Questions - Answers_0001.doc

DOC document 30 KB Posted

Attached to
ELKO SPRING SHRUB PLANTING Federal contract opportunity
Solicitation number
140L3921Q0019
Issued by
Department of the Interior Bureau of Land Management Nevada Region

View the file

Other files for this federal contract opportunity

Other files attached to ELKO SPRING SHRUB PLANTING, newest first.
File Type Posted
B03 Wage Determination_0001.pdf PDF
Sol_140L3921Q0019_Amd_0001.pdf PDF
B03 Wage Determination.pdf PDF
Bid Schedule.doc DOC document
Sol_140L3921Q0019.pdf PDF
A06 Maps.pdf PDF
A04 SOW.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number 140L3921Q0019 Elko Spring Shrub Planting Questions & Answers

Q1) It looks like the period of performance is March 1st-31st. Only working weekdays is 23 days, I imagine one person could plant 500-1000 per day depending on the site conditions, if there was no incremental weather delays that would require a minimum 2 crews of 12 each to finish the job before April. Based on your experience can you tell me if this estimate is correct?

A1) Yes, the Period of performance is March 1st through the 31st as indicated in the solicitation. It’s up to each contractor to determine how many employees would be required to meet the requirements in the period of performance requested.

Q2) I am looking at a cost per acre, can you tell me the range of prior contracts similar to this?

A2) The government cannot provide the estimated cost for this project or the average cost per acre for prior projects. Interested contractors can search on Beta.Sam (https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fbeta.sam.gov%2F&data=04%7C01%7Cmbmerritt%40blm.gov%7C0131e55e21c34491f2de08d8c9f507da%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C637481401518486529%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=QSDBNctVAdyZlWb8yV0kst117G%2Bv%2FLs0CxmRUTtXPAo%3D&reserved=0 ) in Contract Opportunities (FBO) or Contract Data Reports (FPDS Reports) for previous contract information if interested.

Q3) Can it be billed incrementally or just once when the project is complete?

A3) Progress payments would be authorized as work is completed.

Q4) In the past how many solicitors like this are filled by H-2A visa holders?

A4) The BLM doesn't have access to this information.

Q5) What is the Davis Bacon for people planting- $10.95?

A5) This project is subject to the Service Contract Act, no the Davis Bacon Act. A new Wage Determination (1969-0113 Rev No 62) is added to the solicitation with this amendment. The minimum rate for tree planter, along with the Health and Welfare (fringe benefit) rate, is listed on this Wage Determination. See attached.