Pre-Bid_Site_Visit_1.pdf
PDF 437 KB Posted
- Attached to
- Construct Switchgear Building Federal contract opportunity
- Solicitation number
- 15B41918B00000002
About this file
Pre-bid meeting minutes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract.pdf | ||
| Amend_7.pdf | ||
| amendment_6.pdf | ||
| Amendment_5.pdf | ||
| Amend_3.pdf | ||
| Amend_2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Justice Federal Bureau of Prisons
ADMINISTRATIVE UNITED STATES
PENITENTIARY
Office of the Financial Management 1100 One Mile Road P.O. Box 1001 Thomson, IL 61285
August 21, 2018
MEMORANDUM FOR ALL PROSPECTIVE BIDDERS
SUBJECT: Minutes of Pre-Bid Conference Solicitation 15B41918B00000002
Construct Switch Gear Building
Please find the attached copy of the minutes from the pre-bid conference conducted August 21, 2018, at AUSP Thomson, IL.
These minutes are provided for informational purposes only and are not intended to change any part of the solicitation. These minutes do not constitute an amendment and therefore acknowledgement is not required. The Contracting Officer will issue changes, if any, in the form of amendments (Standard Form 30).
Sincerely, /s/
Robert Cox, Supervisory Contract Specialist
Attachment
U.S. Department of Justice
Federal Bureau of Prisons
ADMINISTRATIVE UNITED STATES
PENITENTIARY
Office of the Financial Management 1100 One Mile Road
P.O. Box 1001
Thomson, IL 61285
August 21, 2018
Pre-bid meeting
4C3W – 1541918B00000002
Construct Switchgear Building
On Tuesday, August 21, 2018 at 9:00 am a pre-bid meeting regarding the Construct
Switchgear Building (4C3W- 1541918B00000002) was held.
The following individuals were in attendance:
1. Robert Cox- AUSP Thomson, Supervisory Contract Specialist
2. Eric Ball- AUSP Thomson, Contract Specialist
3. Tabitha Coleman-AUSP Thomson , Contract Specialist
4. Rodney Polk- AUSP Thomson , Facilities Manager
5. Eddie Muncy, AUSP Thomson,COR
6. Stacy Peacock- NCRO, Architect
7. Greg Edmonds- Henderson Engineer, Engineer
8. Chad Bard- SFS Architecture, Architect
9. Mary Clare Amer, Wallace Engineer, Civil Engineer
10. Jesse Shekleton, Jo Carroll Energy, Director of Engineer
11. Brandin Keltner, SJostrom & Sons, Project Manager
12. Michelle Gohl, Pagoda Broadway Joint Venture One, Estimator
13. Randy Tacey, Tri-City Electric, Estimator
14. Jeff Knutsen, Daxon Construction Company, Superintend
15. Steve Larssen, Daxon Construction Company, Project Manager
16. Steve Daxon, Daxon Construction Company, President
17. Rob Davis, Bush Construction, VP of Operations
18. Ryan Dean, Bush Construction, Project Manager
19. Thomas Lund, Richard Group, LLC, CM
20. Rick Siebert, Richard Group, LLC, Estimator
21. Jeromie Nagez, Cerebral Group, Project Manager
22. Rex Danner, Valley Construction, Project Manager
23. Ted James, Company One Fire, Owner
24. Amy James, United Electric, Project Manager
The following topics were discussed:
• The meeting commenced at 9:00 a.m. with Rodney Polk giving a brief description of the solicitation.
• The contractor should notify the COR for the need of a punch list prior to any cover up of mechanical systems.
• Work hours are 7:30 a.m. to 4:00 p.m. Monday - Friday excluding Federal
Holidays unless otherwise stated on the SOW.
• Work delays must be documented and forwarded to the COR and the Contracting Officer.
• NCIC background investigations will be conducted on all contractors entering the institution.
• All work done outside of the scope of the contract must be approved in writing prior to the work beginning.
• Potential changes to the specs and drawings was discussed. Any changes that occur will be via amendment.
Additional correctional environment issues were discussed:
• Institutional emergencies can happen at any time. In the event there is an emergency, all work will cease.
• If a contractor discovers a tool missing, he/she should notify the COR/Contracting Officer immediately.
• All cameras and recording equipment are strictly prohibited without prior written consent from the Warden.
A tour of the construction site took place and covered the following areas:
1. North side of Facilities Building
The following question was asked at the meeting:
Where will the staging area be?
The staging area is behind the existing switchgear and the contractor will use the Camp entrance.
The tour of the work site concluded at 10:21 a.m.
Robert Cox 8/21/2018
Supervisory Contract Specialist Date
| 2018-08-21T16:11:54-0500 | |