Sol_140P2121R0015_Amd_0001.pdf
PDF 122 KB Posted
- Attached to
- FOUN EXHIBIT FABRICATION Federal contract opportunity
- Solicitation number
- 140P2121R0015
About this file
This document is an amendment to a solicitation for exhibit fabrication services for Fort Union National Monument. The National Park Service is seeking a contractor to fabricate and install new exhibits at the Fort Union National Monument in North Dakota. The amendment responds to questions received regarding the cost estimate form and scope of work. For the cost estimate, offerors may replace any unrelated line items with information applicable to the project. Additionally, the amendment clarifies that the contractor is not responsible for purchasing or installing the gallery lighting systems, as those will be covered under a separate renovation contract, but the selected offeror will be responsible for positioning track light heads during installation. The closing date for responses was not provided.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2121R0015 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PHF
Harpers Ferry WV 25425 IDC Building 67 Mather Place DOI, NPS, HFC - Acquisition Managem
PWA
Denver CO 80225 P.O.Box 25287 MS WCP NPS, WASO - WCP Contracting
05/28/20210001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/19/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This is a combined synopsis/solicitation for commercial items prepared in accordance with
Subpart 12.6, as supplemented with additional information in this notice.
The purpose of this amendment is to respond to questions received by the date and time specified in the solicitation in accordance with the attached Description of Amendment consisting of one page.
Legacy Doc #: NPS
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Sheila Spring
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation Number 140P2121R0014 Amendment Number 0001
Description of Amendment Fort Union National Monument
The purpose of this amendment is to respond to questions received by the date and time specified in Solicitation Number 140P2121R0014, Exhibit Fabrication for Fort Union National Monument.
1. The line items in the cost estimate form look to be from a different project. Can you provide a new cost estimate form or should the contractor delete the line items and fill in the information as applicable?
RESPONSE: The Cost Estimate Form is used as a template for all exhibit fabrication projects. It is acceptable to replace any unrelated line items with information for the FOUN project.
2. There is a bit of contradicting information in the bid documents regarding the gallery and track lighting. Can you confirm whether or not the gallery and track lighting is in the contractor's scope of work?
RESPONSE: The Exhibit Fabrication Contractor is not responsible for purchasing / installing the gallery house lighting and exhibit track lighting. These systems will be covered by the building renovation contract. All overhead gallery lighting systems will be installed and powered ahead of the exhibit installation. The Exhibit Fabrication Contractor will be responsible for positioning / aiming track light heads during the exhibit installation.