3-9-24 QA M001.docx

DOCX document 16 KB Posted

Attached to
Upgrade Sewer Lines Federal contract opportunity
Solicitation number
20245201009
Issued by
International Boundary and Water Commission U.S.-Mexico

About this file

This document contains a federal contract opportunity solicitation for upgrading sewer lines. The solicitation is seeking quotes from small businesses only to update the sewer lines for the Falcon Field Office of the International Boundary and Water Commission by replacing all internal sewer piping from the highest to lowest points inside the building with PVC piping. Quotes are due by March 22, 2024 at 3:00 pm MST and shall include responses for all contract line items (CLINs) as specified in the attached CLIN structure. The award will be made to the lowest price technically acceptable offeror considering technical acceptability, technical approach, and past performance. A site visit is recommended and may be arranged by contacting the specified individual. The solicitation also includes an attached statement of work outlining the project requirements and specifications.

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Sewer Lines, newest first.
File Type Posted
Falcon PP Sewer lines and Bathroom Facilities.pdf PDF
PWS-FY24-Falcon Sewer Lines Upgrade Project Rev1 ED 02_06_2024.pdf PDF
Falcon Bathroom Facilities.pdf PDF
Wage Determination.pdf PDF
Falcon PP Sewer Lines Project.pdf PDF
CLIN Structure.docx DOCX document
Falcon Sewer Lines System .pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A - 20245201009 Sewer Lines Modification 001 3-9-24

1. Remove and Replace 6 (six) Standards Toilets with Wall Dividers What type of toilets are you requesting?

flush toilets with dividers for the main floor (Men & Women) and machine shop restroom.

2. Remove and Replace Alcove Shower Panel Kit What is the new size of shower panel kit needed?

The shower trim will include all the fixtures and size should be similar or a little bit bigger.

3. Remove and Replace Single Stainless-Steel Sink Is this the stainless-steel sink in the machine shop area, telephone room or both ?

Only the machine shop sink should be single bowl stainless steel with all the fixtures.

4. Provide and Install New Sewer Piping Lines System in the Facility Confirm that you want to replace all the sewer piping from INSIDE the building from the highest point to the lowest inside the building.

Yes, only the sewer pipes inside the building with all the accessories elbows, Coupland’s, cleaners, etc.

5. Do you want to replace any water lines…perhaps those that provide water to the toilets and sinks?

Water Lines stay the same that should be in another project soon.

6. The sewer line that is located outside of the building to lift station….this is also part of the main sewer line but was NOT mentioned in the project requirements section.

Outside the building Sewer Lines stay the same and should be in another project soon.

7. What of including professional engineering services to guide with plumbing scenarios such as penetrating concrete walls, floors and ceiling. In addition to providing specs for the type of pipe hanger, steal supports and other designed/specification needs.

None, IBWC doesn’t require certified drawings stamped by PE.

8. Is there an inhouse engineer with the International Boudary and Water Comission staff that can provide direction or should one be included with our cost?

N/A

9. All new plumbing is expected to be of high-quality grade cast iron, do I need to include painting of the cast iron?

The project requires PVC piping schedule 40