Questions_and_Answers_0001.pdf
PDF 110 KB Posted
- Attached to
- Roof Replacement Federal contract opportunity
- Solicitation number
- 140P6421R0035
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6421R0035_Amd_0001.pdf | ||
| Past_Performance_Questionnaire.docx | DOCX document | |
| Wage_Determination.pdf | ||
| Bid_Schedule_-.xlsx | XLSX spreadsheet | |
| Statement_of_Work_-_Privy_Roof.pdf | ||
| Bid_Schedule_-.pdf | ||
| Notice_to_Contractors.pdf | ||
| Technical_Questionnaire.pdf | ||
| Technical_Questionnaire.docx | DOCX document | |
| Statement_of_Work_-_Duffy_Roof.pdf | ||
| Past_Performance_Questionnaire.pdf | ||
| Sol_140P6421R0035.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Roof Replacement Project – CUVA Questions and Answers listed below:
QUESTIONS:
Question # Question Answer/Response
1. Can the work areas around the buildings can be trimmed mowed down so that building materials can be cleaned up easily.
I will talk to mow crew and see about getting that done. With no start date mowing would be closer to that time.
2. Can we use a UTV or truck to haul in all the materials needed for the job?
Duffy complex has a staging area on the plot map for parking and materials. The privies are to be staged in each lot, site map locations. The grounds are to be left as found with no ruts or damage.
Repair of grounds will be contractor’s responsibility.