Questions Addressed_0001.docx

DOCX document 18 KB Posted

Attached to
ASPEN RIDGE CLASS III INVENTORY Federal contract opportunity
Solicitation number
140L6220Q0078
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

View the file

Other files for this federal contract opportunity

Other files attached to ASPEN RIDGE CLASS III INVENTORY, newest first.
File Type Posted
Sol_140L6220Q0078_Amd_0001.pdf PDF
Sol_140L6220Q0078.pdf PDF
Map.pdf PDF
Statement of Work.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140L6220Q0078 Aspen Ridge Class III Inventory

AMD 001

Questions Addressed

1. Past Performance: Do we submit only 5 projects (1 per client), or all cultural projects within three years with only a list of 5 clients? Additionally, the SOW doesn’t mention the two years of non-cultural (but similar in complexity) projects to submit. Which is correct?

Solicitation states “Past performance shall provide adequate information describing the offeror’s previous experience in Cultural Inventory within the past three years…offeror shall also list all contracts performed in the past two years…that are of the same magnitude and complexity of this project.” Page 7.

SOW states “Respondents will submit a list of clients (no more than 5) for past and present similar projects covering the past three years.” Page 4.

a. To clarify, please provide past performance information that is specific to your experience in Cultural Inventories that were performed within the past three years. Additionally, please provide a list of all contracts that were performed in the last two years that are of the same magnitude (i.e. same amount or near the amount of the quote that you are providing.

2. Quality Control Plan Solicitation does not mention a Quality Control Plan as part of the submittal.

SOW shows (as number 3) that a Quality Control Plan is to be submitted with the written proposal. Page 4.

2. The Statement of Work provides the specifics to the solicitation, it is asking for a Quality Control Plan (QCP), please submit.

1. First, the SOW indicates the contractor must have a Wyoming Cultural Resource Use Permit. While SWCA has many permitted people in Wyoming, we were wondering if a proposal would be accepted if the Prime small business didn’t have a permit, but we conducted the fieldwork under the supervision of our permitted people.

3. The contractor submitting the quote needs to have the permit. Link below for Wyoming CRUP information. https://www.blm.gov/programs/cultural-heritage-and-paleontology/archaeology/archaeology-in-blm/permits

1. Assuming we can use our permit, can we reuse our PPQs that you should have on file?

4. Yes, you may use past PPQ’s they need to be submitted with proposal from contractor or from their customers referencing the solicitation it is for.