STATEMENT_OF_WORK.docx

DOCX document 21 KB Posted

Attached to
REPLACE TWO OVENS Federal contract opportunity
Solicitation number
15B61618Q00000163
Issued by
Department of Justice Bureau of Prisons Central Office

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE TWO OVENS, newest first.
File Type Posted
ADDITIONAL_PROVISIONS.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES DEPARTMENT OF JUSTICE

FEDERAL BUREAU OF PRISONS

FCC VICTORVILLE

13777 AIR EXPRESSWAY BLVD.

VICTORVILLE CALIFORNIA, 92394

STATEMENT OF WORK

PART I - GENERAL INFORMATION

A. INTRODUCTION

Purchase, Delivery and Install of (2) Ea. Double Rack Gas Ovens for FCI1 Victorville Food Service
Kitchen.

B. SCOPE

Following are specifications for requested equipment

Purchase, Delivery and Installation of (2) Ea. Double Rack Natural Gas Ovens meeting the following specifications:

· Ovens will be in current production with replacement parts readily available, replacement part pricing will be consistent with current market.

· Ovens will be installed side by side, footprint for both ovens combined must be no larger than 179 inches wide x 96 inches deep (to include hood) x 106 inches high.

· Minimum 275 kBTU/hr, Natural Gas Heated

· 208V, 60Hz, 3-Phase 15 amp Blower

· 120V, 60Hz, 1-Phase 15 amp controls

· Rotating, double rack capacity

· Oven may be split into two halves for movement through 36" openings

· 5" thick compartment insulation; rated at 0" combustible wall clearance, sides and back

· Heavy-duty rack lift and rotate with gear driven rotation system

· Standard digital control

· Integrated hood meeting NFPA 96 and Type I & II construction standards

· Heavy-duty stainless steel interior and exterior

· Automatic, heavy-duty lift and gear-driven rotation system, automatically lifts and lowers with door operation, lift capable of lifting 1 double or 2 single racks

· Heavy-duty door with double-pane viewing window

· Interior door safety release mechanism

· Oven accommodates two single or one double rack, will be set up for double racks

· 100-525 deg F temperature range

· Exhaust heat recovery system

· Racks load at floor level (no ramp)

· Fully integrated hood with single point exhaust connection

· Meets the construction requirements of NFPA 96 & UMC for Type I & II Hoods

· Digital Display Control with programmable recipes

· Selectable Automatic Temperature Setback

· Correctional Package Required

· Ovens must be Energy Star Rated

· (4) Ea. Stainless steel Roll-In Oven Racks, Fully Welded, 20 full size sheet pan capacity, double-side load. Oven Racks shall be constructed with minimum 18 gage stainless steel, welded at each slide to the square tubular stainless steel frame and electro-polished to remove weld slag and discoloration. Casters shall be of hi-temperature design, able to withstand up to 600 degrees and shall include a non-metallic, composite wheel. All fasteners shall be stainless steel. Oven racks shall be reinforced at the bottom frame to minimize rack sway when fully loaded.

· One Year Parts and Labor Warranty

· Freight to 13777 Air Expressway Blvd., Victorville Ca. 92394

Installation shall include:

· Removal of existing equipment. Contractor shall disconnect, and remove the existing ovens and place in a location directed by the Facility Manager.

· Contractors shall supply tools and equipment needed to remove old ovens and install new ovens

· Equipment shall be moved into the facility, uncrated, set in place and leveled.

· Final assembly. Final assembly of equipment.

· Final connection. Final utility connections shall be made on all applicable equipment utilizing existing utilities, ductwork and drain plumbing.

· Contractor shall clean all areas of work and return area back to original condition.

· Start up, operation/leak check shall be performed.

· Post Certification to include verification of installation in accordance with manufacturers’ specifications. Post Certification to be submitted to customer within 30 days of completion of installation.

· One Year Parts and Labor Warranty

· Installation will be performed in a manner which will minimize downtime, work will be performed during normal working hours 7:00 am – 3:30 pm, Monday – Friday.

· The installation will be taking place within the secure confines Federal Correctional Institution #1, therefore all contractors will be required to pass background checks per BOP policy.