B09_Solicitation_Amendments_AMD_1_Attach_1_Q___A_Document_0001.docx
DOCX document 340 KB Posted
- Attached to
- JECA 21 WINDOW REPLACEMENT Federal contract opportunity
- Solicitation number
- 140P6322Q0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6322Q0001_Amd_0001.pdf | ||
| B08_Solicitation_Attach_3__alum_wood_clad_windows_specifications_1.pdf | ||
| Sol_140P6322Q0001.pdf | ||
| B08_Solicitation_Attach_5_Wage_Determination_.pdf | ||
| B08_Solicitation_Attach_2_Drawings.pdf | ||
| B08_Solicitation_Attach_4__Experience_Questionnaire.xls | XLS spreadsheet | |
| B08_Solicitation_Attach_1_Project_Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers Remove/Replace Windows Jewel Cave Apartments Jewel Cave National Monument.
Solicitation # 140P6322Q0001
The following questions were generated following the site visit of November 10, 2021. The questions and responses are incorporated into the solicitation via amendment 1.
Questions & Answers
| # |
| Questions |
| Response |
| 1 |
| Manufacturers recommend using capillary tubes in windows installed over 3,000 feet in elevation, but the specs indicate they should be argon filled. Are capillary tubes acceptable rather than argon filled? |
Capillary tubes are acceptable and should be noted in the submittal when submitting product information for approval.
| 2 |
| Horizontal sliders do not meet the maximum U-factor of 0.30, 0.31 is the best I can find. Is this U-factor acceptable for horizontal sliders? |
0.31 U-factor is acceptable and should be noted in the submittal when submitting product information for approval.
| 3 |
| Horizontal sliders can also have an issue meeting the air infiltration requirement of 0.05. We are searching for a product to meet these requirements, if we are not successful, will this requirement be possible to waive? |
Possible to wave with accurate information submitted for review.
| 4 |
| Measurements of the rough openings will need to be performed immediately following award, will the facility be accessible in December/January for measurements? Windows have an approximate lead time of 3 months currently, and with a four-month duration for the contract, timing is a large factor. |
Yes, Facility will be accessible in December/January within regular hrs except during holidays.
| 5 |
| Do you plan to post a list of site visit attendees? |
Yes, the sign in sheet is on page 3 of this document.
| 6 |
| Is there any concern for asbestos or lead within the scope of work for the window replacement? |
There is no concern based on the original construction year 1990
| 7 |
| Can you provide a seed mix for the restoration of the grass after the window wells are removed and replaced? |
Any common lawn seed mix, EXCUDING Kentucky Blue Grass seed.
| 8 |
| Will the parks service be responsible for watering and maintaining the newly seeded area after work is completed? |
The park will care for watering if the area is properly seeded, and seed free straw mulch is approved by COR for area coverage. The park will not be responsible if requirement is not met thus contractor will be responsible for care.
| 9 |
| Is there any concern for ground water for the window well replacement? |
Ground water not a concern
| 10 |
| What email address do we send our proposal to? |
Please send your RFQ to Joseph_Kirk@nps.gov
| 11 |
| Is it acceptable to substitute the Pella window vinyl 250 series or the Pella fiberglass window in lieu of the aluminum clad windows? From discussion with our Pella rep, they no longer manufacture the aluminum clad with the slider as noted in the specifications. If aluminum clad is required can the slider be changed to either a hung window or casement window? |
· Vinyl windows are not acceptable
· If fiberglass is used it must meet required specs
· Sliders are required where sliders are specified
| 12 |
| From discussion with our window rep the current average lead time on windows is 12 to 14 weeks. This would put the window order out around 90 days. If the deadline is to be April as noted on the schedule is it the intent to have an award by the first of December. Looking at the schedule this would put window delivery around the middle of February without time for submittal approval which would put the delivery likely in the first to mid-March leaving only a short time frame to complete the work. Is there consideration for material delays due to supply chain issues and is the deadline firm as noted? |
The Government accounted 70 days for material lead time. If for some reason the material delivery lead time does get pushed back due to supply chain issues the Government will adjust accordingly at that time. The Government would like the project to be completed by 15 April 2022. If there are lead time issues, we will adjust the notice the proceed.
Site Visit Sign-in Sheet image1.png