3- Pictures.pdf

PDF 3 MB Posted

Attached to
Butte Ranger District Lead Paint Removal Federal contract opportunity
Solicitation number
1240LU23Q0049
Issued by
Department of Agriculture Forest Service

About this file

This document outlines the requirements for a federal contract to remove lead-based paint from five buildings at the Old Whitehall Administrative Site in Whitehall, Montana. The contract is solicited by the Department of Agriculture Forest Service under solicitation number 1240LU23Q0049. The work includes complete removal of lead-based paint from the exterior siding, trim, soffit, facia, and windows of the specified buildings. The contractor must be certified and perform all work in accordance with historic preservation requirements for the site. The performance period is 45 calendar days beginning around September 15, 2023. The contractor is responsible for disposing of all debris and temporary utilities and facilities during the work. Payment will be made based on the bid items for the required work.

View the file

Other files for this federal contract opportunity

Other files attached to Butte Ranger District Lead Paint Removal, newest first.
File Type Posted
0) Solicitation Old Whitehall Admin Site Lead Paint Removal.pdf PDF
5- WD General Decision Number MT20230016 01062023.pdf PDF
1- Schedule of Items (to provide quote prices).pdf PDF
4- Work Involving Lead-Based Paint (LBP).pdf PDF
2- Experience Questionnaire.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building #D1014, Men’s Bunkhouse

Old Whitehall Admin Site Lead Paint Removal Pictures

Building #1306, Women’s Bunkhouse

Building #D1501, Residential Garage

Building #D2301, Garage/Shop

Building #D2401, Horse Barn

01110 Summary of Work
1
1 .1 DESCRIPTION
A. The work of this contract consists of the complete removal of lead-based paint from the exterior siding, trim, soffit, facia, and windows on buildings at the Old Whitehall Administrative Site. The work also includes all necessary preparatory work....
B. All work will be performed under a single contract.
1 .2 LOCATION
A. The Old Whitehall Administrative Site is located on the 600 block of West Legion Avenue in Whitehall, Montana.
1 .3 CONTRACT START DATE
A. The Notice to Proceed will be at a mutually agreeable date expected to be on or about September 15, 2023
1 .4 CONTRACT TIME
A. The work of this contract shall be completed within 45 calendar days of the date of the Notice to Proceed. A seasonal shutdown may be issued if weather conditions do not permit work within specified tolerances.
1 .5 CONTRACTOR'S USE OF PREMISES
A. Construction Camp: Establishment of a camp at the construction site will not be permitted.
B. Conduct operations to ensure the least inconvenience to the building occupants.
C. Confine storage of materials to areas designated at the pre-construction conference.
1 .6 CONTRACTOR CERTIFICATION:
1 .7 SPECIAL CONSTRUCTION REQUIREMENTS
A. The Old Whitehall Administrative Site was constructed as a ranger station between 1936 and 1938. Because of the historical significance of the buildings associated with the Whitehall Ranger Station, they have been formally determined to be eligibl...
B. Weekend and Holiday Work Restrictions: No on-site work shall be performed on weekends or federal holidays unless otherwise authorized by the Contracting Officer.
1 .8 FIELD VERIFICATION
A. Field verify all dimensions affecting the work of this contract before ordering products.
1 .9 TEMPORARY SERVICES
A. Electrical service, in the form of 120 volt, 15 amp receptacles, is available at no cost to the Contractor. Contractor is responsible for providing extension cords as needed.
B. No telephone service is available on site for Contractor’s use.
C. Potable water and sanitary facilities are available on the site during normal business hours.
1 .10 TEMPORARY CONTROLS
A. HOUSEKEEPING:
1. Keep project neat, orderly, and in a safe condition at all times. All construction debris be cleaned up at the end of each working day and placed in suitable containers.
2. Provide containers for collecting construction debris. Forest Service trash receptacles shall not be used.
B. DISPOSAL:
1. Dispose of construction debris in a legal manner off of Forest Service property.
1 .11 CONSTRUCTION MATERIALS
A. All materials shall be Contractor-furnished.
1 .12 PRECONSTRUCTION CONFERENCE
A. Before the start of construction, the Contracting Officer will arrange an on-site meeting with the Contractor.
2
3
4
4 .1 SUMMARY OF WORK
A. Payment will be included in the bid item to which this work relates.

02094 Lead Based paint

File details come from the government source that posted it. Updated .