This document is an amendment to a solicitation for the SCCAO Friant Dam Pump Controller Replacement project issued by the Department of the Interior's Bureau of Reclamation. The amendment extends the request for quote (RFQ) submission deadline to July 16, 2024 and provides answers to contractor questions. Key details include:
The agency requires the replacement of electronic components in the pump control system, but did not initially provide a list of components. The amendment clarifies that the contractor should provide the required parts since this is a scope of work, not a specification. The agency has provided photos of the existing equipment, including the PLC, VFD, and control panel. The contractor is responsible for identifying the required digital/analog inputs, outputs, serial ports, and relays for the new PLC. The agency does not have the existing PLC software and is seeking enhanced automation and control capabilities, but not integration with external SCADA systems. The amendment specifies that the new control panel must meet California Electrical Code standards and provides details on the existing cabinet dimensions and mounting. The agency requires one 12-inch HMI screen to be installed and has provided photos of the existing screens. A site visit attendance list is also attached.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2024Q0103_Amd_0002.pdf | ||
| Photos_0001.pdf | ||
| Visitor_List_for_walk_thru_0001.pdf | ||
| Sol_140R2024Q0103.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R2024Q0103 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815
R20
Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation
07/11/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/24/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
CONTRACTORS MUST SIGN AND RETURN A COPY OF PAGE ONE OF THIS AMENDMENT WITH THEIR RFQ
SUBMISSION TO BE CONSIDERED FOR AWARD.
The purpose of the amendment 0001 is as follows:
1) Extend the Request for Quote (RFQ) date to Tuesday, 7/16/2024 at 5:00 PST.
2) Address contractor's questions.
3) Attach photos and site visit sign in sheet.
Answers to questions can be found on following SF30 continuation pages.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Joe Molina
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024Q0103/0001
1. Electronic components:
The agency requires the replacement of electronic components. However, it did not provide a list or description of any electronic components with their salient characteristics to allow potential offerors to develop a budget and a quote. This omission obscures the requirement to a point of unknown, which requires assumptions that can be interpreted in multiple ways, hence ambiguous. We ask the contracting office to list all and any electronic components requiring replacement with their detailed salient characteristics and quantities.
Answer: Contractor should provide the parts since this is a Scope of Work and not a Specifications where we required certain types of equipment.
2. Please provide photos of all the electronic components, including the control cabinet interior and exterior.
Answer: See attached photos
3. Please provide the salient characteristics of the feeding electricity to the control cabinet
(phases, voltage, current).
Answer: 240V Power Supply
4. Please list all sensors connected to the PLC that must be modernized and provide their manufacturer, model, and salient characteristics.
This may include pressure sensors or other sensors.
Answer: See attached photos
5. Please list all Variable Frequency drives connected to the PLC and provide their manufacturer, model, and salient characteristics.
Answer: Please see photo of the VFD installed. In addition, it is a Altivar ATV630 TYPE1 460V -
THIS ALTIVAR PROCESS ATV600 VARIABLE SPEED DRIVE
CAN FEED 3-PHASE SYNCHRONOUS AND ASYNCHRONOUS
POWER MOTORS. IT FEATURES 3 BUILT-IN RJ45
COMMUNICATION PORTS AS STANDARD, 1 ETHERNET PORT,
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024Q0103/0001
2 SERIAL PORTS. IT WORKS AT A RATED SUPPLY
VOLTAGE FROM 380V TO 480V
6. Please list all lights, alarms, strobe lights, sirens, and buzzers connected to the PLC.
Answer: No light alarms or sirens. If contractor wants to add it to the quote we would consider it.
7. Please list all thermometers connected to the
PLC and provide their manufacturer, model, and salient characteristics.
Answer: Please see photos of Honeywell PLC. No thermometers in the system
8. Please list all communication devices, including switches, routers, modems, radios, and cellular- connected devices.
Answer: No outside communications devices, internet or radios.
9. Please list breakers, fuses, timers, power switches, distribution terminals, and power supplies with their quantities and salient characteristics.
Answer: Please see photos
10. Replacement of the PLC
a. Please describe the current PLC program logic:
i. Describe in simple words what the program does and the conditions and logic in its operation.
Answer: Be able to turn on and off the pump, see pump speeds, control the set pressures for it to reset and see the current pressures. In addition, be able to see the history graph of the pump use.
ii. Please provide the program ladder diagram or equivalent to evaluate how the program should be modernized.
Answer: No Diagram Available
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024Q0103/0001
b. Please identify in the new PLC:
i. The number of digital inputs
ii. The number of digital outputs
iii. The number of serial ports
iv. The number of analog inputs
v. The number of analog outputs
vi. The number of relays and their salient characteristics of the electricity they operate.
Answer: Contractors Responsibility
c. Enhance system automation and control:
The solicitation on page 5 requires:
"Supply and install new PLCs with updated technology to enhance system automation and control."
The agency did not describe the enhancements it requires from the system and the additional automation and control it desires to have resulted from this procurement. We ask the agency to describe the system automation and control enhancements.
Answer: Current PLC is a Honeywell
Product from 20 years ago
d. Does the agency hold a copy of the legacy
PLC software so it can act as a starting point for modernization and provide a detailed understanding of the existing logic?
Answer: No, we do not have a copy
e. Please share a copy of the existing PLC software for review.
Answer: No, we do not have a copy
f. Please identify if the contractor must implement any communication with external systems such as SCADA, other PLC or other systems.
Answer: No, It is an isolated system
g. Please identify the enhancement of system automation, including the development of SCADA
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
5 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024Q0103/0001 screens (other than HMI) or the modification of a SCADA program to acquire information from the new PLC program.
Answer: N/A
11. Control Panel
a. Please identify the control panel material
(Stainless steel, powder coated, steel painted, PVC based)
Answer: Please see photos
b. Please provide the dimensions (Height, Width, Depth)
Answer: W: 8 inch
L: 24 inch H: 24 inch
c. Please identify if the cabinet is self-standing or if it is mounted to any device, such as a wall or pedestal.
Answer: Mounted on wall. Please see photos
d. Please provide photos of the control cabinet
Answer: Please see photos
e. Standards The solicitation requires page 6, section
4: "Ensure that the new control panel meets all current standards and is fully integrated with the new system components." Please list which standards are actually required in this solicitation; all current standards are too broad as a requirement and, at many times, contradictory.
Answer: California Electrical Code is the standard
12. HMI Screens
Answer: The solicitation on page 5, section 3 requires: "Install new HMI screens, ensuring they are compatible with the new PLCs and electronic
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
6 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024Q0103/0001 components." Typically, a pump control PLC will have a single screen panel mounted on a control panel door or internally installed within a control cabinet. The solicitation articulated a plural language but has yet to identify the number of screens it wishes the contract to provide in this project.
a. How many (physical) screen panels should be provided and installed within the control cabinet?
Answer: One HMI Screen
b. Please identify the required screen dimensions (4, 7, or 10-inch widescreen).
Answer: 12 inch
c. Please provide photos of each program screen within the HMI screen panel.
Answer: Please see photos
13. Site Visit Attendance
Please provide a copy of the site visit attendance list.
Answer: List attached
14. Does this system need to connect to the existing SCADA system at the dam?
Answer: No, this is an isolated system and local control only
15. Is replacement with a high performance building automation system possible, or does the
BOR require replacement with a PLC?
Answer: We required a local control with no access to outside networks (Cannot connect to the internet) and We believe a local PLC can be the solution unless contractor can provide a better solution.
16. Should the existing pressure sensors be replaced, or should the existing pressure sensors be reused?
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
7 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024Q0103/0001
Answer: If contractor deems necessary, BOR has no objection
17. There is a flow meter installed in the pipe that has been disconnected. Should this flow meter be replaced and connected to the control system?
Answer: No, Flow meter does not need to be connected. We do not measure the flow going out.
18. Does the size of the new touchscreen need to be the exact size of the existing screen (12¿)?
New aspect ratios may make this larger or smaller. Is there a minimum size required for the touchscreen?
Answer: No, Contractor needs to replace same or can increase size of screen if they can modify the box to fit the bigger screen
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)