This is a pre-solicitation notice for Davis Barracks Facility Maintenance services at West Point, New York. The notice seeks capability information from potential sources to determine whether the requirement can be set aside for an 8(a) small business. Interested parties are requested to provide company and point of contact details, small business status, experience on similar requirements as a prime or subcontractor, pricing and delivery information, and recommendations to improve the approach. Responses are due within 30 days and will be used for market research, with no commitment to issue a solicitation. The anticipated NAICS code is 561210 for facilities support services.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
Davis Barracks Facility Maintenance Services
U.S. Military Academy West Point, New York
22 NOV 2022
lakenia.m.brown.civ Draft
Table of Contents
INTRODUCTION
Background Objectives Climate Conditions
1.4 Facility Access
1.5 Traffic Flow
1.6 Drainage
1.7 Restoration of Landscape Damage
1.8 Dust Suppression
2.0 REQUIREMENTS
2.1 Description of Services
2.1.1 Non-Personal Services
2.1.2 General Information
2.1.3 Place of Performance and Hours of Operation
2.1.4 Federal Holidays
2.1.5 Travel/Temporary Duty
2.1.6 Emergency Services
2.1.7 Contract Administration and management
2.1.8 COR/ACOR Functions
2.1.9 Quality Control (QC)
2.1.10 Subcontract Management
2.1.11 Contractor Employees
2.1.12 Business Relations
2.2 Work Management
2.2.1 Coordination
2.2.2 General Fund Enterprise Business System (GFEBS)
2.3 As-Builts and Geospatial Information System (GIS)
2.3.1 Maintain As-Builts
2.3.2 Real Property Records Updates
2.3.3 GIS
2.3.4 GIS Support Services
2.3.5 GIS Files
2.3.6 Other Documents
2.4 Historic Property or Archaeological Site
2.4.1 Repair and Replacement
2.5 Special Requirements
2.5.1 Security
2.5.2 Security Training
2.5.3 Safety
2.5.4 Training, Physical Requirements, or other Expertise Required
2.5.5 Environmental Requirements
2.5.6 Contingency Plans
2.6 Job Order Contract (JOC) Quality Assurance (QA)/inspection Support
2.6.1 Project Support
3.0 PERFORMANCE REQUIREMENTS AND STANDARDS
3.1 High Level Objectives (HLO)
3.1.1 Performance Task Requirements, Standards and Acceptable Quality Levels (AQLs)
3.2 Transition
3.3 Contractor Manpower Reporting Application (CMRA)
3.3.1 Reporting Labor Hours
4.0 PERFORMANCE REQUIREMENTS SUMMARY (PRS) MATRIX
4.1 Quality Assurance
4.2 Quality Control Plan (QCP)
5.0 COMMON LEVELS OF SERVICE (CLS)
6.0 DELIVERABLES
7.0 RELATED DOCUMENTS
7.1 Definitions and Acronyms
7.1.1 Definitions
7.1.2 Acronyms
7.2 Applicable Directives, Publications
7.3 Technical Exhibit (TE)
7.4 Government-Furnished Material (GFM)/Property (GFP)/Equipment (GFE)
7.4.1 Utilities
7.3 Contractor-Furnished Material (CFM)/Property (CFP)/Equipment (CFE)
7.5.1 Contractor-Furnished Material and Responsibilities
7.5.2 Contractor-Furnished Items
7.5.3. Contractor Facilities
7.6 U.S. Department of Labor (DOL) Wage Determination (WD)
1.0 Introduction. This is a non-personal services contract to provide Facility Maintenance Services at the U.S. Military Academy Davis Barracks, West Point, New York
The Government will not exercise any supervision or control over the contract service providers. The Contractor shall perform to the standards specified in this Performance Work Statement (PWS). Contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government. The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary as defined in this PWS.
Background. Davis Barracks is used to house Cadets attending the United States
Military Academy at West Point. It is located along the Hudson River in the state of New York and consists of 1 structure sitting approximately 1 acre of land. West Point has a population base that consists of military, Government civilian, and Contactor personnel, as well as resident family members.
Objectives. The Contractor shall ensure all work accomplished in the performance of this PWS meets all applicable Federal, State, and local laws, regulations, and directives to include, but not limited to, the publications in Section 7, Related Documents
The Contractor shall compile historical data, prepare required reports, and submit all information as specified by the Deliverables presented in the contract. The Contractor shall ensure all work in support of mission requirements tendered to the Government for acceptance conform to the measurable performance standards of quality, timeliness, and quantity specified in the PWS of this contract.
The intent is to establish work requirements that are performance-based and results-oriented. The Contractor shall determine the best and most cost-effective ways to fulfill FACILITY MAINTENANCE and their component needs, emphasizing innovation and commercial best practices.
Climatic Conditions. The average annual rainfall is 47 inches; with the wettest months being May-August. The average annual snowfall is 39 inches, with snowfall expected during the period of November- April. The average frost-free period (growing season) during the year is about 180 days. The first killing frost may be expected about November and the last killing frost generally occurs in May. The average annual maximum and minimum temperatures are approximately 83 degrees and 17 degrees Fahrenheit respectively. Monthly normal temperatures ranged from a low of 22 degrees in the month of February to a high of 83 degrees in the month of July. Summer temperatures often reach 90 degrees Fahrenheit, while sub-freezing weather is common during the winter months.
1.4 Facility Access. The Contractor shall ensure access to all fire detection and suppression systems in case of emergencies or for other Fire Department purposes. The Contractor shall inform the Fire Department point-of-contact (POC), prior to outages that will impact the function of the system, special problems, or circumstances, which require.
Fire Department inspection. The Fire Department will reset alarm systems to operational status.
1.5 Traffic Flow. The Contractor shall maintain the free flow of traffic during surfaced area maintenance. The Contractor shall notify the Contracting Officer (KO), in writing, a minimum of fourteen (14) calendar days in advance of any scheduled closure of streets.
Emergency road closures shall be coordinated with the Contracting Officer Representative (COR) or Alternate Contracting Officer Representative (ACOR).
1.6 Drainage. Maintenance work performed under this contract shall not impede drainage.
1.7 Restoration of Landscape Damage. Trees or other landscape features damaged by the Contractor's operations shall be restored at no additional cost to the Government. The COR/ACOR will decide the method of restoration for trees or whether damaged trees will be removed.
1.8 Dust Suppression. The Contractor shall perform dust suppression as directed by the
COR/ACOR.
2.0 Requirements.
2.1 Description of Services. See Section 5.0 for the specific CLS or Functional Area (FA).
2.1.1 Non-Personal Services. The personnel rendering the services are not subject;
either by the contract's terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees. Non-personal service contracts are authorized by the Government in accordance with (IAW) Federal Acquisition Regulation (FAR) Subpart 37.104, under general contracting authority, and do not require specific statutory authorization.
2.1.2 General Information.
2.1.2.1 Period of Performance (POP). The POP will consist of Base year plus 4 option years. The POP will be established upon award.
2.1.3 Place of Performance and Hours of Operation.
2.1.3.1 Place of Performance. The work to be performed under this contract will be performed at U.S. Military Academy Bldg. #755 Davis Barracks West Point, New York.
2.1.3.2 Hours of Operation. The Government's regular (normal) hours are from 0700 - 1600 hours, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall conduct business during regular hours.
2.1.4 Federal Holidays. The Contractor's performance shall not be required on the Federal public holidays listed below. Holidays occurring on weekends will be observed as directed by the Federal calendar (5 U.S.C. 6103).
New Year's Day Martin Luther King Jr.'s Birthday President's Day Memorial Day Juneteenth
Independence Day Labor Day Columbus Day Veteran's Day Thanksgiving Day Christmas Day
2.1.4.1 The Contractor shall provide emergency personnel support within 2 hours of notification of an emergency by COR. Contractor personnel shall not be scheduled for overtime work unless notified of an emergency.
2.1.4.2 Installation Closures. When an unforeseen installation closure occurs on a regularly scheduled day of work, the Contractor shall:
a. Reschedule the work to be performed the following day unless the following day is a Saturday, Sunday, a legal public holiday, and when routine work is not scheduled for that day; or
b. Reschedule the work on any day mutually satisfactory.
2.1.4.3 Inclement Weather Delay. If the Contractor determines unsafe weather conditions for continued operations, then the Contractor shall notify the KO if inclement weather suspends operations within 2 hours. The Contractor shall resume operations with KO approval.
2.1.5 Travel/Temporary Duty. N/A
2.1.6 Emergency Services. N/A
2.1.6.1 The Contractor or their employees shall immediately notify their supervisor of any accident requiring emergency medical treatment. The Contractor shall notify the KO or COR/ACOR immediately, not later than (NLT) two (2) hours of the incident.
2.1.6.2 The Contractor shall be responsible for the emergency medical treatment services for Contractor personnel.
2.1.7 Contract Administration and management.
2.1.7.1 Post Award Conference. The Contractor shall attend the post award conference convened by the contracting activity or contract administration office IAW FAR Subpart
42.5. The written minutes will be distributed within five (5) workdays after the meeting. If the Contractor does not concur with any portion of the minutes, recorded by the Government, the non-concurrence shall be provided in writing to the KO within two (2) calendar days following receipt of the minutes.
2.1.7.2 Notwithstanding the Contractor's responsibility for total management during the performance of this contract, the administration of the contract requires maximum coordination and cooperation between the Government and the Contractor.
2.1.7.3 The following provides the roles and their respective authority during the performance of the contract:
2.1.7.3.1 Contracting Officer (KO). The KO is the only person authorized to direct changes in any of the requirements under this contract, and, notwithstanding any provisions contained elsewhere in this contract, said authority remains solely with the KO. In the event the Contractor makes any change at the direction of any person other than the KO, the change shall be considered to have been made without authority and solely at the risk of the Contractor. All contract administration will be affected by the KO.
Communications pertaining to contractual administrative matters shall be addressed to the KO. No changes in or deviation from the terms and conditions shall be affected, without a written modification to the contract, executed by the KO authorizing such changes. The KO will approve all submittals and plans required in this PWS.
2.1.7.3.2 Contracting Officer's Representative (COR). The KO will appoint a COR during the performance of this contract. Additional Government personnel may be assigned to assist in contract oversight IAW AR 70-13, Management and Oversight of Service Acquisitions. Other surveillance personnel may be designated as COR or ACOR, and shall be trained and appointed IAW DoDI 5000.72, DoD Standard for Contracting Officer's Representative (COR) Certification and DFARS 201.602-2. The ACOR will serve as on-site representatives of the COR in performance of actual contract surveillance, if they meet all COR training, experience requirements, and are appointed by the KO as an ACOR. The COR/ACOR will aid in identification and resolution of problems, conflicts in priority, subtask requirement definitions, and other operations type problems. The COR/ACOR will perform IAW the responsibilities and duties identified in the appointment letter.
2.1.7.3.2.1 COR Authority. A letter of designation will be issued to the COR/ACOR by the KO. A copy of the letter will be sent to the Contractor. The letter of designation states the responsibilities and limitations of the COR/ACOR, especially regarding changes in cost, price estimates, or changes in delivery dates. The COR/ACOR is not authorized to change any of the terms and conditions regarding cost, quantity, or schedule of the resulting order.
2.1.7.3.3. The Contractor shall not in any way represent the United States (U.S.)
Government, or that it has the authority to contract or procure supplies for the account of the United States of America (USA).
2.1.8 COR/ACOR Functions. The COR/ACOR monitors all technical aspects of the contract and assists in contract administration. The COR/ACOR is authorized to perform the following functions: assure the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance;
maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements; monitor, document, and report Contractor's performance and notify both the KO and Contractor of any deficiencies; coordinate availability of Government-Furnished Property, and coordinate site entry of Contractor personnel.
2.1.9 Quality Control (QC). Quality Control is the responsibility of the Contractor. The Contractor shall provide a Quality Control Plan (QCP) five (5) business days before contract start. The Contractor shall provide and maintain a QCP that is acceptable to the KO. Changes to the Contractor's QCP shall be submitted to the KO for review and approval within five (5) business days prior to implementation.
2.1.9.1 N/A
2.1.10 Subcontract Management Contractor Employees.
2.1.11.1 Key Personnel.
2.1.11.1.1 The Contractor shall provide a Program Manager who is responsible for the performance of the work. The Program Manager shall have full authority to act for the Contractor on all contract matters relating to daily operation of the contract. The name of the Program Manager shall be provided by the Contractor to the KO. The Program Manager shall be available between 0700 - 1600 hours, Monday through Friday except Federal holidays or when the Government facility is closed for administrative reasons.
Contractor personnel performing work under this contract shall have and maintain a favorable National Agency Check at time of the contract start date and for the life of the contract. The Program Manager and any individuals designated as key personnel shall be able to understand, speak, read, and write the English language.
2.1.11.1.2 Certain administrative personnel will require a Common Access Card (CAC) to access Government systems. CAC permits installation access to all contract employees. These persons shall have at a minimum, a favorable National Agency Check
(NAC).
2.1.11.1.3 All Contractor employees shall be legal U.S. residents. The Contractor shall immediately remove any employee that is not a legal U.S. resident. The Contractor personnel shall be able to communicate clearly in the English language.
2.1.11.1.4 Qualification Standards. The Contractor shall inspect, repair, and maintain systems and components associated with facility listed in real property records as required throughout this contract utilizing properly trained, skilled, and qualified employees or subcontractor personnel. The Contractor shall provide objective evidence of key personnel qualifications and years of experience to the KO for review and acceptance.
2.1.11.1.5 Contractor Identification. The Contractor shall ensure all personnel be identified as a Contractor to distinguish themselves (e.g., badge, company logo, or uniform) from Government employees. The Contractor shall ensure all correspondence and reports produced are marked as Contractor products or that Contractor participation is disclosed.
2.1.11.1.6 Standards of Conduct. Contractor personnel's conduct shall not reflect discredit upon the Government. The Contractor shall ensure all personnel present a professional appearance while working on the Government installation. The Contractor's employees shall observe and comply with all local policies and procedures concerning fire, safety, environmental protection, sanitation, security, and possession of firearms or other lethal or illegal weapons or substance. The Contractor shall ensure all Contractor employees, providing services under this contract, conduct themselves and perform services in a professional, safe, and responsible manner. The Contractor shall remove, from the job site, any employee for reasons of misconduct or security. The Contractor shall ensure employee conduct complies with 41 USC 423, Procurement Integrity. The Contractor shall also ensure that no Contractor employees conduct political related activities or events on the installation.
2.1.11.1.7 Contractor Hiring Restrictions. The Contractor shall not hire or sub-contract with off duty or former Government employees whose employment would result in a conflict with AR 600-50, Standards of Conduct.
2.1.11.1.8 Organizational Conflict of Interest (OCI).
2.1.12 Business Relations. The Contractor shall successfully integrate and coordinate all activity needed to execute the requirement of this PWS. The Contractor shall manage the timeliness, completeness, and quality of problem identification to a degree acceptable to the Government. The Contractor shall provide to the COR/ACOR corrective action plans, timely identification of issues, and effective management of subcontractors within 2 days or at a mutually agreed upon date. The Contractor shall ensure customer satisfaction and professional and ethical behavior of all Contractor personnel.
2.2 Work Management. Applicable only for CLS 411.
2.2.1 Coordination. The Contractor shall schedule and coordinate with the COR/ACOR to minimize disruptions to the facility mission.
2.2.2 General Fund Enterprise Business System (GFEBS). N/A
2.2.2.1 GFEBS Certification. N/A
2.2.2.2 Preventive Maintenance Orders (PMO). The Contractor shall respond to and complete scheduled PMO work within one (1) week.
2.2.2.3 Operations Work Orders (OWO). The Contractor shall respond to, and complete individual tasks related to OWOs. An OWO is recurring maintenance.
2.2.2.4 GFEBS Support. N/A
2.2.2.4.1 Database Tasks/Requirements. N/A
2.3 As-Build's and Geospatial Information System (GIS). N/A
2.4
2.4.1 Maintain As-Build's. The Contractor shall maintain as-built drawings. The maps to be provided are the following: Heating & Cooling System, Installation Grounds, and Nature Trails System. Utility repairs, component replacements, modifications, alterations, and additions to all systems and components shall be electronically redlined as well as on the hard copy maps upon completion of work. The Contractor shall redline annotate all components replaced during the period of the contract and annotate all items removed from service.
2.4.1.1 Support. Hard copy markups and electronic redlines shall be delivered to the COR/ACOR at the completion of each major project as identified by the COR/ACOR or, at a minimum, at the end of each contract-year quarterly cycle. The changes shall be integrated into the master data set of GIS, maintained by the DPW, printed, and returned to the Contractor as a revision of the Contractor information set. The Contractor shall validate all maps for accuracy and content. The Contractor shall be responsible for provision of all computer hardware as required to prepare, supervise, and record redline drawings using Intergraph™ GIS software, which the DPW will provide.
2.4.1.2 Training. N/A
2.4.2 Real Property Records Updates. When the Contractor is provided plans or drawings as part of an OMO or PWO, the Contractor shall be responsible for providing two (2) copies of marked up red lines drawings reflecting the changes, to the COR/ACOR. The Contractor shall submit these drawings prior to closing out the OMO or PWO.
2.4.3 GIS. N/A
2.4.4 GIS Support Services. N/A
2.4.5 GIS Files. N/A
2.4.6 Other Documents. The Contractor shall update and maintain other documents, which include the following: N/A
2.5 Historic Property or Archaeological Site. Historic properties and archaeological sites are subject to the provisions of the National Historic Preservation Act (NHPA). The Contractor shall maintain the historic properties on the installation IAW the NHPA, 54 United States Code (U.S.C) § 300101, National Preservation; 36 Code of Federal Regulations (CFR) Part 800, Advisory Council on Historic Preservation; and United Facilities Guide Specifications (UFGS). The Contractor shall comply with all applicable Federal historical structure and archeological laws. Location maps can be found at the local DPW.
2.5.1 Repair and Replacement. The Contractor shall report damages to the COR/ACOR within 2 hours. The Contractor shall repair or replace parts with products similar in appearance to the original. Repairs, renovation, or replacement to historic buildings must be approved by the KO. The Contractor shall coordinate work through the Cultural Resources Manager. The Contractor shall comply with the appropriate provisions and stipulations of the Secretary of Interior's "Standards for Rehabilitation and Guidelines for Rehabilitating Historic Buildings" (Revised 1983) Location maps are available at the DPW.
2.6 Special Requirements.
2.6.1 Security.
2.6.1.1 Access and General Protection/Security Policy and Procedures. The Contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and local security policies and procedures. The Contractor workforce shall comply with all personal identity verification (PIV) requirements as directed by Department of Defense (DOD), Headquarters Department of the Army (HQDA), and local policy. The COR/ACOR will request changes in Contractor security matters or processes if the Force Protection Condition (FPCON) at any individual facility or installation changes.
2.6.1.2 Motor V e hi c l e O pe rat o r s. Contractor’s personnel, w hos e t as k s i n vo l ve operation of any vehicles, shall possess a valid driver's license, certificates, and permits applicable for the type and class of vehicle being operated.
2.6.1.3 Contractor V e h i c l e R e g i s t r a t i o n. The C o n t r a c t o r s h a l l r e g i s t e r a l l Contractor- owned or operated vehicles and trailers operating on the installation within 10 working days of contract start date. The Contractor shall complete all applications with the Provost Marshal Vehicle Registration section located in Building 616. Evidence of vehicle ownership and vehicle liability insurance must be presented upon application of vehicle registration.
2.6.1.4 The Contractor shall provide all information required for background checks to meet installation access requirements, to be accomplished by the installation Provost Marshall Office, Director of Emergency Services, or Security Office.
2.6.1.5 Physical Security. The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use. The Contractor shall maintain a physical security checklist or log (e.g., Standard Form (SF) 701, Activity Security Checklist), which will be available to the COR/ACOR, NL T the tenth (10th) of each month, following the month of surveillance. The Contractor shall secure Government facilities, equipment, and materials at the close of each work period.
The Contractor will be provided a government furnished on-site staging area for necessary equipment and materials. The Contractor shall secure the area at the close of each work period. The Contractor shall be solely responsible for any loss or damage of equipment and material. The Contractor shall ensure debris of any type will be disposed of according to local policies and directives.
2.6.2 Security Training.
2.6.2.1 iWATCH Training. The Contractor shall brief the local iWATCH program (training standards provided by the RA's Anti-Terrorism Officer (ATO)) to all the Contractor's employees and associated subcontractors. This training is used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR/ACOR. The Contractor shall complete the training within thirty (30) calendar days of contract award and within five (5) calendar days of new employees commencing performance with the results reported to the COR/ACOR NLT thirty (30) calendar days after contract award.
2.6.3 Safety. The Contractor shall safeguard and maintain all Government and Contractor property, as well as provide for the safety and well-being of personnel employed under this contract. The Contractor shall comply with AR 385-10, The Army Safety Program.
2.6.3.1 Safety Plan. The Contractor shall develop and implement a safety program for its employees. The Contractor shall submit the Safety Plan to the KO for review and acceptance within ten (10) days of commencement of work. Revisions shall be submitted five
(5) calendar days prior to the effective date of change.
2.6.3.2 Occupational Safety and Health. The Contractor shall comply with the Occupational Safety and Health Administration (OSHA) standards. The Contractor shall comply with all applicable Federal, State, and local laws, regulations, and directives.
2.6.4 Training, Physical Requirements, or other Expertise Required.
2.6.4.1 The Contractor shall ensure all Contractor's employees and associated subcontractors are certified or licensed in the specific areas required by the State of New York. The Contractor shall ensure employees are certified or licensed in the appropriate Environmental Protection Agency (EPA) areas required. The Contractor shall ensure all required documentation of certification or licensure for Contractor personnel are filed with the COR/ACOR within twenty-four (24) hours prior to employees commencing performance.
2.6.5 Environmental Requirements.
2.6.5.1 Green Procurement. Section 6002 of the Resource Conservation and Recovery Act of 1976 (RCRA) requires the use of recycled and recovered products identified in the EPA's Comprehensive Procurement Guidelines.
2.6.5.2 The Contractor shall use these recycled or recovered products unless they cannot be procured within a reasonable period not to exceed seven (7) calendar days; at prices not to exceed five (5) percent of prevailing rates; or the product(s) does not meet technical or performance standards. EPA Guidelines are the minimum requirement. The Contractor shall use materials and products commonly used in industry. The Contractor shall maintain records and submit an annual report to the COR/ACOR, along with the annual certification required by FAR 52.223-9 (Certification and Estimate of Percentage of Recovered Material Content for EPA Designated Items), upon completion of the base year and each option year.
2.6.5.3 Environmental Compliance. The Contractor shall comply with all Federal, State, local, and installation environmental laws, rules, plans, and policies. The Contractor shall use and store all materials, chemicals, and equipment used in the performance of services on the installation IAW with industry standards, local, State and Federal laws, and according to manufactures' recommendations. The Contractor shall be financially responsible for all fines and associated costs for hazardous waste management, transportation, and disposal of waste due to the Contractor's non-compliance. The Contractor shall submit Safety Data Sheets (SOS) for review on all materials, five (5) days before delivery of the material, to the COR/ACOR. The Contractor shall provide upon request from the COR/ACOR all required data to meet environmental-mandated reporting requirements (e.g., air emission data, hazardous material storage/usage, herbicide/pesticide usage, solid/hazardous waste generation). The Contractor shall provide data to meet reporting deadlines and during compliance inspections upon request from the COR/ACOR.
2.6.5.4 Spill Plan. The Contractor shall notify the COR/ACOR within one (1) hour, if the Contractor spills or releases any hazardous substances, i.e., substances listed in 40 CFR 302, Designation, Reportable Quantities, and Notification. The Contractor shall submit a Spill Plan to the KO for approval within thirty (30) days of contract award IAW Spill Prevention Control and Countermeasure Plan.
2.6.6 Contingency Plans.
2.6.6.1 General. The Contractor shall establish, maintain, and implement contingency plans for mobilization, disaster, and labor dispute contingencies. The plans shall assume no Government support to the Contractor workforce. The Contractor shall, within thirty
(30) days of contract award, designate in writing a single contact Designated Contingency Coordinator (DCC) within the Contractor's organization. The DCC shall participate and coordinate with the installation contingency and mobilization planning activities. The DCC shall participate in the installation mobilization planning and execution conferences; and shall modify and maintain appropriate Contractor contingency plans to compliment or enhance corresponding installation plans. The Contractor shall submit all plans to the KO for approval.
2.6.6.2 Mobilization Contingency Plan. This plan shall establish procedures, personnel, and means of maintaining or expanding performance of all PWS requirements in the event of rapid deployment or sudden build-up of military forces. The Contractor shall submit a Mobilization Contingency Plan within (30) days of contract award.
2.6.6.3 Disaster Contingency Plan. This plan shall establish procedures, identify personnel, document essential PWS disaster services and identify the means of maintaining essential PWS services during disasters. Disaster means natural disaster (e.g., earthquake, major storm, flash flood, or hurricane), utility outage, terrorist attack or other special circumstances identified by the Government. The Contractor shall submit a Disaster Contingency Plan within thirty (30) days of contract award.
2.6.6.4 Dispute Contingency Plan. This plan shall establish procedures and identify responsible personnel to provide the services below, with no interruption in the event of a labor dispute:
a. Identify and address critical Preventive Maintenance and inspection tasks,
b. Maintain electrical emergency generators, and
c. Process and execute emergency and urgent service and work orders.
The plan shall establish procedures and time frame to secure replacement personnel in the event of a strike; and shall also record the Contractor's experience with and establish Contractor procedures for collective bargaining. The Contractor shall submit a Labor Contingency Plan NLT contract start date.
2.6.6.5 Plan Updates. The Contractor shall update these plans as changes occur and shall submit a copy of the proposed plan to the KO for approval at least thirty (30) days prior to the proposed effective date of the updated plan.
2.6.6.6 Job Order Contract (JOC) Quality Assurance (QA)/inspection Support. N/A
2.6.6.7 Project Support. N/A
3.0 Performance Requirements and Standards.
3.1 High Level Objectives (HLO).
3.1.1 Performance Task Requirements, Standards and Acceptable Quality Levels
(AQLs).
3.1.1.1 Damage Caused by Contractor. Damages caused by Contractor employees shall be repaired at no cost to the Government. The Contractor shall notify the COR/ACOR and return the damaged area to its previous condition. The Contractor shall furnish all labor, materials, and equipment to perform the repair work including cultivating and applying seed, sprigging, or placing sod. The Contractor shall maintain all turf repair work to ensure successful growth.
3.1.1.1.2 Damage Report. The Contractor shall notify the COR within 2 hrs. of any damage caused by the Contractor.
3.2 Transition (Phase In/Phase Out). The Contractor shall prepare and submit a Phase In/Phase Out Plan to be implemented by the Contractor. The Contractor shall have key personnel on board, during the 60-day transition period. The plan shall specify a training program and a date for transferring responsibilities for the work and shall be subject to the KO's approval. The Contractor shall provide sufficient experienced personnel during the phase-in and phase-out period to ensure that the services are maintained at the required level of proficiency.
3.3 Contractor Manpower Reporting Application (CMRA).
3.3.1 Reporting Labor Hours. The Office of the Assistant Secretary of the Army (Manpower and Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report all Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall completely fill in all the information in the format using the following web address:
https://CMRA.ARMY.MIL.
The required information includes the following:
a. Names of the KO and COR.
b. Contract number, including task and delivery order number.
c. Beginning and ending dates covered by reporting period.
d. Contractor's name, address, phone number, e-mail address, identity of
Contractor employee entering data.
e. Estimated direct labor hours (including subcontractors).
f. Estimated direct labor dollars paid this reporting period (including subcontractors).
g. Total payments (including subcontractors).
h. Predominant Federal Service Code (FSC) reflecting services provided by
Contractor (and separate predominant FSC for each subcontractor if different).
i. Estimated data collection cost.
j. Organizational title associated with the Unit Identification Code (UIC) for the
Army Requiring Activity (RA) (the Army RA is responsible for providing the Contractor with its UIC for the purposes of reporting this information).
k. Locations where Contractor and subcontractors perform the work (specified by zip code in the U.S. and nearest city, country, when in an overseas location, using standardized nomenclature provided on website).
I. Presence of deployment or contingency contract language; and
m. Number of Contractor and subcontractor employees deployed in theater this reporting period (by country).
As part of its submission, the Contractor shall provide the estimated total cost incurred to comply with this reporting requirement.
Reporting period shall be the POP not to exceed twelve (12) months ending thirty (30) September of each Government FY and must be reported by 31 October of each calendar year. The Contractor shall use a direct data transfer to the database server or fill in the fields on the website. The direct transfer is a format for transferring files from a
Contractor's system to the secure website without the need for separate data entries for each required data element at the website. The Contractor shall report the required information to the CMR system's secure database.
The COR/ACOR is responsible for verifying that the Contractor has reported the required data.
4.0 Performance Requirements Summary (PRS) Matrix.
Required Services
#1.
Contractor shall ensure all work accomplished meets all maintenance and repair standards and all applicable Federal, State, and local laws, regulations, and directives to include, but not limited to applicable publications in Section 7, Related Documents.
#2.
The Program Manager shall be available after normal duty hours to serve as the central point of contact for Contractor operations.
#3.
The Contractor shall develop and maintain a Quality Control Plan approved by the KO.
#4.
The Contractor shall remove, from the job site, any employee for reasons of misconduct or security.
Performance Acceptable Incentive
Standard Quality Level Method of Surveillance (Positive and/or (AQL) Negative)
The Contractor 2% Deviation Random Sampling and Contractor shall provide from performance Customer Complaints; compliance rate services IAW Standard; Inspections and complaint shall be utilized as PWS, para. 1.2. % Calculated by validations performed by objective dividing the COR/ACOR. evidence of number of defects contract by the number of compliance and observations. documented into the CPAR System;
Contractor shall re-perform the service.
The Contractor Zero Deviation 100% daily and non-conforming shall provide a from performance verification/confirmation by services will result central point of standard the COR/ACOR. in Non-contact IAW Conforming PWS, para. Reports issued to
2.1.4.1. Contractor and
potential negative CPARS report.
The Contractor Zero Deviation Review and acceptance non-conforming shall provide a from performance by the by the KO on services will result QCP IAW PWS, standard. submission of QCP and in Non-para, 4.2. each revised QCP. Conforming
Reports issued and a potential negative CPARS narrative.
Employee Zero Deviation The COR/ACOR will non-conforming conduct from performance review 100% of Contractor services will result complies with standard. reported occurrences of in Non- 41 U.S.C. 423, Contractor employee Conforming Procurement misconduct, including but Reports issued to Integrity, IAW not limited to violations of Contractor and PWS para. any provision indicated at potential equitable
2.1.11.1.6. 41 U.S.C. 42 3, and/or adjustment by the security violation to ensure Contracting the offending employee is Officer.
removed from the job site.
#5.
Damages caused by Contractor employees shall be repaired at no cost to the Government.
The Contractor shall notify the
COR/ACOR
and return the damaged area to its previous condition AW PWS, para.
3.1.1.1.
Zero Deviation from performance standard
COR/ACOR will review 100% of damage reports.
Non-conforming services will result in Non- Conforming Reports issued and a potential negative CPARS narrative.
#6. The Contractor Zero Deviation 100 Percent Inspection of Non-conforming The Contractor will shall perform from performance copies of these licenses or services will result ensure that the licenses IAWPWS, standard certifications in Non-or certificates and para. 2.3.4.1. (Risk assessed Conforming training of Contractor high risk) Reports issued personnel are kept and a potential current. Copies of these negative CPARS licenses or certifications narrative will be provided to the
COR/ACOR.
4.1 Quality Assurance. The Government will evaluate the Contractor's performance under the contract IAW the Government's Quality Assurance Surveillance Plan (QASP).
QASPs are "living documents," dynamic, adaptable, and subject to modification based on Contractor performance surveillance results. The QASP is not part of the PWS and will not be issued with the solicitation. The QASP focuses on the procedures and processes the Government will implement to assure the Contractor is performing IAW the performance standards within the PWS. The Government plan defines the criteria of how the Contractor's performance will be evaluated, the frequency of surveillance, and the items to be inspected. Although the Government will develop a QASP, Government surveillance of Contractor performance is not limited to the QASP, or the performance objectives, outlined in the Performance Requirements Summary (PRS). The Government retains the right to evaluate all services required by the contract. The Government will perform inspections and tests in a manner that will not unduly delay the work. If any of the services performed do not conform to contract requirements, the Contractor shall perform the services again at no additional cost to the Government.
4.2 Quality Control Plan (QCP). Quality control is the responsibility of the Contractor.
The Contractor shall develop, implement, and maintain an effective quality control program which shall be documented in a QCP to ensure services are performed IAW this PWS. The Contractor shall develop and implement procedures to identify and prevent the recurrence of defective services. The Contractor's QCP is how they assure themselves that the work conforms to contract requirements. The basic principle of the plan is that the Contractor is responsible for quality control. The QCP shall be constructed in such a manner that each CLS service can be extracted and used for that function only and not contain extraneous information. The Contractor's QCP shall include a separate section, which addresses the Contractor's method of managing quality of work. The QCP shall include a description of the inspection system to address services listed in this PWS, and a description of the methods to be used for identifying and preventing defects in the quality of services performed. The plan shall include a description of the
Contractor's inspection system to include specifics as to areas to be inspected on a scheduled and unscheduled basis, frequency of inspections, and the title and organizational placement of the Contractor's inspectors. No lead person or first line supervisor shall be considered a Quality Control Inspector. The Contractor shall develop, maintain, and submit a QCP to the KO for acceptance within thirty (30) calendar days after the contract is awarded. The Contractor shall submit any proposed changes in the QCP to the KO for written approval five (5) working days prior to implementation.
5.0 Work Performance.
The Contractor shall provide overall management, supervision, personnel, labor, generalized or specialized equipment necessary to maintain, repair, operate, and perform all the work needed to perform the PWS below. This shall be done IAW all the terms, conditions, general and special provisions, specifications, drawings, attachments, and exhibits contained herein or incorporated by reference.
The following instruction(s) addresses Directorate of Public Works (DPW) work management and the documents required to perform the work on real property facilities.
The contractor shall ensure all requirements contained in these instructions are adhered to.
Document Title Attachment No.
IMCOM Facilities Maintenance Instruction Attachment 1
The Contractor shall ensure that all work meets or exceeds the specifications for the listed CLS.
PWS Title Attachment No.
411 Facility Maintenance - Vertical Attachment 5
6.0 Deliverables.
7.0 Related Documents.
7.1 Definitions and Acronyms.
7.1.1 Definitions.
7.1.1.1 Acceptable Quality Level (AQL). The AQL is the maximum percent defective (or the number of defects per hundred units) for the purposes of sampling inspection can be considered satisfactory.
7.1.1.2 Alternate Contracting Officer's Representative (ACOR). An employee of the U.S.
Government provided by the RA and appointed by the KO to provide support to CORs in monitoring and documenting the Contractor's performance. These alternate surveillance support personnel will serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR training, experience requirements, and are appointed by the KO as an ACOR.
7.1.1.3 Ashes. The residue from burned wood, coal, coke, and other combustible material.
7.1.1.4 Bulk Waste. Large items of solid waste such as household appliances, furniture, auto parts, pallets, shelving, piping, stone, concrete rubble, brick, lumber, toys, and other wastes; the size or weight of which, precludes or complicates the handling by normal collection, processing, or disposal methods.
7.1.1.5 Bulky Waste. The waste placed at the collection point or curbside that doesn't fit or is too heavy to be placed in the routine collection container. These wastes include but are not limited to lumber, scrap metals, bricks, blocks, concrete rubble, stones, toys, furniture, appliances, logs, limbs, televisions, cabinets, automotive components, power equipment, crates, wheels, de-rimmed tires, electronics, and their components, etc.
7.1.1.6 Cannibalize. Remove parts from Government property for use or for installation on other Government property.
7.1.1.7 Carpet Care. Cleaning and maintenance to keep carpet reasonably free of all stains, soil, and dirt. Methods used for carpet care are vacuum cleaners and carpet shampooers.
7.1.1.8 Child, Youth and School Services (CYS). Overarching naming convention for Child Development Center (CDC), Youth Activity Center, and School Age Services (SAS).
CYS is used when referencing all programs.
7.1.1.9 Cleaning. Removing stains, soil, and dirt; accomplished by chemical or mechanical means.
7.1.1.10 Collection. The pickup of accumulated recyclable material, solid waste, including bulky waste, from any collection point, regardless of quantity.
7.1.1.11 Collection Frequency. The number of times collection is performed during a specific time frame.
7.1.1.12 Collection Point. The location designated on the drawings or maps or described in this performance work statement where solid waste, including bulky materials, will be temporarily stored for collection by the Contractor.
7.1.1.13 Commercial Solid Waste. All types of solid waste generated by stores, offices, restaurants, warehouses, and other non-manufacturing activities, excluding residential and industrial waste.
7.1.1.14 Construction and Demolition (C&D) Waste. The waste building materials, packaging and rubble resulting from construction, remolding, repair, and demolition operation on pavement, housing, commercial buildings, and other structures.
7.1.1.15 Contract Administrator (CA). The official Government representative delegated authority by the KO to administer a contract. This individual, normally working in an appropriate contracting or procurement career field, advises on all technical contractual matters.
7.1.1.16 Contract Discrepancy. A failure of the Contractor to perform IAW contract requirements and specifications, e.g., a failure of the Contractor to provide, or provide on time, the required contract products, or services; or it may result because delivered products or services do not meet specific contract requirements.
7.1.1.17 Contract Discrepancy Report (CDR). A report used to document other than satisfactory Contractor performance. The CDR requires the Contractor to explain, in writing, why performance is other than satisfactory; how performance shall be returned to satisfactory levels; and how recurrence of the problem shall be prevented in the future.
7.1.1.18 Contractor. A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
7.1.1.19 Contractor Acquired Property (CAP). Property acquired, fabricated, or otherwise provided by the Contractor for performing a contract. Contractor retains title.
7.1.1.20 Contracting Officer (KO). A person with authority to enter, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
7.1.1.21 Contracting Officer's Representative (COR). An employee of the U.S.
Government appointed by the KO to help administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor if that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
7.1.1.22 Curb Side Pick-Up. Collection of solid waste or recyclable materials (to include bulky waste) that is placed next to curb, doorway, or alley by the supported activity. This refers to locations that are not serviced by bulk containers (dumpsters or compactors).
7.1.1.23 Debris. Includes, but is not limited to, paper, cans, bottles, cigarette butts, cardboard, plastic, limbs and branches, pine straw and pinecones, leaves, rocks, and other similar items.
7.1.1.24 Defective Service. A service output that does not meet the standard of performance associated with the PWS.
7.1.1.25 Deliverable. Anything that can be delivered; can include non-manufactured things, such as meeting minutes or reports.
7.1.1.26 Equipment. A tangible item that is functionally complete for its intended purpose, durable, nonexpendable, and needed for the performance of a contract. Equipment is not intended for sale and does not ordinarily lose its identity or become a component part of another article, when put into use. Equipment does not include material, real property, special test equipment or special tooling.
7.1.1.27 Fertilization. Fertilization is the process of applying nutrient elements to the soil where the soil has become deficient in nutrients essential for proper plant growth.
7.1.1.28 Food Waste. Organic residue generated by the handling, storage, sale, preparation, cooking and serving of foods.
7.1.1.29 Garbage. Animal and vegetable waste resulting from the handling, preparation, cooking and consumption of foods.
7.1.1.30 General Fund Enterprise Business System (GFEBS). GFEBS is the U.S. Army's web-based enabled financial, asset, and accounting management system that standardizes, streamlines, and shares critical financial data across the Active Army, the Army National Guard, and the Army Reserves. GFEBS is the work management system that the Directorate of Public Works uses for all order types and projects.
7.1.1.31 Generation. The act or process of producing refuse (solid waste) or recyclable materials.
7.1.1.32 Government-Furnished Property (GFP). Property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification.
Government-furnished property also includes Contractor-acquired property if the Contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract.
7.1.1.33 Government Property. All property owned or leased by the Government.
Government property includes both Government-furnished property and Government purchased Contractor-acquired property.
This is the start of the file's text. The full file is on GovTribe.