This document is a comprehensive set of Special Provisions for the City of Sammamish's 2025 ADA Barrier Removal Project, detailing specifications and requirements for a public works construction contract. The project involves constructing a new sidewalk along SE 24th Street from 251st Avenue SE to the entrance of Beaver Lake Lodge, including new curb and gutter, 6-foot-wide sidewalks, low impact development features, and storm drainage system connections. The work encompasses removing and replacing damaged sidewalk panels, mitigating tree root intrusions, and upgrading non-compliant curb ramps to meet ADA accessibility standards. The contract specifies a physical completion timeline of 40 working days, with a project-specific focus on accessibility improvements and careful tree root management.
The contract includes a total bid amount with potential for partial deletion of work for specific sites, and requires detailed documentation including prevailing wage rates, insurance certifications, and performance bonds. Bidders must provide comprehensive documentation, including a breakdown of recycled materials usage, traffic control plans, and adherence to specific technical specifications for sidewalk construction, tree protection, and accessibility features. The project is funded through municipal public works resources, with specific requirements for contractor qualifications, including registration, licensing, and compliance with Washington State labor and construction regulations. Liquidated damages of $1,000 per working day will be assessed for delays beyond the specified completion date, emphasizing the project's time-sensitive nature.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 2025 ADA Barriers - Final Specs Part 1-3 (Proposal).pdf | ||
| 2025 ADA Barriers - Final Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART 4
GENERAL SPECIAL PROVISIONS
SPECIAL PROVISIONS
City of Sammamish Special Provisions 2025 ADA Barrier Removal Project May 2025
SP-1
INTRODUCTION TO THE SPECIAL PROVISIONS
(January 4, 2024 APWA GSP, Option A)
The work on this project shall be accomplished in accordance with the Standard Specifications for Road, Bridge and Municipal Construction, 2025 edition, as issued by the Washington State Department of Transportation (WSDOT) and the American Public Works Association (APWA), Washington State Chapter (hereafter “Standard Specifications”). The Standard Specifications, as modified or supplemented by these Special Provisions, all of which are made a part of the Contract Documents, shall govern all of the Work.
These Special Provisions are made up of both General Special Provisions (GSPs) from various sources, which may have project-specific fill-ins; and project-specific Special Provisions. Each Provision either supplements, modifies, or replaces the comparable Standard Specification, or is a new Provision. The deletion, amendment, alteration, or addition to any subsection or portion of the Standard Specifications is meant to pertain only to that particular portion of the section, and in no way should it be interpreted that the balance of the section does not apply.
The project-specific Special Provisions are not labeled as such. The GSPs are labeled under the headers of each GSP, with the effective date of the GSP and its source. For example:
(March 8, 2013 APWA GSP) (April 1, 2013 WSDOTGSP) (May 1, 2013 SAMMAMISH GSP) (Project-Specific Special Provision)
Also incorporated into the Contract Documents by reference are:
• Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted edition, with Washington State modifications, if any
• Standard Plans for Road, Bridge and Municipal Construction, WSDOT Manual M21-01, current edition
• Public Works Standards, City of Sammamish, current edition
Contractor shall obtain copies of these publications, at Contractor’s own expense.
SP-2
DIVISION 1
GENERAL REQUIREMENTS
DESCRIPTION OF WORK
(March 13, 1995, WSDOT GSP)
This Contract provides for the construction of a new sidewalk along SE 24th Street, from 251st Avenue SE, to the entrance of Beaver Lake Lodge. The work includes new curb & gutter, 6-foot-wide sidewalks, low impact development features, and new storm drainage conveyance system connections, in accordance with the attached Contract Plans, Provisions, and Standard Specifications.
1-01 DEFINITIONS AND TERMS
1-01.3 Definitions (January 19, 2022 APWA GSP)
Delete the heading Completion Dates and the three paragraphs that follow it, and replace them with the following:
Dates
Bid Opening Date The date on which the Contracting Agency publicly opens and reads the Bids.
Award Date The date of the formal decision of the Contracting Agency to accept the lowest responsible and responsive Bidder for the Work.
Contract Execution Date The date the Contracting Agency officially binds the Agency to the Contract.
Notice to Proceed Date The date stated in the Notice to Proceed on which the Contract time begins.
Substantial Completion Date The day the Engineer determines the Contracting Agency has full and unrestricted use and benefit of the facilities, both from the operational and safety standpoint, any remaining traffic disruptions will be rare and brief, and only minor incidental work, replacement of temporary substitute facilities, plant establishment periods, or correction or repair remains for the Physical Completion of the total Contract.
Physical Completion Date The day all of the Work is physically completed on the project. All documentation required by the Contract and required by law does not necessarily need to be furnished by the Contractor by this date.
Completion Date The day all the Work specified in the Contract is completed and all the obligations of the Contractor under the contract are fulfilled by the Contractor. All documentation required by the Contract and required by law must be furnished by the Contractor before establishment of this date.
SP-3
Final Acceptance Date The date on which the Contracting Agency accepts the Work as complete.
Supplement this Section with the following:
All references in the Standard Specifications or WSDOT General Special Provisions, to the terms “Department of Transportation”, “Washington State Transportation Commission”, “Commission”, “Secretary of Transportation”, “Secretary”, “Headquarters”, and “State Treasurer” shall be revised to read “Contracting Agency”.
All references to the terms “State” or “state” shall be revised to read “Contracting Agency” unless the reference is to an administrative agency of the State of Washington, a State statute or regulation, or the context reasonably indicates otherwise.
All references to “State Materials Laboratory” shall be revised to read “Contracting Agency designated location”.
All references to “final contract voucher certification” shall be interpreted to mean the Contracting Agency form(s) by which final payment is authorized, and final completion and acceptance granted.
Additive A supplemental unit of work or group of bid items, identified separately in the Bid Proposal, which may, at the discretion of the Contracting Agency, be awarded in addition to the base bid.
Alternate One of two or more units of work or groups of bid items, identified separately in the Bid Proposal, from which the Contracting Agency may make a choice between different methods or material of construction for performing the same work.
Business Day A business day is any day from Monday through Friday except holidays as listed in Section 1-08.5.
Contract Bond The definition in the Standard Specifications for “Contract Bond” applies to whatever bond form(s) are required by the Contract Documents, which may be a combination of a Payment Bond and a Performance Bond.
Contract Documents See definition for “Contract”.
Contract Time The period of time established by the terms and conditions of the Contract within which the Work must be physically completed.
SP-4
Notice of Award The written notice from the Contracting Agency to the successful Bidder signifying the Contracting Agency’s acceptance of the Bid Proposal.
Notice to Proceed The written notice from the Contracting Agency or Engineer to the Contractor authorizing and directing the Contractor to proceed with the Work and establishing the date on which the Contract time begins.
Traffic Both vehicular and non-vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and equestrian traffic.
1-02 BID PROCEDURES AND CONDITIONS
1-02.1 Prequalification of Bidders
(January 24, 2011 APWA GSP)
Delete this Section and replace it with the following:
1-02.1 Qualifications of Bidder (January 24, 2011 APWA GSP)
Before award of a public works contract, a bidder must meet at least the minimum qualifications of RCW 39.04.350(1) to be considered a responsible bidder and qualified to be awarded a public works project.
1-02.2 Plans and Specifications
(June 27, 2011 APWA GSP)
Delete this section and replace it with the following:
Information as to where Bid Documents can be obtained or reviewed can be found in the Call for Bids (Advertisement for Bids) for the work.
After award of the contract, plans and specifications will be issued to the Contractor at no cost as detailed below:
To Prime Contractor No. of Sets Basis of Distribution
Reduced plans (11" x 17") 3 Furnished automatically upon award.
Contract Provisions
3 Furnished automatically upon award.
SP-5
Large plans (e.g., 22" x 34") N/A Furnished only upon request.
Additional plans and Contract Provisions may be obtained by the Contractor from the source stated in the Call for Bids, at the Contractor’s own expense.
1-02.4(1) General (December 30, 2022 APWA GSP Option B)
The first sentence of the ninth paragraph, beginning with “Any prospective Bidder desiring…”, is revised to read:
Prospective Bidders desiring an explanation or interpretation of the Bid Documents, shall request the explanation or interpretation in writing by close of business 3 business days preceding the bid opening to allow a written reply to reach all prospective Bidders before the submission of their Bids.
1-02.5 Proposal Forms (July 31, 2017 APWA GSP)
The Proposal Form will identify the project and its location and describe the work. It will also list estimated quantities, units of measurement, the items of work, and the materials to be furnished at the unit bid prices. The bidder shall complete spaces on the proposal form that call for, but are not limited to, unit prices; extensions; summations; the total bid amount;
signatures; date; and, where applicable, retail sales taxes and acknowledgment of addenda;
the bidder’s name, address, telephone number, and signature; the bidder’s UDBE/DBE/M/WBE commitment, if applicable; a State of Washington Contractor’s Registration Number; and a Business License Number, if applicable. Bids shall be completed by typing or shall be printed in ink by hand, preferably in black ink. The required certifications are included as part of the Proposal Form.
The Contracting Agency reserves the right to arrange the proposal forms with alternates and additives, if such be to the advantage of the Contracting Agency. The bidder shall bid on all alternates and additives set forth in the Proposal Form unless otherwise specified.
1-02.6 Preparation of Proposal (January 4, 2024 APWA GSP 1-02.6, Option B)
Supplement the second paragraph with the following:
4. If a minimum bid amount has been established for any item, the unit or lump sum price must equal or exceed the minimum amount stated.
5. Any correction to a bid made by interlineation, alteration, or erasure, shall be initialed by the signer of the bid.
Delete the last two paragraphs, and replace them with the following:
SP-6
The Bidder shall submit with their Bid a completed Contractor Certification Wage Law Compliance form, provided by the Contracting Agency. Failure to return this certification as part of the Bid Proposal package will make this Bid Nonresponsive and ineligible for Award.
A Contractor Certification of Wage Law Compliance form is included in the Proposal Forms.
The Bidder shall make no stipulation on the Bid Form, nor qualify the bid in any manner.
A bid by a corporation shall be executed in the corporate name, by the president or a vice president (or other corporate officer accompanied by evidence of authority to sign).
A bid by a partnership shall be executed in the partnership name, and signed by a partner. A copy of the partnership agreement shall be submitted with the Bid Form if any DBE requirements are to be satisfied through such an agreement.
A bid by a joint venture shall be executed in the joint venture name and signed by a member of the joint venture. A copy of the joint venture agreement shall be submitted with the Bid Form if any DBE requirements are to be satisfied through such an agreement.
1-02.7 Bid Deposit
(March 8, 2013 APWA GSP)
Supplement this section with the following:
Bid bonds shall contain the following:
1. Contracting Agency-assigned number for the project;
2. Name of the project;
3. The Contracting Agency named as obligee;
4. The amount of the bid bond stated either as a dollar figure or as a percentage which represents five percent of the maximum bid amount that could be awarded;
5. Signature of the bidder’s officer empowered to sign official statements. The signature of the person authorized to submit the bid should agree with the signature on the bond, and the title of the person must accompany the said signature;
6. The signature of the surety’s officer empowered to sign the bond and the power of attorney.
If so stated in the Contract Provisions, bidder must use the bond form included in the Contract Provisions.
If so stated in the Contract Provisions, cash will not be accepted for a bid deposit.
1-02.9 Delivery of Proposal
(Special Provision) Supplement
SP-7
Each Proposal shall be submitted through Bidnet, with the Project Name as stated in the Invitation for Bids as the subject line, or as otherwise required in the Bid Documents, to ensure proper handling and delivery.
All other information required to be submitted with the Bid Proposal must be submitted with the Bid Proposal itself, at the time stated in the Call for Bids.
Sealed proposals that are received as required will be publicly opened and read as specified in Section 1-02.12. The Contracting Agency will not open or consider any Bid Proposal that is received after the time specified in the Call for Bids for receipt of Bid Proposals, or received in a location other than that specified in the Call for Bids. The Contracting Agency will not open or consider any “Supplemental Information” that is received after the time specified above, or received in a location other than that specified above.
If an emergency or unanticipated event interrupts normal work processes of the Contracting Agency so that Proposals cannot be received at the office designated for receipt of bids as specified in Section 1-02.12 the time specified for receipt of the Proposal will be deemed to be extended to the same time of day specified in the solicitation on the first workday on which the normal work processes of the Contracting Agency resume.
1-02.10 Withdrawing, Revising, or Supplementing Proposal
(July 23, 2015 APWA GSP)
Delete this section in its entirety, and replace it with the following:
After submitting a physical Bid Proposal to the Contracting Agency, the Bidder may withdraw, revise, or supplement it if:
1. The Bidder submits a written request signed by an authorized person and physically delivers it to the place designated for receipt of Bid Proposals, and
2. The Contracting Agency receives the request before the time set for receipt of Bid
Proposals, and
3. The revised or supplemented Bid Proposal (if any) is received by the Contracting Agency before the time set for receipt of Bid Proposals.
If the Bidder’s request to withdraw, revise, or supplement its Bid Proposal is received before the time set for receipt of Bid Proposals, the Contracting Agency will return the unopened Proposal package to the Bidder. The Bidder must then submit the revised or supplemented package in its entirety. If the Bidder does not submit a revised or supplemented package, then its bid shall be considered withdrawn.
Late revised or supplemented Bid Proposals or late withdrawal requests will be date recorded by the Contracting Agency and returned unopened. Mailed, Emailed, or faxed requests to withdraw, revise, or supplement a Bid Proposal are not acceptable.
SP-8
1-02.13 Irregular Proposals (January 4, 2024 APWA GSP)
1. A Proposal will be considered irregular and will be rejected if:
a. The Bidder is not prequalified when so required;
b. The Bidder adds provisions reserving the right to reject or accept the Award, or enter into the Contract;
c. A price per unit cannot be determined from the Bid Proposal;
d. The Proposal form is not properly executed;
e. The Bidder fails to submit or properly complete a subcontractor list (WSDOT Form
271-015), if applicable, as required in Section 1-02.6;
f. The Bidder fails to submit or properly complete a Disadvantaged Business
Enterprise Certification (WSDOT Form 272-056), if applicable, as required in Section 1-02.6;
g. The Bidder fails to submit Written Confirmations (WSDOT Form 422-031) from each DBE firm listed on the Bidder’s completed DBE Utilization Certification that they are in agreement with the bidder’s DBE participation commitment, if applicable, as required in Section 1-02.6, or if the written confirmation that is submitted fails to meet the requirements of the Special Provisions;
h. The Bidder fails to submit DBE Good Faith Effort documentation, if applicable, as required in Section 1-02.6, or if the documentation that is submitted fails to demonstrate that a Good Faith Effort to meet the Condition of Award in accordance with Section 1-07.11;
i. The Bidder fails to submit a DBE Bid Item Breakdown (WSDOT Form 272-054), if applicable, as required in Section 1-02.6, or if the documentation that is submitted fails to meet the requirements of the Special Provisions;
j. The Bid Proposal does not constitute a definite and unqualified offer to meet the material terms of the Bid invitation.
1. A Proposal may be considered irregular and may be rejected if:
a. The Proposal does not include a unit price for every Bid item;
b. Any of the unit prices are excessively unbalanced (either above or below the amount of a reasonable Bid) to the potential detriment of the Contracting Agency;
c. The authorized Proposal Form furnished by the Contracting Agency is not used or is altered;
d. The completed Proposal form contains unauthorized additions, deletions, alternate
Bids, or conditions;
e. Receipt of Addenda is not acknowledged;
f. A member of a joint venture or partnership and the joint venture or partnership submit Proposals for the same project (in such an instance, both Bids may be rejected); or
g. If Proposal form entries are not made in ink.
SP-9
1-02.14 Disqualification of Bidders (May 17, 2018 APWA GSP, Option A)
A Bidder will be deemed not responsible if the Bidder does not meet the mandatory bidder responsibility criteria in RCW 39.04.350(1), as amended.
The Contracting Agency will verify that the Bidder meets the mandatory bidder responsibility criteria in RCW 39.04.350(1). To assess bidder responsibility, the Contracting Agency reserves the right to request documentation as needed from the Bidder and third parties concerning the Bidder’s compliance with the mandatory bidder responsibility criteria.
If the Contracting Agency determines the Bidder does not meet the mandatory bidder responsibility criteria in RCW 39.04.350(1) and is therefore not a responsible Bidder, the Contracting Agency shall notify the Bidder in writing, with the reasons for its determination. If the Bidder disagrees with this determination, it may appeal the determination within two (2) business days of the Contracting Agency’s determination by presenting its appeal and any additional information to the Contracting Agency. The Contracting Agency will consider the appeal and any additional information before issuing its final determination. If the final determination affirms that the Bidder is not responsible, the Contracting Agency will not execute a contract with any other Bidder until at least two business days after the Bidder determined to be not responsible has received the Contracting Agency’s final determination.
1-02.15 Pre-Award Information (December 30, 2022 APWA GSP)
Revise this section to read:
Before awarding any contract, the Contracting Agency may require one or more of these items or actions of the apparent lowest responsible bidder:
1. A complete statement of the origin, composition, and manufacture of any or all materials to be used,
2. Samples of these materials for quality and fitness tests,
3. A progress schedule (in a form the Contracting Agency requires) showing the order of and time required for the various phases of the work,
4. A breakdown of costs assigned to any bid item,
5. Attendance at a conference with the Engineer or representatives of the Engineer,
6. Obtain, and furnish a copy of, a business license to do business in the city or county where the work is located.
7. Any other information or action taken that is deemed necessary to ensure that the bidder is the lowest responsible bidder.
1-03 AWARD AND EXECUTION OF CONTRACT
1-03.1 Consideration of Bids
SP-10
Revise the first paragraph to read:
After opening and reading proposals, the Contracting Agency will check them for correctness of extensions of the prices per unit and the total price. If a discrepancy exists between the price per unit and the extended amount of any bid item, the price per unit will control. If a minimum bid amount has been established for any item and the bidder’s unit or lump sum price is less than the minimum specified amount, the Contracting Agency will unilaterally revise the unit or lump sum price, to the minimum specified amount and recalculate the extension. The total of extensions, corrected where necessary, including sales taxes where applicable and such additives and/or alternates as selected by the Contracting Agency, will be used by the Contracting Agency for award purposes and to fix the Awarded Contract Price amount and the amount of the contract bond.
1-03.1(1) Identical Bid Totals
After opening Bids, if two or more lowest responsive Bid totals are exactly equal, then the tie-breaker will be the Bidder with an equal lowest bid, that proposed to use the highest percentage of recycled materials in the Project, per the form submitted with the Bid Proposal.
If those percentages are also exactly equal, then the tie-breaker will be determined by drawing as follows: Two or more slips of paper will be marked as follows: one marked “Winner” and the other(s) marked “unsuccessful”. The slips will be folded to make the marking unseen. The slips will be placed inside a box. One authorized representative of each Bidder shall draw a slip from the box. Bidders shall draw in alphabetic order by the name of the firm as registered with the Washington State Department of Licensing. The slips shall be unfolded and the firm with the slip marked “Winner” will be determined to be the successful Bidder and eligible for Award of the Contract. Only those Bidders who submitted a Bid total that is exactly equal to the lowest responsive Bid, and with a proposed recycled materials percentage that is exactly equal to the highest proposed recycled materials amount, are eligible to draw.
1-03.2 Award of Contract
Section 1-03.2 is supplemented with the following:
The Contract will be awarded on the basis of the total of all bid items (Contract Total). After the award, the Contracting Agency has the option of deleting work associated with the construction of Site 1 or Site 2.
The deletion of this work will be documented by a change order. The change order will not be subject to protest or negotiation. The amount of the change order price reduction shall be the sum of the amounts for the bid items.
1-03.3 Execution of Contract
SP-11
(January 4, 2024 APWA GSP Option B)
Within 3 calendar days of Award date (not including Saturdays, Sundays and Holidays), the successful Bidder shall provide the information necessary to execute the Contract to the Contracting Agency. The Bidder shall send the contact information, including the full name, email address, and phone number, for the authorized signer and bonding agent to the Contracting Agency.
Copies of the Contract Provisions, including the unsigned Form of Contract, will be available for signature by the successful bidder on the first business day following award. The number of copies to be executed by the Contractor will be determined by the Contracting Agency.
Within 10 calendar days after the award date, the successful bidder shall return the signed Contracting Agency-prepared contract, an insurance certification as required by Section 1- 07.18, a satisfactory bond as required by law and Section 1-03.4, the Transfer of Coverage form for the Construction Stormwater General Permit with sections I, III, and VIII completed when provided. Before execution of the contract by the Contracting Agency, the successful bidder shall provide any pre-award information the Contracting Agency may require under Section 1-02.15.
Until the Contracting Agency executes a contract, no proposal shall bind the Contracting Agency nor shall any work begin within the project limits or within Contracting Agency-furnished sites. The Contractor shall bear all risks for any work begun outside such areas and for any materials ordered before the contract is executed by the Contracting Agency.
If the bidder experiences circumstances beyond their control that prevents return of the contract documents within the calendar days after the award date stated above, the Contracting Agency may grant up to a maximum of 10 additional calendar days for return of the documents, provided the Contracting Agency deems the circumstances warrant it.
1-03.4 Contract Bond
(July 23, 2015 APWA GSP)
Delete the first paragraph and replace it with the following:
The successful bidder shall provide executed payment and performance bond(s) for the full contract amount. The bond may be a combined payment and performance bond; or be separate payment and performance bonds. In the case of separate payment and performance bonds, each shall be for the full contract amount. The bond(s) shall:
1. Be on Contracting Agency-furnished form(s);
2. Be signed by an approved surety (or sureties) that:
a. Is registered with the Washington State Insurance Commissioner, and
b. Appears on the current Authorized Insurance List in the State of Washington published by the Office of the Insurance Commissioner, SP-12
3. Guarantee that the Contractor will perform and comply with all obligations, duties, and conditions under the Contract, including but not limited to the duty and obligation to indemnify, defend, and protect the Contracting Agency against all losses and claims related directly or indirectly from any failure:
a. Of the Contractor (or any of the employees, subcontractors, or lower tier subcontractors of the Contractor) to faithfully perform and comply with all contract obligations, conditions, and duties, or
b. Of the Contractor (or the subcontractors or lower tier subcontractors of the Contractor) to pay all laborers, mechanics, subcontractors, lower tier subcontractors, material person, or any other person who provides supplies or provisions for carrying out the work;
4. Be conditioned upon the payment of taxes, increases, and penalties incurred on the project under titles 50, 51, and 82 RCW; and
5. Be accompanied by a power of attorney for the Surety’s officer empowered to sign the bond; and
6. Be signed by an officer of the Contractor empowered to sign official statements (sole proprietor or partner). If the Contractor is a corporation, the bond(s) must be signed by the president or vice president, unless accompanied by written proof of the authority of the individual signing the bond(s) to bind the corporation (i.e., corporate resolution, power of attorney, or a letter to such effect signed by the president or vice president).
1-03.7 Judicial Review
All decisions made by the Contracting Agency regarding the Award and execution of the Contract or Bid rejection shall be conclusive subject to the scope of judicial review permitted under Washington Law. Such review, if any, shall be timely filed in the Superior Court of the county where the Contracting Agency headquarters is located, provided that where an action is asserted against a county, RCW 36.01.050 shall control venue and jurisdiction.
1-04 SCOPE OF WORK
1-04.2 Coordination of Contract Documents, Plans, Special Provisions, Specifications, and Addenda
Revise the second paragraph to read:
Any inconsistency in the parts of the contract shall be resolved by following this order of precedence (e.g., 1 presiding over 2, 2 over 3, 3 over 4, and so forth):
1. Addenda,
2. Proposal Form,
3. Special Provisions,
4. Contract Plans,
5. Standard Specifications,
6. Contracting Agency’s Standard Plans or Details (if any), and
SP-13
7. WSDOT Standard Plans for Road, Bridge, and Municipal Construction.
1-04.4 Changes
1-04.4(1) Minor Changes (May 30, 2019 APWA GSP)
Delete the first paragraph and replace it with the following:
Payments or credits for changes amounting to $10,000 or less may be made under the Bid item “Minor Change”. At the discretion of the Contracting Agency, this procedure for Minor Changes may be used in lieu of the more formal procedure as outlined in Section 1-04.4, Changes. All “Minor Change” work will be within the scope of the Contract Work and will not change Contract Time.
1-04.6 Variation in Estimated Quantities (December 30, 2022 APWA GSP, Option B)
Revise the first paragraph to read:
Payment to the Contractor will be made only for the actual quantities of Work performed and accepted in conformance with the Contract. When the accepted quantity of Work performed under a unit item varies from the original Proposal quantity, payment will be at the unit Contract price for all Work unless the total accepted quantity of the Contract item, adjusted to exclude added or deleted amounts included in change orders accepted by both parties, increases or decreases by more than 25 percent from the original Proposal quantity, and if the total extended bid price for that item at time of award is equal to or greater than 10 percent of the total contract price at time of award. In that case, the City will initiate a change order that details the bid item(s) whose quantities have changed. The change order will provide calculations and justifications for the changed quantities and costs. The change order will be agreed upon and signed by the City and the Contractor prior to the work associated with the changed bid item quantities has begun.
If the total cost of the project exceeds the original bid amount as noted in the contract, a contract amendment to increase the total contract amount will be initiated by the City and agreed upon by the Contractor. The amendment will be in the form of a supplemental agreement.
1-05 CONTROL OF WORK
SP-14
1-05.4 Conformity With And Deviations From Plans And Stakes
Section 1-05.4 is supplemented with the following:
(March 9, 2023, WSDOT GSP, OPT4.GR1)
Contractor Surveying – ADA Features
ADA Feature Staking Requirements The Contractor shall be responsible for setting, maintaining, and resetting all alignment stakes, and grades necessary for the construction of the ADA features.
Calculations, surveying, and measuring required for setting and maintaining the necessary lines and grades shall be the Contractor's responsibility. The Contractor shall build the ADA features within the specifications in the Standard Plans and contract documents.
ADA Feature Contract Compliance The Contractor shall be responsible for completing measurements to verify all ADA features comply with the Contract in the presence of the Engineer. These measurements include the curb ramp running slope, curb ramp cross slope, sidewalk running slope, sidewalk cross slope, clear space, detectable warning, turning space, flare slope, counter slope, and ramp width.
In the case where there is conflict among ADA standards, ADA-compliant shall be defined as being consistent with PROWAG Final Rules as adopted by the USDOT.
In the case where the existing layout of the roadway, utilities, or other obstructions do not allow for ADA compliancy, the City will complete the Maximum Extent Feasible documentation.
The Maximum Extent feasible will be determined by the Engineer.
ADA Feature As-Built Measurements The Contractor shall be responsible for providing the latitude and longitude of each ADA feature as indicated on the ADA Inspection Form(s) (WSDOT Form 224-020).
The completed ADA Inspection Form(s) (WSDOT Form 224-020) shall be submitted as a Type 3 Working Drawing and transmitted to the Engineer within 30 calendar days of completing the ADA feature. After acceptance, the Contracting Agency will submit the final form(s) to the WSDOT ADA Steward.
Payment Payment will be made for the following bid item that is included in the Proposal:
ADA Features Surveying Per Lump Sum
The lump sum Contract price for "ADA Features Surveying" shall be full pay for all the Surveying Work as specified.
https://ftp.wsdot.wa.gov/public/design/projectdevelopment/gsps/word/1-05.4.OPT4.GR1
SP-15
1-05.7 Removal of Defective and Unauthorized Work
(October 1, 2005 APWA GSP)
This section is supplemented with the following:
If the Contractor fails to remedy defective or unauthorized work within the time specified in a written notice from the Engineer, or fails to perform any part of the work required by the Contract Documents, the Engineer may correct and remedy such work as may be identified in the written notice, with Contracting Agency forces or by such other means as the Contracting Agency may deem necessary.
In the instance where an ADA feature does not meet accessibility requirements or the Maximum Extent Feasible, all work to replace the non-compliant items shall be completed at no additional cost to the Contracting Agency.
If the Contractor fails to comply with a written order to remedy what the Engineer determines to be an emergency situation, the Engineer may have the defective and unauthorized work corrected immediately, have the rejected work removed and replaced, or have work the Contractor refuses to perform completed by using Contracting Agency or other forces. An emergency situation is any situation when, in the opinion of the Engineer, a delay in its remedy could be potentially unsafe, or might cause serious risk of loss or damage to the public.
Direct or indirect costs incurred by the Contracting Agency attributable to correcting and remedying defective or unauthorized work, or work the Contractor failed or refused to perform, shall be paid by the Contractor. Payment will be deducted by the Engineer from monies due, or to become due, the Contractor. Such direct and indirect costs shall include in particular, but without limitation, compensation for additional professional services required, and costs for repair and replacement of work of others destroyed or damaged by correction, removal, or replacement of the Contractor’s unauthorized work.
No adjustment in contract time or compensation will be allowed because of the delay in the performance of the work attributable to the exercise of the Contracting Agency’s rights provided by this Section.
The rights exercised under the provisions of this section shall not diminish the Contracting Agency’s right to pursue any other avenue for additional remedy or damages with respect to the Contractor’s failure to perform the work as required.
1-05.11 Final Inspection
1-05.11 Final Inspections and Operational Testing
(October 1, 2005 APWA GSP)
1-05.11(1) Substantial Completion Date
SP-16
When the Contractor considers the work to be substantially complete, the Contractor shall so notify the Engineer and request the Engineer establish the Substantial Completion Date. The Contractor’s request shall list the specific items of work that remain to be completed in order to reach physical completion. The Engineer will schedule an inspection of the work with the Contractor to determine the status of completion. The Engineer may also establish the Substantial Completion Date unilaterally.
If, after this inspection, the Engineer concurs with the Contractor that the work is substantially complete and ready for its intended use, the Engineer, by written notice to the Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer does not consider the work substantially complete and ready for its intended use, the Engineer will, by written notice, so notify the Contractor giving the reasons therefor.
Upon receipt of written notice concurring in or denying substantial completion, whichever is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized interruption, the work necessary to reach Substantial and Physical Completion. The Contractor shall provide the Engineer with a revised schedule indicating when the Contractor expects to reach substantial and physical completion of the work.
The above process shall be repeated until the Engineer establishes the Substantial Completion Date and the Contractor considers the work physically complete and ready for final inspection.
1-05.11(2) Final Inspection and Physical Completion Date
When the Contractor considers the work physically complete and ready for final inspection, the Contractor by written notice, shall request the Engineer to schedule a final inspection. The Engineer will set a date for final inspection. The Engineer and the Contractor will then make a final inspection and the Engineer will notify the Contractor in writing of all particulars in which the final inspection reveals the work incomplete or unacceptable. The Contractor shall immediately take such corrective measures as are necessary to remedy the listed deficiencies. Corrective work shall be pursued vigorously, diligently, and without interruption until physical completion of the listed deficiencies. This process will continue until the Engineer is satisfied the listed deficiencies have been corrected.
If action to correct the listed deficiencies is not initiated within 7 days after receipt of the written notice listing the deficiencies, the Engineer may, upon written notice to the Contractor, take whatever steps are necessary to correct those deficiencies pursuant to Section 1-05.7.
The Contractor will not be allowed an extension of contract time because of a delay in the performance of the work attributable to the exercise of the Engineer’s right hereunder.
Upon correction of all deficiencies, the Engineer will notify the Contractor and the Contracting Agency, in writing, of the date upon which the work was considered physically complete. That date shall constitute the Physical Completion Date of the contract, but shall not imply acceptance of the work or that all the obligations of the Contractor under the contract have been fulfilled.
1-05.11(3) Operational Testing
SP-17
It is the intent of the Contracting Agency to have at the Physical Completion Date a complete and operable system. Therefore, when the work involves the installation of machinery or other mechanical equipment; street lighting, electrical distribution or signal systems; irrigation systems; buildings; or other similar work it may be desirable for the Engineer to have the Contractor operate and test the work for a period of time after final inspection but prior to the physical completion date. Whenever items of work are listed in the Contract Provisions for operational testing they shall be fully tested under operating conditions for the time period specified to ensure their acceptability prior to the Physical Completion Date. During and following the test period, the Contractor shall correct any items of workmanship, materials, or equipment which prove faulty, or that are not in first class operating condition. Equipment, electrical controls, meters, or other devices and equipment to be tested during this period shall be tested under the observation of the Engineer, so that the Engineer may determine their suitability for the purpose for which they were installed. The Physical Completion Date cannot be established until testing and corrections have been completed to the satisfaction of the Engineer.
The costs for power, gas, labor, material, supplies, and everything else needed to successfully complete operational testing, shall be included in the unit contract prices related to the system being tested, unless specifically set forth otherwise in the proposal.
Operational and test periods, when required by the Engineer, shall not affect a manufacturer’s guaranties or warranties furnished under the terms of the contract.
Add the following new section:
1-05.12(1) One-Year Guarantee Period
The Contractor shall return to the project and repair or replace all defects in workmanship and material discovered within one year after Final Acceptance of the Work. The Contractor shall start work to remedy any such defects within 7 calendar days of receiving Contracting Agency’s written notice of a defect, and shall complete such work within the time stated in the Contracting Agency’s notice. In case of an emergency, where damage may result from delay or where loss of services may result, such corrections may be made by the Contracting Agency’s own forces or another contractor, in which case the cost of corrections shall be paid by the Contractor. In the event the Contractor does not accomplish corrections within the time specified, the work will be otherwise accomplished and the cost of same shall be paid by the Contractor.
When corrections of defects are made, the Contractor shall then be responsible for correcting all defects in workmanship and materials in the corrected work for one year after acceptance of the corrections by Contracting Agency.
This guarantee is supplemental to and does not limit or affect the requirements that the Contractor’s work comply with the requirements of the Contract or any other legal rights or remedies of the Contracting Agency.
1-05.13 Superintendents, Labor and Equipment of Contractor
SP-18
(August 14, 2013 APWA GSP)
Delete the sixth and seventh paragraphs of this section.
1-05.14 Cooperation with Other Contractors
Section 1-05.14 is supplemented with the following:
(March 13, 1995)
Other Contracts Or Other Work It is anticipated that the following work adjacent to or within the limits of this project will be performed by others during the course of this project and will require coordination of the work:
Utility Companies may choose to select their own forces or contractors to perform work on their facilities impacted by work performed as part of this Contract:
Utility Companies with facilities located within the work area are:
• Sammamish Plateau Water and Sewer District
• Puget Sound Energy
• Comcast Cable
• Verizon
• CenturyLink (Lumen)
• Williams Gas Pipelines
The Contractor shall coordinate work with the garbage and waste recycling collection contractors so that collection services to property owners are not interrupted by work for this Contract. If the Engineer determines it to be necessary, hours or work will be reduced on collection days to allow for collection services. No additional compensation will be allowed if the working hours are reduced on the days of waste and recycling collection.
Republic Service Contacts
Carla Johnson Contract Administrator Carla.Johnson2@republicservices.com
(425) 646-2533
Wendy Weiker Municipal Sales Manager WWeiker@republicservices.com
(206) 390-7630
SP-19
Rich Rinehart General Manager – Bellevue/Lynnwood RRinehart2@republicservices.com
Waste Management Contacts
Jeff McMahon Senior District Manager North Sound Phone: 425-825-0007 Mobile: 425-471-5046 E-mail: jmcmaho@wm.com
Alan Schaible District Operations Manager North Sound Phone: 425-420-1701 Mobile: 425-766-5173 E-mail: aschaibl@wm.com
1-05.15 Method of Serving Notices
Revise the second paragraph to read:
All correspondence from the Contractor shall be served and directed to the Engineer. All correspondence from the Contractor constituting any notification, notice of protest, notice of dispute, or other correspondence constituting notification required to be furnished under the Contract, must be written in paper format, hand delivered or sent via certified mail delivery service with return receipt requested to the Engineer's office. Electronic copies such as e-mails or electronically delivered copies of correspondence will not constitute such notice and will not comply with the requirements of the Contract.
Supplement this section with the following:
The contracting agency reserves the right to accept alternative methods of notice, including but not limited, to email attachments and other forms electronic notification. Specific methods shall be discussed and agreed upon at the preconstruction conference.
Add the following new section:
1-05.16 Water and Power
(October 1, 2005 APWA GSP)
The Contractor shall make necessary arrangements and shall bear the costs for power and water necessary for the performance of the work, unless the contract includes power and water as a pay item.
SP-20
1-05.18 Record Drawings
The Contractor shall maintain one set of full-size plans for Record Drawings, updated with clear and accurate, red-lined field revisions on a daily basis, and within 2 business days after receipt of information that a change in Work has occurred. The Contractor shall not conceal any work until the required information is recorded.
This Record Drawing set shall be used for this purpose alone, shall be kept separate from other Plan sheets, and shall be clearly marked as Record Drawings. These Record Drawings shall be kept on site at the Contractor’s field office, and shall be available for review by the Contracting Agency at all times. The Contractor shall bring the Record Drawings to each progress meeting for review.
The preparation and upkeep of the Record Drawings is to be the assigned responsibility of a single, experienced, and qualified individual. The quality of the Record Drawings, in terms of accuracy, clarity, and completeness, is to be adequate to allow the Contracting Agency to modify the computer-aided drafting (CAD) Contract Drawings to produce a complete set of Record Drawings for the Contracting Agency without further investigative effort by the Contracting Agency.
The Record Drawing markups shall document all changes in the Work, both concealed and visible. Items that must be shown on the markups include but are not limited to:
• Actual dimensions, arrangement, and materials used when different than shown in the Plans.
• Changes made by Change Order or Field Order.
• Changes made by the Contractor.
• Accurate locations of storm sewer, sanitary sewer, water mains and other water appurtenances, structures, conduits, light standards, vaults, width of roadways, sidewalks, landscaping areas, building footprints, channelization and pavement markings, etc. Include pipe invert elevations, top of castings (manholes, inlets, etc.).
If the Contract calls for the Contracting Agency to do all surveying and staking, the Contracting Agency will provide the elevations at the tolerances the Contracting Agency requires for the Record Drawings.
When the Contract calls for the Contractor to do the surveying/staking, the applicable tolerance limits include, but are not limited to the following:
Vertical Horizontal
As-built sanitary & storm invert and grate elevations
± 0.01 foot ± 0.01 foot
As-built monumentation ± 0.001 foot ± 0.001 foot
As-built waterlines, inverts, valves, hydrants
± 0.10 foot ± 0.10 foot
SP-21
As-built ponds/swales/water features ± 0.10 foot ± 0.10 foot
As-built buildings (fin. Floor elev.) ± 0.01 foot ± 0.10 foot
As-built gas lines, power, TV, Tel, Com ± 0.10 foot ± 0.10 foot
As-built signs, signals, etc. N/A ± 0.10 foot
Making Entries on the Record Drawings:
• Use erasable colored pencil (not ink) for all markings on the Record Drawings, conforming to the following color code:
• Additions - Red
• Deletions - Green
• Comments - Blue
• Dimensions - Graphite
• Provide the applicable reference for all entries, such as the change order number, the request for information (RFI) number, or the approved shop drawing number.
• Date all entries.
• Clearly identify all items in the entry with notes similar to those in the Contract Drawings (such as pipe symbols, centerline elevations, materials, pipe joint abbreviations, etc.).
The Contractor shall certify on the Record Drawings that said drawings are an accurate depiction of built conditions, and in conformance with the requirements detailed above. The Contractor shall submit final Record Drawings to the Contracting Agency. Contracting Agency acceptance of the Record Drawings is one of the requirements for achieving Physical Completion.
Payment will be made for the following bid item:
Record Drawings (Minimum Bid $1,000)
Lump Sum
Payment for this item will be made on a prorated monthly basis for work completed in accordance with this section up to 75% of the lump sum bid. The final 25% of the lump sum item will be paid upon submittal and approval of the completed Record Drawings set prepared in conformance with these Special Provisions.
A minimum bid amount has been entered in the Bid Proposal for this item. The Contractor must bid at least that amount.
1-06 CONTROL OF MATERIAL
1-06.2(2)B Financial Incentive
(January 4, 2024 AWPA GSP)
SP-22
Replace the first sentence of this Section with the following:
The maximum Composite Pay Factor shall be 1.00.
1-06.6 Recycled Materials
(January 4, 2016 APWA GSP)
Delete this section, including its subsections, and replace it with the following:
The Contractor shall make their best effort to utilize recycled materials in the construction of the project. Approval of such material use shall be as detailed elsewhere in the Standard Specifications.
Prior to Physical Completion the Contractor shall report the quantity of recycled materials that were utilized in the construction of the project for each of the items listed in Section 9-03.21.
The report shall include hot mix asphalt, recycled concrete aggregate, recycled glass, steel furnace slag and other recycled materials (e.g. utilization of on-site material and aggregates from concrete returned to the supplier). The Contractor’s report shall be provided on DOT form 350-075 Recycled Materials Reporting.
1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC
1-07.1 Laws to be Observed
(October 1, 2005 APWA GSP)
Supplement this section with the following:
In cases of conflict between different safety regulations, the more stringent regulation shall apply.
The Washington State Department of Labor and Industries shall be the sole and paramount administrative agency responsible for the administration of the provisions of the Washington Industrial Safety and Health Act of 1973 (WISHA).
The Contractor shall maintain at the project site office, or other well known place at the project site, all articles necessary for providing first aid to the injured. The Contractor shall establish, publish, and make known to all employees, procedures for ensuring immediate removal to a hospital, or doctor’s care, persons, including employees, who may have been injured on the project site. Employees should not be permitted to work on the project site before the Contractor has established and made known procedures for removal of injured persons to a hospital or a doctor’s care.
The Contractor shall have sole responsibility for the safety, efficiency, and adequacy of the Contractor’s plant, appliances, and methods, and for any damage or injury resulting from their failure, or improper maintenance, use, or operation.