About this file

This is a Question and Answer document (Amendment 0002) dated March 4, 2025, for the BLM Pinto Mesa Hand Thinning and Pile project (Solicitation #140L3725Q0023) managed by the Department of the Interior Bureau of Land Management Idaho Region.

The Q&A addresses site access conditions, indicating that while access is available via gravel country roads, contractors should expect muddy conditions for the next couple of weeks. The document notes current light snowfall at the site, with accumulation expected to be minimal (1-2 inches) and likely to melt off quickly.

View the file

Other files for this federal contract opportunity

Other files attached to BLM PINTO MESA HAND THINNING AND PILE, newest first.
File Type Posted
Sol_140L3725Q0023_Amd_0003.pdf PDF
Sol_140L3725Q0023_Amd_0002.pdf PDF
Sol_140L3725Q0023_Amd_0001.pdf PDF
B09_SF30_SOW_Revision_1_03032025_0001.pdf PDF
Sol_140L3725Q0023.pdf PDF
B08_Attachment_3_Native_File_Attachments.zip ZIP file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0002 03/04/2025 Question 1: Do you happen to know how access to the site for the project is looking and is there currently any snow accumulation?

Answer 1: Access is available. Roads to the site are gravel country roads, so contractors should expect muddy roads for the next coupe of weeks. Previously dry but currently snowing. No expectation of getting more than an inch or two out at the site and should melt off.