2124404B4200RJ027_IGE.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Display Repairs Federal contract opportunity
Solicitation number
70Z08524Q39020B00
Issued by
Department of Homeland Security US Coast Guard

About this file

This document appears to be an Independent Government Cost Estimate (IGCE) for repairing 19" flat panel displays. The IGCE provides a detailed cost breakdown for materials, labor, overhead, and profit for repairing 4 units, totaling $61,204.74. The materials cost includes an "Open and Inspect Fee" of $3,059.31 per unit, and piece parts costing $9,691.88 per unit. Labor costs cover opening, inspecting, repairing, testing, and packaging the units.

The related federal contract opportunity is for "Display Repairs" and requires the vendor to be a SCIOTEQ Authorized Repair Facility. The solicitation is issued by the Department of Homeland Security US Coast Guard, with a solicitation number of 70Z08524Q39020B00.

View the file

Other files for this federal contract opportunity

Other files attached to Display Repairs, newest first.
File Type Posted
01-619-2658_RD.pdf PDF
01-620-2172_RD.pdf PDF
2124404B4200RJ027_REPAIR SPECS.doc DOC document
SOLICITATION.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

INDEPENDENT GOVERNMENT COST ESTIMATE
ITEM COST BREAK DOWN
TITLEOPEN AND INSPECT REPAIR - 19" Flat Panel, Display
ITEMNew or Obsolete 19" Flat Panel, Display
NSNNSN: 7025-01-619-2658 & 7025-01-620-2172
A. MATERIALSQUAN.U/ICOST/UNITTOTAL COST
1Open and Inspect Fee1EA$ 3,059.31$ 3,059.31
2Piece Parts per unit1EA$ 9,691.88$ 9,691.88
$ - 0
$ - 0
$ - 0
$ - 0
7025-01-619-2658, QTY 2$ - 0
7025-01-620-2172, QTY 2$ - 0
$ - 0
$ - 0
$ - 0
$ - 0
TOTAL MATERIALS$ 12,751.19
B. LABOR COSTSHRS.COST/HRTOTAL COST
1Open, Inspect, Report perUnit4$ 150.00$ 600.00
2Overhaul/Repair per Unit6$ 200.00$ 1,200.00
3Testing per Unit3$ 200.00$ 600.00
4Packaging Per Unit1$ 150.00$ 150.00
$ - 0
$ - 0
$ - 0
$ - 0
$ - 0
$ - 0
TOTAL LABOR$ 2,550.00
RATE
OVERHEAD0%TOTAL OVERHEAD$ - 0

C. TOTAL COST OF MATERIAL + LABOR + LABOR HEAD $ 15,301.19

D.G & A COST POOL 0% TOTAL G&A $ - 0

SUB TOTAL $ 15,301.19

E. PROFIT PERCENTAGE 0% TOTAL PROFIT $ - 0

F. TOTAL COST OF ONE ITEM$ 15,301.19
QUAN
G. TOTAL QUANTITY4TOTAL QUANTITY COST$ 61,204.74

This estimate was developed using generally available information on the materials, the preparers experience with this type of supply, and past procurement history when available.

TOTAL COST BASE YEAR OR ONE TIME BUY / REPAIR $ 61,204.74

TOTAL COST FOR THIS CONTRACT / PO $ 61,204.74

Randolf Aragon7/2/24
PREPARED BYDATE