QUESTIONS AND ANSWERS 1 = ALLENWOOD ASPHALT
Q - What tack are you specifying for this project? CSS-1h, CNTT Trackless Tack, NTT Trackless Tack. These are all PennDOT approved with different costs.
A - Any PennDOT approved tack is acceptable
Q - How is the application of the tack being performed? Are we able to spray the entire area that will paved for that day first thing in the morning? Or will we need to account for an employee to be present the entire day of paving? This will affect unit cost.
A - The tack can be sprayed the morning of for the area that will be completed that day. We are requesting that the tack truck be on site a minimum of 30 minutes prior to the first delivery of asphalt.
Q - What ESALs would you like for the 9.5mm? <0.3 (50gyr), 0.3<3 (75gyr), or 3<30 (100gyr) Being a parking lot I'm assuming 50 or 75 gyration.
A - <0.3 (50gyr)
Q - What SRL (Skid Resistance Level) would you like? Again being a parking lot I'm assuming SRL-L
A - Low