Updated_Attachment_7_Questions_and_Answers_0001.docx
DOCX document 14 KB Posted
- Attached to
- BLM CO DEMO / REPLACE VAULT TOILET Federal contract opportunity
- Solicitation number
- 140L4221Q0023
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Updated_Amendment_002__Attachment_7_Questions_and_Answers_0002.docx | DOCX document | |
| Sol_140L4221Q0023_Amd_0002.pdf | ||
| Sol_140L4221Q0023_Amd_0001.pdf | ||
| Attachment_8_TiogaSpecial_Vault_Specs.pdf | ||
| Attachment_2_Statement_of_Work.pdf | ||
| Attachment_1_General_Information.doc | DOC document | |
| Attachment_4_Bid_Schedule.pdf | ||
| Attachment_7_Questions_and_Answers.docx | DOCX document | |
| Attachment_6_Section_889_Reps_and_Certs.pdf | ||
| Sol_140L4221Q0023.pdf | ||
| Attachment_3_DRAWINGS.pdf | ||
| Attachment_5_Wage_Determination.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLM CO Replace Vault Toilet and Other Upgrades Questions and Answers
1. When will the Presolicitation move to Solicitation? Around June 1st
2. How quickly will it go from that point to award. We are into the construction season which is causing shortages? The solicitation is expected to run for thirty days. Then proposals will be evaluated and award and POP start is expected to be around the beginning of July.
3. Is BLM buying the prefab bathroom unit since you have it all specified or will the contractor buy it according to the specifications? Awarded vendor will be responsible for providing the prefab bathroom.
4. It says the contractor will demo the old unit but will it be drained of waste or will we have to do that as well? Awarded vendor will not have to pump/drain the old unit
Questions and Answers added 6/11/2021
5. Pre-Bid RFI #1 – Sheet C501 includes details for a steel parking stop and a steel parking delineator. Are these included in the project? if yes, please provide location and quantity.
Not anymore-just the fence
6. Pre-Bid RFI#2 – Is there a coating/paint requirement for the steel bollards associated with the fence system? If yes, please provide system details.
Fence is raw steel – no coating