QAs 2-13-24.docx
DOCX document 38 KB Posted
- Attached to
- Generator Federal contract opportunity
- Solicitation number
- 20245201003
About this file
This document contains a request for quote for generator services and related questions and answers. The International Boundary and Water Commission, United States Section requires a generator to be installed at the Falcon Field Office in Falcon Heights, Texas by April 30, 2024. The solicitation number is 20245201003 and is set aside for small businesses only. Offerors should quote services as outlined in the attached statement of work and CLIN structure. Site visits are recommended by February 12th and quotes are due by February 20th. The award will be made to the lowest price technically acceptable offeror.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| GENERAL ONE LINE 480 Falcon PP-01-02 rev2.pdf | ||
| Generator Switchgear images.pdf | ||
| 480 Volts Switchgear.pdf | ||
| Updated PWS FY24 Falcon PP Emergency Generator Project ED.pdf | ||
| PWS FY24 Falcon PP Emergency Generator Project ED.pdf | ||
| CLIN Structure.docx | DOCX document | |
| Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JPEC Services LLC
TECL 28193
1) Are there any concrete areas in the facility that cannot be core drilled to route new conduit
NO
2) Are there any concrete areas in the facility that cannot be drilled into to place concrete anchors less than ½” in size. NO
3) What are scanning requirements to core drill any concrete areas in facility to avoid structural steel. At this point NONE
4) PWS lists 300 Gallon Tank & 660 Gallon tank. The tank size is determined from the desired run time at 100% load. Approximately 524 Gallons of fuel will provide the 300KW generator with 24 hour run time at 100% load. Will a 524 Gallon tank be acceptable Yes
5) Will the contractor be responsible for initially filling the generator will fuel. Yes, for testing purposes
6) Are there any weight limitations of the platform in front of transformers and new generator location. NO restrictions, the platform can support a big crane.
7) Can the facility overhead crane or exterior platform trolley crane be utilized by contractor or government personnel to aide in setting generator in the event of weight limitations on platform preventing mobile crane usage. If the Contractor needed for any reason Powe Plant provide the Operator.
8) Is annunciator desired to monitor generator. If the Generators has an Annunciator will be enough nor modifications are required on current Annunciator system
9) If annunciator is desired would it be located in the control room. Not Required
10) Will generator remote (start/stop) wires terminate to PLC inside control room or Switchgear>Switchgear
11) What is the process to schedule any necessary power outages to land generator power feeders or accessory circuits. Power Plant personnel will be responsible to schedule any outages to install or test the Generator
12) PWS calls for arc flash study analysis. Generators are particularly difficult because they have very low fault current capability. With standard 10X Inst trip breakers, they almost never make it into the INST trip region, and thus you have high Cal values because of the long time component. Programmable breakers can over come this because you can adjust the INST range. If being on generator is just a 'once in while' event, like a power outage we typically recommend to arc flash label "Live Work Prohibited while supplied from generator". Would labeling the generator & switchgear with “Live Work Prohibited while supplied from generator” That works for this project and equipment.
13) Will the main power tie into the switchgear need to be performed with switchgear energized.
Power Plant personnel will be responsible to schedule any outages to install or test the Generator
14) Can restrooms in facility be used by contractor or will onsite portable restroom be required Portable Restroom will be required for this project.
15) Can the government provide any As Built / manufacturer documents detailing main switchgear installation. Yes, Falcon Power Plant provide the As built for the switchgear project
File details come from the government source that posted it. Updated .