Generators for Virgin Islands NP Federal contract opportunity
Solicitation number
140P5418Q0042
Issued by
Department of the Interior National Park Service

About this file

Atch 1 to Am 1-Q&As

View the file

Other files for this federal contract opportunity

Other files attached to Generators for Virgin Islands NP, newest first.
File Type Posted
Sol_140P5418Q0042_Amd_0001.pdf PDF
Sol_140P5418Q0042.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P5418Q0042 Amendment 1 Attachment 1

Question #1: Is installation a requirement??

Answer: No.

Question #2: Will equipment be available to off-load the equipment ?

Answer: Yes we have a bob-cat or skid-steer with attachments.

Question #3: Is a loading dock available to off-load the equipment?

Answer: Equipment is available to off-load the generators.

Question #4: I cannot find anything that tells me the operating voltage for these generators. The Kohler model numbers can be configured in several different voltages. Do you have the voltages available?

Answer: Correct, the voltage can be adjusted. Basically, 120/208v - 3ph - and the amperage is different based upon the total Kw.

Question # 5: The motors that will be supplied by the generator in standby mode are designed to operate +/-10% (roughly 187V-229V) but will operate best at 208V. The generator has some room for adjustment. Is it acceptable if we quote the generator at 208V 3-phase?

Answer: Yes

Question # 6: Generator voltage?

Answer: 120/208

Question # 7: Auto transfer switch voltage and amperage?

Answer: ATS’s, Nema 4X, stainless steel, open transition, non-by-pass with a 3 pole 200A breaker.

Question # 8: Switch to be service-entrance rated?

Answer: YES

Question # 9: To include generator battery charger?

Answer: YES

Question # 10: Batteries included, or local purchase for warranty?

Answer: Battery included

Question # 11: "48 and 72 hour" fuel tank rating -- is this at 100% load, or the more desirable operating average of ~50% load?

Answer: Reference: Kohler 40REOZK with 48 hour (229 gal) subbase tank & Kohler 30REOZK with 72 hour (209 gal) subbase tank

Question # 12: Generator circuit breaker required? Amps?

Answer: Yes, 200 amp

Question # 13: Is the aluminum housing to be weather protective only, or sound-attenuated?

Answer: Weather and sound.

Question # 14: Delivery dockside port of St. John? Or delivered locally to site(s)?

Attachment 1

Answer: Per solicitation, quote must include delivery to Virgin Islands NP, 1300 Cruz Bay Creek, St John, VI 00830

Question # 15: Prime rating specified, for applications where utility service not connected.

Answer: Prime rating for extended (Hurricane aftermath) run time

Question # 16: Will there be utility power connected, with the gensets operating in standby mode or completely off-grid requiring Tier 4 EPA emissions certification??

Answer: Utility connected and also Tier 4 EPA emissions certification.

Question # 17: Startup/commissioning required on-site?

Answer: No, delivery only

Question # 18: fuel tanks to be dual wall, UL142 compliant per EPA? Or single wall with masonry containment on site?

Answer: See referenced model for minimum specs.

Question # 19: What level of EPA Emissions must these generators comply with? Tier 4 Final? Tier 4 Interim or less?

Answer: Tier 4 final

Question # 20: Are these Skid-Mounted units? Or, on trailers?

Answer: per the posted specs, mounted on a belly fuel tank (subbase)

Question # 21: Is the 60 Day delivery time negotiable?

Answer: Yes, quote your best delivery time after receipt of an order.

Question # 22: Please confirm delivery address of 1300 Cruz Bay Creek, St John, VI 00830. This does not pull up on a map. Perhaps there are GPS coordinates?

Answer: Lat/Long is 18° 19' 59"N and 60° 47' 26"W

Question # 23: Please confirm you will have the means to off load them at the delivery site.

Answer: Answered above

Question # 24: Please confirm this is for the purchase of equipment only and does not include installation.

Answer: Answered above

Question # 25: On the ATS, it mentions requiring a 200amp breaker. Most standard ATS’s do not have breakers unless you are requesting a service entrance rated ATS’s which would have a main breaker for the utility power coming in. Please confirm.

Answer: Answered above.

Question # 26: Please confirm the voltages required for each of the generators.

Answer: Answered above

Question # 27: Please confirm if batteries, battery chargers, or any other accessory is required.

Attachment 1

Answer:

Question # 28: Please confirm if the sub base tank shall be double wall.

Answer: Answered above.