Amendment 00001.pdf

PDF 603 KB Posted

Attached to
Replace Chiller and Cooling Towers FDC Houston Federal contract opportunity
Solicitation number
15BFA022B00000011
Issued by
Department of Justice Bureau of Prisons Field Acquisition Office

About this file

This document contains meeting minutes and questions and answers from a pre-bid site visit for solicitation number 15BFA022B00000011 to replace chillers and cooling towers at the Federal Detention Center in Houston. Key details include:

  • The site visit was held on May 31, 2022 and covered Bureau of Prisons policies and procedures for contractor performance, introductions of key personnel and responsibilities, and a tour of the worksite.

  • Written questions are due by June 3, 2022 and should be submitted to crios@bop.gov. Answers will be posted to sam.gov.

  • Bids are due by June 23, 2022 at 1:00pm Central Time.

  • Security clearance requirements and protocols for contractor employee access to the facility were outlined.

  • Logistics regarding work hours, material storage, trash removal, parking and necessary permits were also addressed.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Chiller and Cooling Towers FDC Houston, newest first.
File Type Posted
Replace Chillers Bid Abstract.pdf PDF
Additional Q-A.pdf PDF
Amendment 00003.pdf PDF
Amendment 00002.pdf PDF
Site visit QA Answered.pdf PDF
Instructions to Offerors.pdf PDF
Standard Form 24 - Bid Bond.pdf PDF
IFB Houston 15BFA022B00000011.pdf PDF
NCIC SECURITY CHECK FORMS.pdf PDF
Construction wage Rates.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return 1 copy to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This Amendment 00001 is being issued to incorporate the following into solicitation 15BFA022B00000011, Replace Chillers and Cooling Towers at FDC Houston ;

1. Sign in sheet from the site visit;

2. Meeting minutes from the site visit;

No further changes at this time.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR)

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES 1 1

2. AMENDMENT/MODIFICATION NUMBER

00001

3. EFFECTIVE DATE

6/7/2022

4. REQUISITION/PURCHASE REQUISITION NUMBER

BPQ15B51722PR00039

5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive

Grand Prairie, TX 75051

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) ( X) 9A. AMENDMENT OF SOLICITATION NUMBER

15BFA022B00000011

9B. DATED (SEE ITEM 11)

5/13/2022

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

22ZAC2

X

(1 page) (3 pages)

3. Question and answers from the site visit (5 pages)

4. Change COR from Larry Thrash to Edward Sherwood.

A pre-bid meeting and site visit for 15BFA022B00000011 was held on Tuesday, May 31, 2022.

The meeting was called to order by Henrietta Johnson, SCS, at 9:00 a.m. (Local Time). The following individuals participated in the meeting and site visit:

Name

Organization Represented Henrietta Johnson, Supervisory Contract Specialist FDC Houston Johnny Batiste, Contract Specialist FDC Houston Hector Lozano, Safety Manager FDC Houston Sondra Miller, Executive Assistant FDC Houston Ed Sherwood, Engineering Technician/COR FDC Houston Nathan Vandiver, Facilities Manager FDC Houston Gregory Thackston, Operations Manager RJY Group Travis Bugg, Project Manager Letsos Company Kwan Lee, MCOC/Engineer SEAPAC Engineering

Ms. Johnson thanked everyone for participating in today’s pre-bid conference/site visit and advised that meeting minutes would be prepared and forwarded to Ms. Rios for posting on the sam.gov website.

Ms. Johnson then identified the project as 22Z5AC2 solicitation 15BFA022B00000011, Replace Chiller and Cooling Towers and the building automation system at FDC Houston.

She informed the contractors that this site visit is being held to familiarize the bidders with the Bureau of Prisons policies and procedures to be observed during the performance of the work;

introduce personnel associated with this project, their authority, functions, and responsibilities;

and to see the location where the work will be performed.

Ms. Johnson stated that “Nothing said at this conference shall be interpreted as modifying the provisions or requirements of the solicitation, and that any revisions or changes to the solicitation will be issued as formal amendment by Ms. Rios, Contracting Officer.”

Ms. Johnson also noted that questions will NOT be answered at the site visit. Only written questions will be accepted and answered. Written questions must be submitted in Microsoft Word format to crios@bop.gov. The deadline for receipt of written questions is Friday, June 3, 2022 at 1:00 p.m. central time. Answers will be posted to the sam.gov website.

The Contracting Officer’s Representative (COR) for this project is Mr. Ed Sherwood. The COR is the technical representative for the Federal Bureau of Prisons who has overall responsibility (except for contractual matters) for the administration of operational activities at the project site.

Instructions to Bidders – Ms. Johnson called attention to the Instructions to Bidders which contains the submission procedures. THE DUE DATE FOR RECEIPT OF BIDS IS June

23, 2022, BY 1:00 PM LOCAL CENTRAL TIME.

Ms. Johnson noted that each bidder shall pay particular attention and complete all forms, clauses, and statements with his/her bid. Failure to do so may cause your offer to be considered as non-mailto:crios@bop.gov responsive and ineligible for award. Do NOT include any extraneous information/documentation outside of the solicitation requirements. Please submit all 57 pages with your bid regardless of whether you completed any information on that page or not. It is recommended to use the Instructions to Bidders as a checklist to ensure you submit all required documents.

In absence of Ms. Colon-Kenny, Human Resource Manager, security clearance requirements were presented by Ms. Johnson as stated below:

Security Clearance Requirements – In order for your employees to work on the job site they have to be cleared in accordance with HSPD-12. For access inside of the institution is required, all contractor employees (including subcontractors) will be required to complete a security clearance packet, present picture identification in person, and be fingerprinted before the paperwork can be processed. Contract workers will be fingerprinted and there will be an on-site orientation meeting each applicant will be required to attend. Contractors should allow four (4) hours for this process. The requirement for contractors to access the EQUIP computer system as part of the application process. After all of the required paperwork is properly completed and the BOP has an acceptable package, it will take approximately 2-3 weeks for a determination to be made whether or not the security clearance will be granted. Once the decision has been made the contractor will be immediately notified by the Facility Manager or designee. Any of the contractor’s employees not cleared will not be allowed on the premises.

OSHA – Mr. Lozano, Safety Manager, stated even on Federal sites OSHA regulation are to be followed. Inmates have been known to call OSHA and report unsafe conditions. Any injury on the job will be the responsibility of the contractor. Also, utilize lockout/tagout when needed.

Make sure all your employees obey all applicable laws & rules.

In absence of Captain Gonzales, tool control, institution Code of Code and other security concerns were presented by Mr. Vandiver, as stated below:

Tool Control – A locked tool box (job box) will be allowed on the jobsite. Tools will need to be inventoried at the beginning and end of each work day. An accurate master inventory sheet will be kept inside the job box at all times. The lock box will consist of two locks, one from the BOP and the other will be from the contractor. If a tool is broken on the jobsite please report it to the escort officer. If a tool is lost on the jobsite, report it to the Escort Officer immediately. Also, cell phones are not permitted in the institution.

Institution Code of Conduct – The contractor shall inform his employees that all tobacco products, intoxicating beverages, drugs, weapons, cameras, and cell phones are strictly prohibited on institution grounds. Introduction of contraband shall be subject to the penalties prescribed by Title 18 U.S.C.-1791. There will be no fraternizing with inmates as this is prohibited. If you happen to know one personally, report it immediately to the Escort Officer.

Finally, no green uniforms, khakis, BDU’s or shorts may be worn by the contractors.

Mr. Nathan Vandiver, Facilities Manager, covered the items below:

Access to the site- The project site will be opened to the contractors 5 days per week, Monday through Friday, excluding Federal Holidays. Any workers coming inside the institution will need to be preapproved and cleared for entry. Walk ups will not have guaranteed access to the site.

Covid 19 Protocol – Contractors are to adhere the institution Covid-19 matrix plan which can include mandatory mask wear and temperature screening for admittance into the institution.

Working Hours- The contractor will check in for work at 6:30 am and receive their ID badge prior to commencement of work. In order to accommodate for the daily security clearances process, the contractor should allow a total of 1 hour a day for entering and exiting the institution (30 minutes to enter and 30 minutes to exit). Work hours and workdays may be altered only with a 48 hour advance approval of the Contracting Officer. During an emergency situation, no work will be allowed. During working hours, there will be limited traffic in and out of the institution and contractors shall prepare to remain on the jobsite throughout the duration of the day, besides emergency situations. If is highly recommended for contractors to bring their lunch to the job site.

Inclement Weather and Institution Emergencies- No contract workers will be allowed on site during fog. During an Institution “lock–down”, contractor entry will be at the Warden’s discretion and determined on a case by case basis.

Construction Material Storage - The successful contractor will be familiarized with the storage site at the pre-construction conference. The contractor is responsible for site security and storage of all construction materials and equipment. On the side of the building there is an area which can be utilized and a laydown yard for storage. No materials or equipment will be stored inside the institution. The contractor will be responsible for providing fencing and security of this area.

Provisions for removal of trash and debris – It is the contractor’s responsibility for removal of all trash and debris from the job site on a daily basis.

Outline for Escorting Prospective Contractor's through site –The contractor will be under direct supervision at all times during the completion of the work. If there will be multiple work crews, arrangements will need to be made for additional escorts. The contractor will submit to the Facility Manager a list of employees and types of equipment the contractor will be utilizing on a daily basis.

Work performed outside - While most of the work will be performed inside the institution, should there be extended work outside the contractor will need to provide a portable restroom and make sure it is secured.

Parking Space - Contractor will be responsible for their own parking. There are pay parking lots in the area.

Permits – Contractor will be required to pull all permits through the City of Houston to include lane and sidewalk closure permits.

Before taking the contractors to view the site, Ms. Johnson asked if there were any questions regarding the solicitation packet. There were no other questions asked.

The site visit was conducted and contractors were taken downstairs to see worksite. The site visit lasted approximately 40 minutes.

With nothing further to discuss the contractors departed after the site visit.

Amendment 00001
SIGNIN
PREBID SITE VISIT MINUTES1