Pre-bid_Meeting_Minutes.pdf
PDF 561 KB Posted
- Attached to
- Remove Latora Hall Federal contract opportunity
- Solicitation number
- 15B40218B00000001
About this file
Pre-bid Meeting MInutes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Justice
Federal Bureau of Prisons Administration Division
Field Acquisition Office Grand Prairie, Texas 75051
August 30, 2018
All Prospective Bidders
SUBJECT: Minutes of Pre-Bid Conference Solicitation 15B40218B00000001
Remove Latora Hall FPC Duluth
Please find the attached copy of the minutes from the pre-bid conference conducted August 28, 2018, at FPC Duluth.
These minutes are provided for informational purposes only and are not intended to change any part of the solicitation. These minutes do not constitute an amendment and therefore acknowledgement is not required.
Changes, if any, will be issued in the form of amendments (Standard Form 30) by the Contracting Officer only.
Sincerely, Michelle Morgan, Contracting Officer
Attachment
1 | P a g e
PRE-BID CONFERENCE MEETING MINUTES
15B40218B00000001 – REMOVE LATORA HALL
FPC DULUTH - PROJECT 4C2D
DATE: August 28, 2018
A prebid conference was held for the project entitled Remove Latora Hall. The meeting began at 1:00 pm CST and ended at approximately 1:30 pm CST.
The following were present:
Contractor Representative Company Nick Linneman Landwe
Government Representatives P. Wernke Facilities Manager (COR) G. Ignaszewski Captain John Stanford Safety manager Adam Hastings IT Manager Blaze Shrake Property and Procurement Specialist Michelle Morgan Contracting Officer
PURPOSE OF MEETING:
The purpose of this meeting is to familiarize the contractor with the unique circumstances and requirements surrounding a correctional setting. This meeting is also to explain the solicitation, as issued, and not to furnish additional information.
Nothing said here shall be interpreted as a change to the solicitation without the issuance of a formal amendment through the Contracting Officer, Michelle Morgan.
MINUTES:
Advised minutes will be recorded and distributed via FedBizopps at www.fbo.gov.
FRONT COVER PAGE FORMS AND INSTRUCTIONS:
Note the instructions on the cover letter in the Solicitation and all bids sent by mail shall be addressed to:
FEDERAL BUREAU OF PRISONS
FIELD ACQUISITION OFFICE
ATTN: MICHELLE MORGAN
346 MARINE FORCES DRIVE
GRAND PRAIRIE, TX 75051
TIME FRAMES AND LOCATION FOR SUBMISSION OF BIDS:
• The deadline for submission of bids for this project is September 12, 2018 by 2:00 P.M. CST.
http://www.fbo.gov/
2 | P a g e
• QUESTIONS: All questions about the solicitation documents will be posed to Michelle Morgan no later than Friday, August 30, 2018 no later than 1:00 pm CST.
• DAVIS BACON ACT: This contract is subject to the Davis Bacon Act. Wage
• LICENSING AND PERMITS: All required licensing and permits are required to be obtained by the contractor who receives contract award.
• MAGNITUDE: The magnitude of the project is between $250,000.00 and $500,000.00.
• PERIOD OF PERFORMANCE: The completion period is 178 calendar days after issuance of notice to proceed.
• TIME EXTENSIONS: Time extensions for inclement weather will not be granted unless the weather is unusually severe and abnormal in comparison to prior years.
• PRE-CONSTRUCTION CONFERENCE: A Pre-Construction conference is required after the contract is awarded and will be scheduled accordingly.
• PROGRESS SCHEDULE: A copy of the progress schedule is to be provided to the Contracting Officer and Contracting Officer Representative as soon as possible. Each time the progress schedule is changed, it must be provided to both the Contracting Officer and COR. It is suggested an updated document be provided by the Prime Contractor at the mandatory monthly progress meeting.
• PROGRESS MEETINGS: Progress meetings are mandatory and will be scheduled monthly.
• PAYMENT REQUESTS: Application for payments are to be submitted on AIA G702(Continuation) or the contractors own form as long as the information is similar to the G702. Contactors can get these forms from the following website www.aiabookstore.com
COR
• COR: The contracting Officer’s Representative (COR) is Mr. Paul Wernke, Facilities Manager.
• WORK HOURS: 7:00 – 3:00 M-F. No weekends or federal holidays.
• ACCESS TO SITE/PARKING OF VEHICLES: Parking will be provided for employee vehicles and contractor work vehicles.
• STORAGE OF MATERIALS: Storage of materials will be coordinated with the Contracting Officer’s Representative.
• CONTRACTOR TEMPORARY OFFICE: No temporary office space will be provided.
http://www.aiabookstore.com/
3 | P a g e
SAFETY MANAGER:
• The contractor is responsible for providing required protective gear to all contractor workers, should it be required. Contractor will ensure that all workers have proper safety gear at all times.
• Contractor is responsible for the prevention of accidents on the project site and has spill kit onsite and containment procedures. OSHA requirements will be adhered to.
• Manifest copies must be provided to the COR.
• The Contractor will have a Safety Representative on site at all times during the completion of this project.
• Proper storage of any chemicals in lay down yard with SDS present.
CAPTAIN:
SECURITY
• ADVERSE WEATHER: Whenever adverse weather conditions or other institution emergency contingencies are in effect, contract workers will not be permitted passage into the secure institution. Should emergency conditions be implemented while contract workers are inside the secure perimeter, they will be required to secure their tools, remove vehicles and equipment, and leave the institution grounds until the emergency situation has been resolved.
Depending upon the nature of the emergency, this normally will not affect any construction outside of the secure perimeter. Contractor is reminded that fog days will be treated like rain days. The performance period of 365 days will allow adequate time to complete the job, and no consideration will be allowed for normal rain days and normal fog days. The normal rain, snow or fog days will be based on the average over the last ten (10) years for the local community.
• SECURITY CLEARANCES: Contract workers are subject to security investigative procedures.
Please refer to the contract for details. Workers will be required to wear a badge provided by the BOP. Please refer to Page 17 of the contract.
• EMPLOYEE IDENTIFICATION: Contractor personnel working on project site must bring valid photo identification to the institution each day. The identification will be surrendered upon entry to, and returned upon exit from institution property.
• TOOL ACCOUNTABILITY: Strict accountability and control of all contractor tools and hazardous materials must be maintained at all times. All contractor tools to be used inside the secure perimeter must be inventoried and accounted for at the conclusion of the work day Contractor tools may not be stored on-site overnight. The contractor should provide for enough time at the conclusion of the work day for the return and accounting of all tools issued during the work day.
Lost or missing tools must be reported to the COR the Captain immediately.
• ILLEGAL ITEMS ON FEDERAL PROPERTY: Cell phones, firearms, ammunition, knives, other weapons, drugs, narcotics, and alcoholic beverages are not permitted inside/outside the secure perimeter or anywhere else on Federal property at any time. This includes the private vehicles of contract workers. Violators will be subject to criminal prosecution. All persons, vehicles, and
4 | P a g e equipment are subject to search by institution authorities at any time.
• NO CONTACT WITH INMATES: Contract workers are not to have any contact with inmates at any time. No photographs may be taken of inmates.
• PHOTOGRAPHS: The institution’s Facilities Department maintains a digital camera that will be utilized by FBOP staff to document the project work. The Contractor may request copies of these photos, and may request that photos be taken for specific conditions. Cellular telephones equipped with photographic capabilities are prohibited on the project construction site.
Meeting minutes recorded by:
Michelle Morgan, Contracting Officer
NOTICE:
MEETING MINUTES ARE PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THEY ARE NOT
INTENDED TO CHANGE ANY SPECIFICATIONS, TERMS OR CONDITIONS OF THE SOLICITATION.
ANY AND ALL CHANGES TO THE SOLICITATION SHALL BE ISSUED IN SUBSEQUENT
AMENDMENTS ISSUED BY THE CONTRACTING OFFICER ON A STANDARD FORM 30 (SF-30).
| meeting minutes letter |
| August 30, 2018 |
| Michelle Morgan, Contracting Officer |
| PRE-BID MEETING MINUTES |
Meeting Minutes
| 2018-08-30T13:43:53-0500 | |
| MICHELLE MORGAN |
| 2018-08-30T13:43:24-0500 | |
| MICHELLE MORGAN |
File details come from the government source that posted it.