Designation. A COR may or may not be assigned to this contract. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.9.1. A COR is not required for this action.

Key Personnel (Government):

Greg Tickle Facility Specialist US Army Acquisition Logistics Technology Enterprise Systems and Services (ALTESS) Office: 540-731-3593 Email: gregory.a.tickle.civ@mail.mil

Tim Hancock Team Lead, Facility Management US Army Acquisition Logistics Technology Enterprise Systems and Services (ALTESS) Office: 540-731-3522 Email: timothy.w.hancock@us.army.mil

Contracting Office Representative (COR) Roger K. Mann A.P.P., C.P.M.

Acquisitions & Contracts PD-ALTESS/US Army Acquisition Logistics Technology Enterprise Systems and Services Office: 540-731-5417 Email: roger.k.mann.civ@mail.mil

1.6.10 Key Personnel (Contractor): The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between of 7:00 am – 4:00 pm Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

1.6.11 Identification of Contractor Employees: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed. Contract personnel will wear visible badges at all times.

1.6.12 Contractor Travel: There is no specific Government-directed travel as part of this PWS.

1.6.13 Data Rights: The Government will have full ownership of all technical data, reports, and deliverables associated with this task order option.

1.6.14 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS:

2.1.1. CONTRACTOR. A supplier or vendor having a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. DELIVERABLE. Anything that can be physically delivered but may include non-physical things such as meeting minutes.

2.1.6. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.7. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.8. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.9. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.10. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.11. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12. WORK WEEK. Is defined as Monday through Friday, unless specified otherwise.

2.2. ACRONYMS

ACORAlternate Contracting Officer's Representative
AFARSArmy Federal Acquisition Regulation Supplement
ARArmy Regulation
CCEContracting Center of Excellence
CFRCode of Federal Regulations
CONUSContinental United States (excludes Alaska and Hawaii)
CORContracting Officer Representative
COTRContracting Officer's Technical Representative
COTSCommercial Off the Shelf
DADepartment of the Army
DD250Department of Defense Form 250 (Receiving Report)
DD254Department of Defense Contract Security Requirement List
DFARSDefense Federal Acquisition Regulation Supplement
DMDCDefense Manpower Data Center
DODDepartment of Defense
FARFederal Acquisition Regulation
HIPAAHealth Insurance Portability and Accountability Act of 1996
KOContracting Officer
OCIOrganizational Conflict of Interest
OCONUSOutside Continental United States (includes Alaska and Hawaii)
ODCOther Direct Costs
PIPOPhase In/Phase Out
POCPoint of Contact
PRSPerformance Requirements Summary
PWSPerformance Work Statement
QAQuality Assurance
QAPQuality Assurance Program
QASPQuality Assurance Surveillance Plan
QCQuality Control
QCPQuality Control Program
TETechnical Exhibit

3. GOVERNMENT FURNISHED PROPERTY, EQUIPMENT AND SERVICES:

3.1The Government will make available the restroom facilities in Building 220 and/or Building 450 for the contractor’s use in performance of tasks outlined in the PWS. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.

4. CONTRACTOR FURNISHED ITEMS

4.1 General: The Contractor shall furnish all supplies, equipment, and services required to perform work under this contract in accordance with this PWS.

5. SPECIFIC TASKS:

5.1. The Modular Power Revitalization Services shall provide:

· Removal and disposal service WMPRS520-MP-520 for:

· One (1) APC Symmetra PX500kW IO Frame with Right Mounted Maintenance Bypass and Distribution (S/N QD1422120004).

· Removed and disposed components include:

· Power Modules

· Intelligence Modules

· Static switch

· Network card(s)

· Power view display(s)

· Main fan

· Switchgear board(s)

· Battery monitoring

· System Power Supply Unit(s) (PSU)

· All transportation of removed parts off-site for proper disposal under state, local, and EPA guidelines

5.2 The Modular Power Revitalization Services shall:

· Provide procurement and installation services WMPRS520-MP-520 for:

· One (1) APC Symmetra PX500kW IO Frame with Right Mounted Maintenance Bypass and Distribution (S/N QD1422120004).

· Provide scheduling upgrade to 7x24 for MBRS Part Number WUPGMBRS7x24-MB-00

· Provide procurement and installation services for:

· Power Modules

· Intelligence Modules

· Static switch

· Network card(s)

· Power view display(s)

· Main fan

· Switchgear board(s)

· Battery monitoring

· System Power Supply Unit(s) (PSU)

· Fully certified Schneider Electric CPCS trained/certified technicians

· New Original Equipment Manufacturer (OEM) components/parts from original manufacturer with a current year manufacturer date stamp on them. No grey market, refurbished, used or recycled items will be accepted.

· Perform all services associated with the revitalization without any interruption to the UPS supported load and/or associated IT equipment.

· Perform revitalization services while UPS systems are online and providing uninterruptible power to the critical load during performance of work and/or at the end of each business day.

· Provide system configurations and functional checks by certified APC technicians upon completion of revitalization services and/or prior to departure from site.

· Provide system configuration and functionality verification.

· Must be performed upon completion of services

· Provide One (1) year Single Phase Advantage Plan

· Relocate all used components from UPS system location to a site designated shipping dock location.

· Palletize used components for shipment, and transport/load onto shipping vehicle.

· Ship used components to approved off-site disposal location under state, local, and EPA guidelines

· Perform all services associated with the revitalization without any interruption to the UPS supported load and/or associated IT equipment.

· Provide ALTESS government representatives with all proper environmental documentation that reflects proper disposal methods were met per local, state, and EPA guidelines.

Critical Notes:

Any and all electrical work required and/or associated with this service must meet or exceed national, state, and local electrical codes. (NEC)

6. CONTRACTOR MANAGEMENT REPORTING (CMR) The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall completely fill in all the information in the format using the following web address 8. CONTRACTOR MANAGEMENT REPORTING (CMR). The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall completely fill in all the information in the format using the following web address https://Contractormanpower.army.pentagon.mil. The required information includes: (1) Contracting Office, Contracting Officer, Contracting Officer’s Technical Representative (COTR) or also known as the Contracting Officer’s Representative (COR); (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours (including sub-Contractors); (6) Estimated direct labor dollars paid this reporting period (including sub-Contractors); (7) Total payments (including sub-Contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.

6.1. Contractor Manpower Reporting. The Contractor will report ALL Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Department of the Army via a secure data collection site. The Contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil, and then click on "Department of the Army CMRA" or the icon of the DoD organization that is receiving or benefitting from the contracted services.

Reporting inputs will be for the labor executed during the period of performance during each government FY, which runs from October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported NLT October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk by clicking on "Send an email" which is located under the Help Resources ribbon on the right side of the login page of the applicable service/Component's CMR website at http://www.ecmra.mil. As part of its submission, the Contractor will also provide the estimated total cost (if any) incurred to comply with this reporting requirement."

7. PERFORMANCE REQUIREMENTS SUMMARY

7.1 Surveillance of Contractor performance will employ the performance objectives and thresholds as defined in Table 6.0, Performance Requirements Summary.

7.2 Note: Must be an authorized Schneider Electric reseller/partner

Table 7: Performance Requirements Summary

Service Required
PWS Paragraph Number/ Reference
Standard of Performance
Acceptable Quality Level

(AQL)

Surveillance Method Incentive / Disincentive

Contractor shall provide removal and disposal of MPRS services WMPRS520-MP-520 for One (1) APC Symmetra PX 500kW IO Frame with Right Mounted Maintenance Bypass and Distribution (S/N QD1422120004)
1. General

1.3. Objectives

5.1 Specific Tasks

Components shall be removed and transported by contractor to an approved off-site disposal/recycle facility prior to contractor’s departure from site and/or upon completion of service as stated in PWS.

Zero damage to equipment, facilities and/or impact to environment during services.
PD ALTESS datacenter managers, Facility manager and/or COR representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance inspection.

None

Contractor shall provide installation service WMPRS520-MP-520 for One (1) APC Symmetra PX 500kW IO Frame with Right Mounted Maintenance Bypass and Distribution (S/N QD1422120004)
1. General

1.3. Objectives

5.2 Specific Tasks

All components for installation to include ordering and shipping to site shall be provided by contractor prior to performance of services without deviation from specified dates/times designated by contractor and government representatives.

Zero delays, loss of man-hours, miss-shipments to include safety, environmental incidents throughout the duration of the services.
PD ALTESS datacenter managers, Facility manager and/or COR representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance inspection.
None
Contractor shall provide Schneider Electric CPCS trained/certified technicians.
5.2 Specific Tasks
Contractor to provide fully certified Schneider Electric APC/UPS certified technicians prior to and during services. Contractor shall make available certification documents prior to services if requested by government representatives.
Zero damage to equipment, facilities and/or impact to environment during services.
PD ALTESS datacenter managers, Facility manager and/or COR representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance inspection.
None
Contractor shall provide ordering, shipping, transportation and movement of used and new components to and from service site.
5. Specific Tasks
The contractor shall confirm the components ordered, along with the ship to address, shipment date and any special site condition, and the time and date of the Service Professional arrival at the customer site to include Service Professional will arrive on site as scheduled, coordinating the service delivery and any special Requirements, with the appointed contact as stated within this PWS.
Zero delays, loss of man-hours, miss-shipments to include safety, environmental incidents throughout the duration of the services.
PD ALTESS datacenter managers, Facility manager and/or COR representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance inspection.
None
Contractor shall provide Schneider Electric service inspection of system conditions, configurations and functional testing.
5. Specific Tasks
Contractor shall inspect condition, configurations, and functional testing of systems prior to and/or upon completion of revitalization service as stated within this PWS.
Zero damage to equipment, facilities and/or impact to environment during services.
PD ALTESS datacenter managers, Facility manager and/or COR representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance inspection.
None

8. DELIVERABLES

8.1 The items listed Table 7.0, Deliverables Summary, are deliverable to the Government in accordance with this PWS.

Table 8: Deliverables Summary

Deliverable
Frequency
Number of Items/Copies

Format

Submit To

Proof of manufacturer replacement warranty
Once
1 per APC unit.
Hardcopy or via email
Greg Tickle,

gregory.a.tickle.civ@mail.mil, PD ALTESS

Documentation of environmental disposal
Once
1 per piece of disposal equipment. (Document may encompass multiple pieces of equipment disposed if necessary and/or as dictated by ALTESS government representative.
Hardcopy or via email
Greg Tickle,

gregory.a.tickle.civ@mail.mil, PD ALTESS

One (1) year Single Phase Advantage Plan pamphlet/data sheet
Once
1 per item(s) as necessary.
Hardcopy or via email
Greg Tickle,

gregory.a.tickle.civ@mail.mil, PD ALTESS

Results of system functional checks prior to, during and upon completion of revitalization service.
Once
1 per APC unit.
Hardcopy or via email
Greg Tickle,

gregory.a.tickle.civ@mail.mil, PD ALTESS

File details come from the government source that posted it. Updated .