DEPARTMENT OF THE NAVY
HRMC (NMD)
SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED
SPECIFICATION NUMBE HRMC- M&E-23-0010
INCLUDES ALL CHANGES THROUGH 5/31/2023
DRAFT
INDEX
SHIP: HRMC-HM&E-23-0010
ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-24 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.
ITEM NO. TITLE CHANGE DATE CHANGE
009-01 General Criteria; accomplish 09/27/2022 Original
009-02 Environmental Compliance Report for Material Usage; accomplish 09/27/2022 Original
009-03 Toxic and Hazardous Substance; control 09/27/2022 Original
009-04 Quality Management System; provide 09/27/2022 Original
009-05 Temporary Access; accomplish 09/27/2022 Original
009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
09/27/2022 Original
009-07 Confined Space Entry, and Certification; accomplish 09/27/2022 Original
009-08 Shipboard Fire Protection and Fire Prevention; accomplish 10/14/2022 Original
009-10 Asbestos-Containing Material (ACM); control 09/27/2022 Original
009-18 Mine Warfare Ships Magnetic Material; control 09/29/2022 Original
009-19 Provisioning Technical Documentation (PTD); provide 09/27/2022 Original
009-20 Government Property; control 09/27/2022 Original
009-21 Logistics and Technical Data; provide 09/27/2022 Original
009-23 Interference; remove and install 09/29/2022 Original
009-24 Authorization, Control, Isolation, Blanking, Tag ing, and anliness;
accomplish
09/27/2022 Original
009-34 Fire Protection of Unmanned Ves l a Contracto acility; accomplish 09/27/2022 Original
009-39 Technical Manual Contract R quiremen (TMCR) fo a New Technical Manual for Commercial Equipment/ mpone plish
09/27/2022 Original
009-40 Contractor Crane, Multi-Purpos Machine and Material Handling Equipment at a Naval Facility; pr d
09/27/2022 Original
009-60 Schedule and A ociated R orts fo CNO Availabilities; provide and manage 09/30/2022 Original
009-61 Shipboard Us of Fluorocarbon control 09/27/2022 Original
009-67 Integrated Total S Testing; manage 09/27/2022 Original
009-69 Heavy Weather/Mooring P n; provide 09/27/2022 Original
009-70 Confined Space Entry, Certification, Fire Protection, Fire Prevention and
Housekeeping for Unmanned Vessels; accomplish
09/27/2022 Original
009-72 Physical Security at a Private Contractor Facility; accomplish 09/30/2022 Original
009-73 Shipboard Electrical/Electronic Cable Procedure; inspect, test, install, remove, and repair
09/30/2022 Original
009-74 Occupational, Safety and Health Plan; accomplish 09/30/2022 Original
009-80 Ship Facilities; maintain 09/27/2022 Original
009-81 Compartment Closeout; accomplish 09/30/2022 Original
009-82 Installation of Equal Component Vice Specified Component; report 09/27/2022 Original
009-84 Threaded Fastener Requirements; accomplish 09/30/2022 Original
009-88 Collection, Holding and Transfer (CHT) and Motor Gasoline (MOGAS) Tanks, Spaces, and Piping, including Sewage or MOGAS-Contaminated Tanks, Spaces, and Piping; certify
09/27/2022 Original
009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution
Prevention Act (PPA) Information; provide
09/27/2022 Original
SHIP HRMC-HM&E-23-0010
ITEM_NO. TITLE CHANGE DATE CHANGE
009-99 Ship Departure Report; provide 09/27/2022 Original
009-100 Ship's Stability; maintain 09/30/2022 Original
009-101 Ship Transit and Berthing; accomplish 09/27/2022 Original
009-106 Work Authorization Form Coordinator (WAFCOR); provide 09/27/2022 Original
009-109 Non-SUBSAFE Work on SUBSAFE-Certified Vessel; accomplish 09/27/2022 Original
009-110 Non-Nuclear Work on a Nuclear Vessel; accomplish 09/27/2022 Original
009-111 Schedule and Associated Reports for non-CNO Availabilities; provide and manage
09/30/2022 Original
009-117 Combat Systems, Light-Off Suport; provide 09/30/2022 Original
009-118 CG Deck Loading; accomplish 09/27/2022 Original
009-120 Fact Finding and Critique of Unplanned Event; manage 09/30/2022 Original
009-122 Temporary Padeye; install and remove 09/30/2022 Original
009-125 Boats Less Than 65 Feet Long; accomplish 10/25/2022 Original
CATEGORY II. FY-24 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER.
TITLE CHANGE DATEITEM NO. CHANGE
009-12 Weld, Fabricate, and Inspect; accomplish 09/27/2022 Original
009-25 Structural Boundary Test; accomplish 09/29/2022 Original
009-26 Deck Covering; accomplish 09/29/2022 Original
009-32 Cleaning and Painting Requirements; accomplish 09/29/2022 Original
009-87 Chemical disinfection Procedures; accomplish 09/27/2022 Original
009-90 Technical Representative; provide 09/27/2022 Original
ITEM NO. TITLE
Hazardous Waste Produced on Naval Vessels; control077-00-001
Voids, Tanks; open and inspect123-11-001
Engine & Equipment Room Hatch; repair167-11-001
Door Hardware and Locks; replace167-11-002
Power Panel and Tool Chest; repair180-11-001
Main Engines and Reduction Gears; repair233-11-001
Sea Intake Strainer; replace233-11-002
Shafts, Propellers, & Rudders; repair245-10-001
Generator; repair311-21-001
Low Voltage Meters; replace320-00-001
Flood Light; replace320-11-002
Backup Camera & Monitor; install439-11-001
Air Conditioning Unit; repair514-31-001
Bilge Pump; replace529-21-001
Transfer of Boat Cust dy; accomp is583-11-001
Push Knee an Hull Fen ring; rep ce611-11-001
Stanchion, Rai g, a d Lifeline Assembly; repair612-11-001
W dshield pers, M tors, & Switches; replace625-11-001
Underwater Hull preserve631-31-001
Nons d; repai634-11-001
Pilot House Flooring; replace634-11-002
Drydocking, Undocking; accomplish997-11-001
SHIP: ITEM NO: 077-00-001
COAR: 26 PCN: DSV4-L001
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 5 ITEM NO: 077-00-001
1. SCOPE:
1.1 Title: Hazardous Waste Produced on Naval Vessels; control
1.2 Location of Work:
1.2.1 Throughout the Ship
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Resource Conservation and Recovery Act (RCRA)
2.2 Federal Hazardous Materials Transportation Act, 49 U.S.C. 5103
2.3 Applicable Hazardous Waste Manifest Form
2.4 10 U.S.C. , 7311
3. REQUIREMENTS:
3.1 Manage and dispose of all hazard s wa te listed in 3.5 in accordance with 2.1 and 2.2.
3.1.1 When a Navy generato umber is required by this Work Item, submit the original of 2.3 t th SUPERV SOR for assignment of Environmental Protection Agen y (EPA) r delegated state environmental agency id ntifica ion number.
3.1.2 Manage and t anspo t for Navy disposal, Navy-generated
hazardous waste l sted i 3 5 in accordance with 2.1 and 2.2, as designated by the UPERVISOR.
3.1.3 Submi o leg le copy of 2.3 signed by the owner or operator of the dis osal fa ility to the SUPERVISOR within 48 hours of receipt from own or opera or of disposal facility.
3.2 Complete d umentation required by 2.1 and 2.2, using EPA or delegated state en iro mental agency identification number in accordance with 2.4.
3.2.1 Documentation related to hazardous waste generated solely by the physical actions of Ship's Force or Navy employees (termed Navy- Generated Hazardous Waste) on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law. The contractor shall obtain SUPERVISOR'S concurrence with the categorization of the waste as Navy-generated before completion of the manifest. The manifest prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.
3.2.2 Documentation related to hazardous waste generated solely by the physical actions of contractor personnel (termed Contractor- Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law.
Regardless of the presence of other material in or on the shipboard systems or structure which may have qualified a waste stream as hazardous, where the contractor performs work on a system or
SHIP:
SSP: HRMC-HM&E-23-0010 2 of 5 ITEM NO: 077-00-001 structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator number issued to the contractor.
3.2.3 Documentation related to hazardous waste generated by the combined physical actions of Navy and contractor personnel (termed Co-Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law. When the contractor merely drains a system and such drainage creates hazardous waste or the contractor performs work on system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste, documentation related to such waste shall bear a generator identification number issued to the contractor and shall also cite in the remarks block a generator identification number issued to the Navy. The contractor shall sign the gener tor certification on the Uniform Hazardous Waste Manifest wheneve u e of the manifest is required for disposal. The contractor shall btain SUPERVISOR's concurrence with the categorization f the wast s as co-generated before completion of the manifest. Manifests pre ared shall be presented to the SUPERVISOR for c mpleti n after the hazardous waste has been identified.
3.3 If the contractor, while performing rk at a Government facility, cannot obtain a separate generat r dentifi tion number from the state in which the availability will be perf ed, the contractor shall notify the SUPERVISOR within three busin ss days of receipt of written notification by the stat fter btaining approval of the SUPERVISOR, the contractor shall us the avy s te generator identification number and insert in the rem rks bl ck the contractor generator identification number issued for the s te where h s main facilities are located.
3.4 If, for ava lab liti at a contractor-owned or controlled facility, the Navy canno obtain a sep rate generator identification number for use at a contract r facility the Navy shall notify the contractor within three business ays of r ceipt of notification by the state. The contractor shall dispos of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.
3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:
AMOUNT
TYPE NAVY CO-GENERATED CONTRACTOR
Acid Solutions (may include _____ ____________ __________ spent sulfamic, citric, chromic, nitric, sulfuric, hydrochloric, etc.)
Ethylene Glycol (Antifreeze) _____ ____________ __________
Sodium Hydroxide _____ ____________ __________
Cleaning Solvents _____ ____________ __________
SSP: HRMC-HM&E-23-0010 3 of 5 ITEM NO: 077-00-001
Sodium Phosphates (Tri, Bi, _____ ____________ __________ or Mono)
Fluorocarbons _____ ____________ __________
Morpholine _____ ____________ __________
Sodium Chromates _____ ____________ __________
Hydrazine _____ ____________ __________
Methyl Ethyl Ketone _____ ____________ __________
Spent Abrasive Blast Material _____ ____________ __________
(contaminated with a known hazardous waste)
Trichloroethane _____ ____________ __________
Miscellaneous Chemicals _____ _ __________ __________
(Rust Preventative)
Miscellaneous Chemicals _____ _____ ______ __________
(Corrosive)
Miscellaneous Chemicals _____ ____________
(TCLP Toxic)
Miscellaneous Chemicals __ __ ____________ __________
(Reactive)
Oil (Synthetic) _____ ____________ __________
Paints (Enamel, Latex, _ _ ____________ __________
Epoxy, thinners, l base , rubber paint, on-skid lacquer, remov r, varnis es)
Paints (May inclu e le d, _____ ____________ __________ cadmium, or chrome)
Paint Strippers (phenols, _____ ____________ __________ lead, chromium)
Sludges (Contaminated with a known hazardous waste) _____
Wool Felt (contaminated _____ ____________ __________ with chromium and PCB's)
Lube/Fuel Oil Soaked Rags _____ ____________ __________
Paint/Flakes (Pressure Washing _____ ____________ ________
Ext Hull Surfaces)
Fuel Oil(Residual) _____ ____________ __________
Bilge Water _____ ____________ __________
SSP: HRMC-HM&E-23-0010 4 of 5 ITEM NO: 077-00-001
Oil/Water _____ ____________ __________
AFFF/Water _____ ____________ __________
MEK Contaminated Rags _____ ____________ __________
3.5.1 Provide 0 dollars for managing and disposing of all hazardous waste listed in 3.5. Total cost greater or less than above dollar amount will be the subject of an equitable adjustment.
3.6 Submit one legible copy, in approved transferrable media of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the SUPERVISOR.
3.6.1 The report shall include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.
3.6.1.1 Chemical analysis shall be accomplished by laboratories with state or EPA approved quality assur nce programs.
3.6.2 The contractor shall make an effort to minimize hazardous waste generation by reducing the volume r xicity by neutralizing, recycling, or otherwise removing it from the quirements of Subtitle C of 2.1 and include a description o such effo ts in the report.
3.7 Nothing contained in this Work Item shall relieve the contractor from complying with applicable federal st e, and local laws, codes, ordinances, and regulations, including t obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.
4. NOTES:
4.1 The waste listed in 3.5 is ba ed on the best information available at the time of prepara ion of the s licitation. Hazardous waste generated during the ctual formance of the work may vary in type or amount from waste liste i 3.5 which may result in renegotiation for credit or increas rsua t to Paragraph (b) of 2.4. The contractor is expected to us best m nage ent practice to identify and dispose of all hazardous was e. Some f the substances listed in 3.5 may be neutralized, r cycled, o otherwise removed from the requirements of Subtitle C of 2. Incl sion of these substances in the waste listed in
3.5 does not precl de he contractor from taking action consistent with
2.1 to reduce or eli inate the hazardous constituents of any waste required to be disposed of under the contract in accordance with 2.2.
Processes that add hazardous constituents to the bilges may require that bilge water be disposed of as a hazardous waste.
4.1.1 The types and amounts of wastes listed in 3.5 are estimates of waste to be disposed of under this contract as required by 2.4. They are not estimates of the amount of the work involved in generating that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.
4.2 Hazardous wastes are determined by one or more of the following methods:
4.2.1 Chemical analysis which shows that the material
characteristics of ignitability, corrosivity, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed the limits for that material in 40 CFR 261.20 Subpart C.
SSP: HRMC-HM&E-23-0010 5 of 5 ITEM NO: 077-00-001
4.2.2 Reference to a Material Safety Data Sheet (MSDS), or
4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.
4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When an availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated shall be included in 3.5.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SHIP: ITEM NO: 123-11-001
COAR: 16 PCN: DSV4-L005
DSV4-L013
DSV4-L003
DSV4-L004
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 123-11-001
1. SCOPE:
1.1 Title: Voids, Tanks; open and inspect
1.2 Location of Work:
1.2.1 Throughout
1.3 Identification:
1.3.1 Fuel Tank
1.3.2 Port Fresh Water Tank
1.3.3 STBD Fresh Water Tank
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Informati Book for 60-Foot Dive Support Boat, Hull 60DS1001
2.3 1-2, General Arrangement – chinery ayout
2.4 2-3, Fuel Tank Construction
2.5 2-9, Fresh Water Tank
3. REQUIREMENTS:
3.1 Provide the servi es o tified marine chemist to accomplish gas free certification of ea h tank listed in 1.3.
3.2 Open, vent late, mpty render dry, and clean each tank listed in
1.3 using 2.2 through 2 5 fo guidance.
3.2.1 Rem e and commercially dispose of each liquid and waste in accordance w h all federal, state and local laws, codes, ordinances or regulations
3.3 Accomplish a visual inspection of each tank listed in 1.3 for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, including tank vents, overflows, piping, structural members, covers, hoses, hose clamps and foundations.
3.3.1 Submit one legible copy, in hard copy or approved transferable media, of a report listing results of the requirements of 3.3 to the
SUPERVISOR.
3.4 Replace each hose and hose clamp for each tank listed on 1.3 using
2.3 through 2.5 as guidance as directed by the SUPERVISOR.
(V)(G) "COMPLETION AIR TEST"
3.5 Accomplish the requirements of 009-25 of 2.1 for air test of each tank listed in 1.3. Test pressure shall be 2 PSIG and shall be maintained 15 minutes, prior to the start of the test, to accommodate temperature stabilization. After temperature stabilization, the test pressure shall
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 123-11-001 be held for 10 minutes. Allowable drop in pressure: None.
3.5.1 Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.5 to the
SUPERVISOR.
3.6 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 167-11-001
COAR: 16 PCN: DSV4-L002
DSV4-L006
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 167-11-001
1. SCOPE:
1.1 Title: Engine & Equipment Room Hatch; repair
1.2 Location of Work:
1.2.1 Main Deck
1.3 Identification:
1.3.1 Quantity (One EA), Port Engine Access Hatch
1.3.2 Quantity (One EA), Stbd Engine Access Hatch
1.3.3 Quantity (One EA), Engine Room Egress Hatch
1.3.4 Quantity (One EA), Equipment Room E ress Hatch
2. REFERENCES:
2.1 Standard Items, (FY 23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Informati n Book for 60-Foot Dive Support Boat, Hull 60DS1001
2.3 2-2 Rev C, Engine Room Hatch
3. REQUIREMENTS:
3.1 Accomplish the requirements o lean, inspect and repair each deck hatch assembly including ac seat ng surface identified in 1.3 located in 1.2 using 2.2 and 2 as g idanc .
3.1.1 Chip and gr nd s flush in way of repairs.
3.2 Accomplish th requ ements of 009-12 of 2.1, including Table 3, Column C, Lines One t ough 7, for seating surface repair.
3.2.1 Ac omplish n ndestructive testing in accordance with Line 10 on all new elds. Criteria: No signs of cracks and or deformation allowed.
3.3 Remove and repl ce with new each deck hatch Hydraulic hatch lifter for equipment listed in 1.3.1 and 1.3.2 using 2.2 and 2.3 for guidance.
3.4 Replace with new each gasket, bushing, and apply new grease for equipment listed in 1.3 using 2.2 and 2.3 for guidance.
(V)(G) "CHALK TEST"
3.5 Accomplish the requirements of 009-25 of 2.1 for a chalk test of each deck hatch located in 1.3. Chalk imprint shall be centered with 100 percent contact.
(V)(G) "OPERATIONAL TEST"
3.6 Accomplish an operational test of each deck hatch listed in 1.3.
Operate through 3 complete cycles, with no sticking or binding permitted.
3.7 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 167-11-001
4. NOTES:
4.1 None
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 167-11-002
COAR: 16 PCN: DSV4-L028
DSV4-L026
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 167-11-002
1. SCOPE:
1.1 Title: Door Hardware and Locks; replace
1.2 Location of Work:
1.2.1 Pilot House
1.2.2 Main Cabin
1.3 Identification:
1.3.1 Quantity (One EA): Aft Sliding Door
1.3.2 Quantity (One EA): Port Sliding Door
1.3.3 Quantity (One EA): Stbd Sliding Doo
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9008-JJ-BIB-010 Rev 1, Boat Inf rmatio Book for 60-Foot Dive Support Boat, Hull 60DS1001
2.3 Operators Manual Rev 1, Armstrong Ma ine, 60FT Diver Support Boat AMI Hull #US-IAR 60 MONB111 Navsea Hull #60 S1001
3. REQUIREMENTS:
3.1 Accomplish the follo in repa rs to each sliding door closure listed in 1.3 located in 1.2 i acco dance with 2.2 and 2.3.
3.1.1 Remove, an acco p a visual inspection of each sliding
door closure listed i 1.3 using 2.2 and 2.3 for guidance.
3.1.1.1 Sub it o e legible copy, in hard copy or electronic
media of a rep rt listing results of the requirements of 3.1.1 to th SUPERVIS R.
3.1.2 Repla with new the upper rollers and lower guides for each sliding door c s re listed in 1.3 including fasteners.
3.1.3 Install and adjust each repaired sliding door closure removed in 3.1.1.
3.2 Lubricate each sliding door closure with grease (MIL-P-17578).
3.3 Remove existing and install new each lock hasp and lockset for each door listed in 1.3.2 and 1.3.3 located in 1.2.1.
(V)(G) "OPERATIONAL TEST"
3.4 Accomplish an operationally test of each sliding door closure listed in 1.3 through 5 complete cycles. Each door and new lock installed shall operate smoothly with no sticking or binding ensuring freedom of movement and proper lock operation.
3.4.1 Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.4 to the
SUPERVISOR.
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 167-11-002
3.5 Accomplish the requirements of 009-32 of 2.1, for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 180-11-001
COAR: 16 PCN: DSV4-L025
DSV4-L037
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 180-11-001
1. SCOPE:
1.1 Title: Power Panel and Tool Chest; repair
1.2 Location of Work:
1.2.1 Engine Room
1.2.2 Dive Equipment Room
1.3 Identification:
1.3.1 Quantity: (2 EA) latch for 24P Engine Room Main Distribution Panel
1.3.2 Quantity: (6 EA) tool chest
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Informatio Book for 60-F ot Dive Support Boat, Hull 60DS1001
2.3 Operators Manual Rev 1, 60FT Diver pport Boat AMI Hull #US-IAR 60 MONB111 Navsea Hull #60DS1001
3. REQUIREMENTS:
3.1 Accomplish a visual i pectio of the distribution panel, each tool chest and its bracket fo ndat on l ted in 1.3 and located in 1.2 for structural defects, mi sing parts and deterioration, using 2.2 and 2.3 for guidance.
3.1.1 Submit ne leg ble copy, in hard copy or approved
transferrab e med a, o a report listing results of the requirements of 3.1 to the SUPERVISOR
3.2 Remove ex ting and replace with new each latch listed in 1.3.1 and located in 1.2.1 sing .2 and 2.3 for guidance as directed by Supervisor.
3.3 Remove existing and replace with new each bracket foundation for each equipment listed in 1.3.2 and located in 1.2.2 using 2.2 and 2.3 for guidance.
3.3.1 Template from existing material type, size and configuration.
(V)(G) "FIT AND FUNCTION"
3.4 Accomplish appropriate fit and function test to ensure that each newly installed latch and bracket foundation perform its normal functions within the system.
3.4.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.4 to the SUPERVISOR.
4. NOTES:
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 180-11-001
4.1 None
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 233-11-001
COAR: 16 PCN: DSV4-L007
DSV4-L008
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 3 ITEM NO: 233-11-001
1. SCOPE:
1.1 Title: Main Engines and Reduction Gears; repair
1.2 Location of Work:
1.2.1 Engine Compartment
1.3 Identification:
1.3.1 Quantity (One EA): Port Diesel Engine, Make: Cummings, Model:
QSM11 MCD Rating, 455 HP @ 2100 RPM S/N: 35274908
1.3.2 Quantity (One EA): Starboard Diesel Engine, Make: Cummings, Model: QSM11 MCD Rating, 455 HP @ 2100 RPM S N: 35274909
1.3.3 Quantity (One EA):Port Main engine R duction Gear, ZF Marine, Model 325-1A, Ratio: 1.727:1 S/N: 20077 21
1.3.4 Quantity (One EA):Starboard M in engine R duction Gear, ZF Marine, Model 325-1A, Ratio: 1.727 1 S/N: 2007782
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Info mat Book for 60-Foot Dive Support Boat, Hull 60DS1001
2.3 Operators Manual Rev , Armst ng Marine, 60FT Diver Support Boat AMI Hull #US-IAR 60 MON 111 N vsea ull #60DS1001
3. REQUIREMENTS:
3.1 Accomplish th requ ements of 009-90 of 2.1, for the inspection, repair, and mai tenan se vice requirements of the equipment listed in
1.3 located i 1.2, usi g Ma ufactures service manual, 2.2 and 2.3 for guidance.
3.2 Provide the ervic s of a qualified Cummings Diesel technical representative to c mplish the following service / repairs to the equipment listed in 1.3.1 and 1.3.2 in accordance with manufacturer's instructions and or specified in this Work Item.
3.2.1 Remove each existing and replace with new each associated engine zincs (anodes).
3.2.2 Drain and replace lubricating oil and filter.
3.2.3 Clean and service engine air filter assembly.
3.2.4 Inspect and adjust engine valve lash.
3.2.5 Remove and replace primary and secondary fuel filter.
3.2.6 Inspect and adjust each fuel injector.
3.2.7 Remove and replace with new fuel/transmission cooler assembly.
3.2.8 Remove and replace with new raw water pump impeller.
3.2.9 Remove and replace with new each engine belt.
SSP: HRMC-HM&E-23-0010 2 of 3 ITEM NO: 233-11-001
3.2.10 Inspect each seawater hose and replace each with new.
3.2.11 Drain, flush and replace engine coolant.
3.2.12 Remove and replace with new coolant filter.
3.2.13 Remove and replace with new heat exchanger cap (Radiator cap).
3.2.14 Inspect each coolant hose for damage and replace each damaged coolant hose.
3.2.15 Inspect each engine wiring harness for damage or chaffing and replace each damaged and chaffed wire harness.
3.2.16 Visually inspect each engine vibration damper.
3.2.17 Accomplish an overhead set adjustment.
3.2.18 Check for current and pending fault codes on engine ECM.
3.2.19 Remove, inspect, clean and reseal charge air cooler
3.2.20 Remove, inspect, clean and reseal e gine heat exchanger
3.2.21 Take sample of engine oil and coolant nd send out for
analysis.
3.3 Provide the services of a qualif ed ZF Marine technical
representative to accomplish the follo ing ervice / repairs to the equipment listed in 1.3.3 and 1.3.4 in cordance with manufacturer's instructions, using 2.2 and 2.3 r guidan and or specified in this Work Item.
3.3.1 Remove and replace tra sm ssion lubrication oil and filter.
3.3.2 Remove, inspe t and cle n suction pick up screen.
3.3.3 Remove eac prope ler shaft mounting bolt and check alignment.
3.3.4 Take sample f fluid and send out for analysis.
3.4 Remove and dispo of ystem fluids in accordance with federal, state, and lo al laws, odes ordinances, and regulations.
(V)(G) "OPERATIONAL TEST"
3.5 Accomplish an p rational test of the equipment listed in 1.3, to verify proper operation. Operational parameters: Normal. No external leakage permitted. No unusual noise, vibration, or heat build up permitted.
3.5.1 Coordinate with Dive Locker personnel to accomplish an
operational test.
3.5.2 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.5 to the SUPERVISOR.
3.6 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 Dive Locker Point of Contact (POC):
SSP: HRMC-HM&E-23-0010 3 of 3 ITEM NO: 233-11-001
NDC Fox Email:
EM1 Oviso Email:
ETC Tucker Email:
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 233-11-002
COAR: 16 PCN: DSV4-L035
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 233-11-002
1. SCOPE:
1.1 Title: Sea Intake Strainer; replace
1.2 Location of Work:
1.2.1 Engine Room
1.3 Identification:
1.3.1 Quantity (1 EA), Port Sea Intake Strainer Assembly, Cage Code:
72922, Manufacturer Part # ARG-2500-S
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Information Book f r 60-Foot Dive Support Boat, Hull 60DS1001
3. REQUIREMENTS:
3.1 Disconnect mechanically, remove e isting and ins all new, the equipment listed in 1.3 for the port gine located in 1.2, using 2.2 for guidance and as directed by SUPERVISOR.
3.1.1 Retain fasteners for use.
3.2 Clean each fastener and rem ve di grease, debris and foreign matter leaving no injurious effec s.
3.2.1 Restore flang ma ing s rfaces exposed by strainer removals.
Repair by removing high spots, burrs, abrasions and foreign matter, where removal can e ac ished by hand tools, using 2.2 for guidance.
(V)(G) "VISUAL INSPECTION
3.3 Inspect s rainer fo ndation for structural integrity, deterioration, pitting, cracks nd are s of damage or distortion.
3.3.1 Submit one legible copy of a report, in hard copy and
electronic media, listing the results of the requirements of 3.3 to the SUPERVISOR.
(V)(G) "OPERATIONAL TEST"
3.4 Ship's Force will accomplish operational test of the duplex strainer and associated piping system under system operating pressure using approved shipboard procedure. Allowable leakage at new and disturbed joints: None.
3.4.1 Operate each strainer through five (5) complete cycles, using
2.2 for guidance. Allowable rubbing or binding: None. The Contractor shall be present to correct any discrepancies resulting from work associated with this Work Item.
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 233-11-002
3.4.2 Submit one legible copy of a report, in hard copy and
electronic media, listing the results of the requirements of 3.4 to the SUPERVISOR.
3.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 Dive Locker Point of Contact (POC):
NDC Fox Email:
Phone:
EM1 Oviso Email:
Phone:
ETC Tucker Email:
Phone:
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 245-10-001
COAR: 16 PCN: DSV4-L016
DSV4-L017
DSV4-L020
DSV4-L018
DSV4-L019
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 4 ITEM NO: 245-10-001
1. SCOPE:
1.1 Title: Shafts, Propellers, & Rudders; repair
1.2 Location of Work:
1.2.1 Underwater Hull
1.3 Identification:
1.3.1 Quantity (2 EA): Propellers
1.3.2 Quantity (2 EA): Propulsion Shaft
1.3.2.1 Quantity (2 EA): VM Dafoe trut Hub w/ Non-Metallic
Marine Bearing 3 1/8" OD x 2 1/2" ID x 10" LG
1.3.2.2 Quantity (2 EA): PYI haft Seal, model PPS 2-212-400
1.3.3 Quantity (2 EA) Rudder
1.3.3.1 Tides Type C Rudder Port Bearing, Part # RPB-C-2250-00
1.3.3.2 Tides STD Upper Rud r Bear ng, Part # URB-STD-2250-00
2. REFERENCES:
2.1 Standard Items, (FY 23, CH-3)
2.2 S9086-TX-STM-010 CH-583 Boats and Small Craft
2.3 S9245-AR-TSM-010, M ine Propeller Inspection Repair, and
Certification
2.4 T9074-AS GIB-010/2 1, R quirements for Non-destructive Testing Methods
2.5 MIL-STD-203 Non- estructive Testing Acceptance Criteria
2.6 2-8 Rev A, Sha t Strut
2.7 3-2 Rev A, Steering Schematic
2.8 S9200-A2-MMA-010, Main Propulsion System Alignment Manual for Craft of the U. S. Navy
3. REQUIREMENTS:
3.1 Disassemble, disconnect and remove each equipment listed in 1.3, using 2.2 and 2.3 for guidance.
3.1.1 Clean and polish the propeller, removing a minimum of metal, maintaining design dimensions and tolerances.
3.1.2 Inspect each part for wear and defects.
3.1.2.1 Measure and record sizes and clearances.
3.1.2.2 Include sizes, clearances, fits, and finishes for
wearing parts, seal and packing areas, and physical conditions of
SSP: HRMC-HM&E-23-0010 2 of 4 ITEM NO: 245-10-001 parts not specified for renewal.
3.1.2.3 Submit one legible copy, in hard copy or electronic
media, of a report listing results of the requirements of 3.1.2 through 3.1.2.2 to the SUPERVISOR.
3.2 Accomplish the following repairs on the equipment listed 1.3.1 using 2.2, 2.3, and 2.6 as guidance.
3.2.1 Clean and polish the propeller, removing a minimum of metal, maintaining design dimensions and tolerances.
(I)(G) "LIQUID PENETRANT INSPECTION"
3.2.2 Accomplish liquid penetrant test on the propeller listed in 1.3.1, in accordance with 2.4. The accept or reject criteria shall be in accordance with Class 2 of 2.5.
3.2.3 Balance the propeller using 2.3 as guidance.
(V)(G) "INSPECT FIT"
3.2.4 Fit the propeller hub bore to sh ft t er using prussian blue applied to the shaft taper. Obtain a it of at least 60 percent uniformly distributed contact on both the forwar and aft lands of the propeller bore.
3.2.4.1 Submit one legible cop , in hard copy or electronic
media, of a report listing resul of the requirements of 3.2.2 through 3.2.4 to the SU E VISOR.
3.3 Accomplish the following re airs o the equipment listed 1.3.2 using 2.2 and 2.7 as guidance.
3.3.1 Remove high pots, burrs abrasions, nicks, corrosion, gasket material, and for ign ma ter from exposed flanges and mating surfaces.
3.3.2 Remov rs a d high spots from exposed sliding surfaces, screw thre ds, key , an keyways.
3.3.3 Ch se and tap exposed threaded areas.
3.3.4 Handw rk and skim cut machined, sealing, aligning, mating, and gasket surface aking precautions to ensure no excessive metal removal.
3.3.5 Polish machined surfaces in way of repairs.
3.3.6 Straighten each shaft identified in 1.3.2 to within 0.002 inch total indicator reading, using 2.6 for guidance.
3.3.7 Remove and install new equipment listed in 1.3.2.1 using 2.6 for guidance.
3.4 Accomplish the following repairs on the equipment listed in 1.3.3 using 2.2 and 2.7 as guidance.
3.4.1 Remove vent and drain plugs from the rudders and stern frame.
Drain all water and preservative from within.
3.4.1.1 Collect and dispose of drained fluid (including
preservatives) in accordance with local, state and federal regulations.
SSP: HRMC-HM&E-23-0010 3 of 4 ITEM NO: 245-10-001
3.4.2 Disconnect all linkages, hoses, rams rudder stocks.
3.4.3 Remove burrs, high spots, nicks corrosion and foreign matter from wear and sealing surfaces.
3.4.4 Chase and tap exposed threads.
3.4.5 Clear and clean pockets and passages on the stern frame and rudders, free of obstructions and foreign matter.
3.4.6 Measure and record rudder post dimensions.
3.4.7 Measure and record dimensions of the through hull fittings.
3.4.8 Accomplish dye penetrant inspection of the rudder, rudder stock and attachment welds using 2.5 for accept/reject criteria.
3.4.9 Remove and inspect rudder seal, rudder bearings, rudder post, identify any damage and deterioration.
3.4.9.1 Submit one legible copy, in hard copy or electronic
media, of a report listing results of the requirements of 3.4.6 through 3.4.9 to the SUPERVISOR.
3.4.10 Fill with new, preservatives removed 3.4.1.
3.4.11 Remove and replace with new equipment li ed in 1.3.3.1 and 1.3.3.2.
3.5 Assemble, install, align and conne t he equipment listed in 1.3, fitting and installing new seals and hard are using 2.2 and 2.8 for guidance.
3.5.1 Remove and replace wit new e ipment listed in 1.3.2.2.
3.5.2 Measure and re d the inal sizes and clearances.
3.5.2.1 Submi one legible copy, in hard copy or electronic
media, of a r port i g results of the requirements of 3.5.2 to the SUPERVIS R
(V)(G) "VERIFY ALIGNMENT
3.6 Accomplis alignmen of the shaft using 2.2 and 2.8 for guidance, evaluate alignm t measurements and determine corrections required.
3.6.1 Reposit on each main propulsion engine and transmission to correct misalignment using 2.8 for guidance.
3.6.2 Measure and record final alignment readings.
3.6.3 Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.6 to the
SUPERVISOR.
(V)(G) "OPERATIONAL TEST"
3.7 Accomplish waterborne operational test of propulsion train throughout all ranges, from low to full power. No binding, irregular or excessive noise or vibration allowed.
3.7.1 Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.7 to the
SUPERVISOR.
3.8 Accomplish the requirements of 009-32 of 2.1 for each new and
SSP: HRMC-HM&E-23-0010 4 of 4 ITEM NO: 245-10-001 disturbed surface.
4. NOTES:
4.1 Dive Locker Point of Contact (POC):
NDC Fox Email:
Phone:
EM1 Oviso Email:
Phone:
ETC Tucker Email:
Phone:
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 311-21-001
COAR: 16 PCN: DSV4-L009
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 311-21-001
1. SCOPE:
1.1 Title: Generator; repair
1.2 Location of Work:
1.2.1 Engine Room Compartment
1.3 Identification:
1.3.1 Quantity (One EA): Generator, Make: Northern Lights 25kw, 440V Model# 864W3, Serial# 8642-42807C
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Information Book f r 60-Foot Dive Support Boat, Hull 60DS1001
2.3 Operators Manual, Armstrong Marine, 0FT Diver Support Boat AMI Hull #US-IAR 60 MONB111 Navsea Hull #60DS100
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009- of 2.1, for the inspection, repair, and maintenance service quiremen s of the equipment listed in 1.3, located in 1.2, using Manuf ctu Serv ce Manual, 2.2 and 2.3 for guidance.
3.2 Provide the services a qua ified Northern Lights technical representative to accom lish he fo lowing service / repairs to the equipment listed in 1 3 in a cordanc with manufacturer's instructions and or specified in th W rk It
3.2.1 Disas m e, d sconnect and remove components listed in
3.2.1.1 th ough 3. 1.4 using 2.2 and 2.3 for guidance.
3.2.1 1 Remove and replace with new, engine oil and lube oil filter.
3.2.1.2 R mo e and replace with new, generator air cleaner.
3.2.1.3 Remove and replace with new, raw water impeller.
3.2.1.4 Remove and replace with new, primary fuel filter and
secondary fuel filter element.
3.2.2 Clean and inspect each part for wear and defects, adjust, repair or replace with new as required, for the equipment listed in
1.3 using 2.2 and 2.3 for guidance.
3.2.2.1 Inspect and check V-belt and tension, adjust as needed.
3.2.2.2 Load test and service the associated batteries currently to assure the proper working condition.
3.2.2.3 Clean and inspect air cleaner, including associated
hoses, replace if required.
3.2.2.4 Inspect/check injection pump settings, maximum speed, exhaust smoke and for wear and defects.
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 311-21-001
3.2.2.5 Check valve clearances, adjust if required.
3.2.2.6 Inspect turbocharger air, lubrication and cooling lines for leaks, replace hoses, lines and gaskets if required.
3.2.2.7 Remove, clean, inspect and test injectors.
3.2.2.8 Clean and inspect all zinc electrodes for wear, allowable lost 50 percent, replace if required.
3.2.2.9 Drain, clean, inspect and refill cooling system, check for signs of leakage. Allowable leakage: None.
3.2.2.10 Drain, clean, flush, and inspect heat exchangers. Fill cooling system and check for leaks. Allowable leakage: None.
3.2.2.11 Inspect/check generator starter and alternator.
3.3 Remove and dispose of system fluids in accordance with federal, state, and local laws, codes, ordinances, and regulations.
(V)(G) "OPERATIONAL TEST"
3.4 Accomplish an operational test of the quipm nt listed in 1.3, to verify proper operation. Test shall be at a minimum of 30 continues minutes of run time. Operational parameters: Normal. No external leakage permitted. No unusual noise, vibrati n, or heat build up permitted.
3.4.1 Coordinate with Dive Locker pe onnel to accomplish an
operational test.
3.4.2 Submit one legible copy, in h d copy or approved
transferrable media, of a rep rt listing results of the requirements of 3.4 to the SUPERVISOR.
4. NOTES:
4.1 Dive Locker Point of Contact (POC):
NDC Fox Email:
Phone:
EM1 Oviso Email:
Phone:
ETC Tucker Email:
Phone:
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
AFT
SHIP: ITEM NO: 320-00-001
COAR: 16 PCN: DSV4-L036
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 1 ITEM NO: 320-00-001
1. SCOPE:
1.1 Title: Low Voltage Meters; replace
1.2 Location of Work:
1.2.1 Main Cabin
1.3 Identification:
1.3.1 Quantity: (One EA), Main 120-440 Vac Panel
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9008-JJ-BIB-010 Rev 1, Boat Information Bo k for 60-Foot Dive Support Boat, Hull 60DS1001
2.3 DOD-STD-2003, Electric Plant Installa ion S andard Methods
3. REQUIREMENTS:
3.1 Remove and replace with new 4 ea h digi al low voltage meters for panel listed in 1.3.1, located in 1.2 in 2.2 and 2.3 for guidance as directed by SUPERVISOR.
(V)(G) "OPERATIONAL TEST"
3.2 Accomplish an operational te t f each of the meter replaced in 3.1.
3.2.1 Submit one legibl copy in hard copy or electronic media, of a report listing c mplet d test results to the SUPERVISOR.
3.3 Accomplish the req ir ments 009-32 of 2.1 for each new and disturbed surface
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MA ERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 320-11-002
COAR: 16 PCN: DSV4-L038
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 320-11-002
1. SCOPE:
1.1 Title: Flood Light; replace
1.2 Location of Work:
1.2.1 Frame 20, Stbd
1.3 Identification:
1.3.1 Quantity (One EA), Aqua Signal 500W Halogen Floodlight, S/N:
9009D0830
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 Operators Manual Rev 1, Armstrong Marine 60FT Diver Support Boat AMI Hull #US-IAR 60 MONB111 Navsea Hull #60D 100
2.3 DOD-STD-2003, Electric Plant Install tion Stan ard Methods for Surface Ships and Submarines
2.4 S9086-K9-STM-000/CH-330, Lighting
2.5 S9086-KY-STM-010/CH-320, Electric P er Distribution Systems
3. REQUIREMENTS:
3.1 Disconnect electrically and ech nic ly and remove the equipment listed in 1.3 and located i 1.2 u ng 2.2 through 2.5 as guidance and as directed by Supervisor.
3.1.1 Remove ass ciated cables and cable supports.
3.1.2 Record and r in electrical hook-up data.
3.2 Install ne , equ men listed 1.3 and associated cable and cable supports usin 2.2 thro gh 2 5 and manufacturer's instructions for guidance.
3.2.1 Reconn ct equipment using hook-up data of 3.1.2 for guidance.
(V)(G) "OPERATIONAL TEST
3.3 Accomplish an operational test of the newly installed equipment using 2.2 through 2.5 and manufacturer's instructions for guidance.
3.4 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 320-11-002
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 439-11-001
COAR: 16 PCN: DSV4-L022
CMP: NONE
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 439-11-001
1. SCOPE:
1.1 Title: Backup Camera & Monitor; install
1.2 Location of Work:
1.2.1 Pilot House
1.2.2 Frame 20, Centerline
1.3 Identification:
1.3.1 Quantity (One EA), Ocean Systems Inc., Splash Cam DeckScan 20/20 FW with Cable
1.3.2 Quantity (One EA), Furuno NTSC/PAL Interface Kit for camera operation
1.3.3 Quantity (One EA), NavNet Integra ed Network System-10.4" LCD Monitor
2. REFERENCES:
2.1 Standard Items, (FY 23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Information B ok for 60-Foot Dive Support Boat, Hull 60DS1001
2.3 Operators Manual Rev 1, Armstrong rine, 60FT Diver Support Boat AMI Hull #US-IAR 60 MONB111 Navse Hull #60DS1001
2.4 MIL-STD-1310, Shipb ard onding, Grounding, and Other Techniques for Electromagnetic Compat bility and Safety
2.5 MIL-STD-2003, Ele ri Plant nstallation Standard Methods for Surface Ships and Submar es
3. REQUIREMENTS:
3.1 Obtain th services of a qualified Camera and Monitor technician for the installation and testing of the equipment listed in 1.3 and located in 1.2.
3.2 Install new each equipment listed in 1.3, located in 1.2.1 and 1.2.2, in using 2.2 through 2.5 for guidance and as directed by
SUPERVISOR.
3.2.1 Bond and ground equipment in accordance with 2.4.
3.2.2 Each electrical equipment installation shall conform to the requirement of 2.5.
(V)(G) "OPERATIONAL TEST"
3.3 Accomplish an operational test of the newly installed items listed in 1.3, using the manufacturer's manual for guidance.
3.3.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.3 to the SUPERVISOR.
3.3.2 Deliver each Technical Manual and Warranty Information to the
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 439-11-001
Dive Locker representative. Provide the name and date of the representative receiving the documents to the SUPERVISOR
3.4 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 514-31-001
COAR: 16 PCN: DSV4-L010
DSV4-L024
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 514-31-001
1.1 Title: Air Conditioning Unit; repair
1.2 Location of Work:
1.2.1 Main Cabin
1.2.2 Galley
1.2.3 Dive Equipment Room
1.3 Identification:
1.3.1 Quantity (One EA), Flagship Marine M del HVAC FM60S-V, 61K BTUs, 2100 CFM, 8.0 KW
2. REFERENCES:
2.1 Standard Items, (FY 23, CH-3)
2.2 S9008-JJ-BIB-010, Boat Informati Book for 60-Foot Dive Support Boat, Hull 60DS1001
2.3 Operators Manual Rev 1, Arm rong Mar e, 60FT Diver Support Boat AMI Hull #US-IAR 60 MONB111 Navs a H l #60D 1001
2.4 3-12 Rev C, HVAC Schematic
2.5 S9086-RW-STM-010/CH 516 ev 5, Refrigeration Systems
3. REQUIREMENTS:
3.1 Obtain a qualified rine HVAC technician for the inspection, cleaning, and ma t ance ervice requirements of the HVAC system including the quipmen lis d in 1.3, located in 1.2, using 2.2 through
2.5 for guida ce.
3.2 Accomplish he following service/repairs to the HVAC system including equipmen li ted in 1.3 in accordance with manufacturer's instructions and us g 2.2 through 2.5 as guidance.
3.2.1 Clean and Inspect equipment listed in 1.3.
3.2.1.1 Submit one legible copy, in approved transferrable
media, of a report listing results of the requirements of 3.2.1.
3.2.2 Remove all liquids, clean, and recharge unit listed in 1.3 with refrigerant coolant.
3.2.3 Clear all drain lines.
3.3 Accomplish a pressure test of the HVAC system in accordance with Paragraph 516-8.2.3 of 2.5. Allowable leakage: None.
3.3.1 Submit one legible copy, in approved transferrable media, of a report listing results of the requirements of 3.3.1.
3.4 Accomplish repair to air conditioning return plenum filter housing and grill located in 1.2.3.
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 514-31-001
(Q)(G) "OPERATIONAL TEST"
3.5 Accomplish an operational test of the HVAC system using 2.2 through
2.5 as guidance. Adjust and set switches, valves, capacity controls and automatic features using 2.3 as a guide, and bring the temperatures of the chilled water down to the required operating temperatures.
3.6 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 Dive Locker Point of Contact (POC):
NDC Fox Email:
Phone:
EM1 Oviso Email:
Phone:
ETC Tucker Email:
Phone:
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 529-21-001
COAR: 16 PCN: DSV4-L033
DSV4-L021
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 529-21-001
1. SCOPE:
1.1 Title: Bilge Pump; replace
1.2 Location of Work:
1.2.1 Engine Room
1.2.2 Equipment Room
1.2.3 Galley
1.2.4 Lazrette
1.3 Identification:
1.3.1 Quantity (4 EA), Rule/Port Supply, odel #16A, Submersible Electric Bilge Pump 3700 GPH 24VDC
2. REFERENCES:
2.1 Standard Items, (FY-23, CH-3)
2.2 S9086-T8-STM-010/CH-593, Pollution Co trol
2.3 S9008-JJ-BIB-010, Boat Information B k for 60-Foot Dive Support Boat, Hull 60DS1001
2.4 3-8 Rev B, Bilge Schematic
3. REQUIREMENTS:
3.1 Clean bilge of sp ce lis ed in 1.2.1 free of trash, debris,grease, oily liquid, and other liqu aminant prior to the initial certification, using par raph 593-3.1 and 593-3.2 of 2.2.
3.1.1 Remo e and comm rcially dispose of all liquids and wastes in accordanc with all fede al, state and local laws, codes, ordinances or regula ons.
3.1.2 Maint in each bilge to a clean, dry condition on a 7 day a week, 24 hour d y basis.
3.2 Remove and replace with new equipment listed in 1.3.1 located at 1.2 using 2.3 and 2.4 for guidance.
(V)(G) "OPERATIONAL TEST"
3.3 Accomplish an operational test of the bilge pump listed in 1.3, in the location listed in 1.2 under normal operating conditions. Allowable leakage: None.
3.3.1 Submit one legible copy, in approved transferrable media, of the operational instructions and technical data of the equipment listed in 1.3 to the SUPERVISOR.
(V)(G) "CLEAN AND DRY BILGE"
3.4 Accomplish a final detergent cleaning and drying of bilge in space listed in 1.2.1, removing trash, debris, grease, oily liquid, and other
SSP: HRMC-HM&E-23-0010 2 of 2 ITEM NO: 529-21-001 liquid contaminant from each bilge.
3.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: ITEM NO: 583-11-001
COAR: 16 PCN: DSV4-L014
CMP: NONE
PLANNER:
SSP: HRMC-HM&E-23-0010 1 of 2 ITEM NO: 583-11-001
1. SCOPE:
1.1 Title: Transfer of Boat Custody; accomplish
1.2 Location of Work: Contractor's Plant
1.3 Identification:
1.3.1 None
2. REFERENCES:
2.1 Attachment (A): Boat Custody Form
3. REQUIREMENTS:
(V)(G) "CUSTODY TURNOVER"
3.1 The Government will deliver custody of he oat to contractor facility prior to avail start and will accept cust dy of the boat at contractor facility upon satisfactory co pletion of ll contracted work.
3.1.1 Prior to turning over the boat to the contractor, the
customerand contractor shall do a precheck on all systems and equipment to the max extent possible A list of the equipment stored onboard the boat and system quipment not working shall be signed by the customer and submitted a CF
3.1.2 The…