Response_to_Questions_20180628.docx

DOCX document 19 KB Posted

Attached to
Asphalt BPA Federal contract opportunity
Solicitation number
18T0007
Issued by
Department of the Air Force Space Command

View the file

Other files for this federal contract opportunity

Other files attached to Asphalt BPA, newest first.
File Type Posted
RFQ_Asphalt_BPA_20180614.xlsx XLSX spreadsheet
SOW_Asphalt_BPA_CO_Revd_20180420.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS:

Asphalt BPA

#RFQ18T0007

Questions were due to 30 CONS by 25 June 2018. The following questions were received and answers are provided below. Here are the responses to those respective questions. As a friendly reminder, proposals are due by 12:00 PM PST on 09 July 2018. Please respond to the #RFQ18T0007.

Question 1: How much Asphalt is needed?

Answer: The estimated annual use of asphalt (of all aggregate sizes is 995 tons).

The following table details the estimated quantities set forth herein are stated for the information of the perspective contractor. The actual quantities ordered may be more or less than the estimated quantities. The Contractor shall be paid for the actual quantities ordered and accepted by the Government.

Description of Services
*Estimated Quantities
Unit

Asphalt

TYPE B 3/8" HMA

PG 64-10 OIL

525
TON

TYPE B 1/2" HMA

PG 64-10 OIL

250
TON

TYPE B 3/4" HMA

PG 64-10 OIL

20
TON

SC 800 OIL

COLD MIX

200