B09_SF30_Amendment_0002_Question_and_Answer_Attachment_01_03042025_0002.docx
DOCX document 12 KB Posted
- Attached to
- BLM PINTO MESA HAND THINNING AND PILE Federal contract opportunity
- Solicitation number
- 140L3725Q0023
About this file
This is a Question and Answer document (Amendment 0002) dated March 4, 2025, for the BLM Pinto Mesa Hand Thinning and Pile project (Solicitation #140L3725Q0023) managed by the Department of the Interior Bureau of Land Management Idaho Region.
The Q&A addresses site access conditions, indicating that while access is available via gravel country roads, contractors should expect muddy conditions for the next couple of weeks. The document notes current light snowfall at the site, with accumulation expected to be minimal (1-2 inches) and likely to melt off quickly.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L3725Q0023_Amd_0003.pdf | ||
| Sol_140L3725Q0023_Amd_0002.pdf | ||
| Sol_140L3725Q0023_Amd_0001.pdf | ||
| B09_SF30_SOW_Revision_1_03032025_0001.pdf | ||
| Sol_140L3725Q0023.pdf | ||
| B08_Attachment_3_Native_File_Attachments.zip | ZIP file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0002 03/04/2025 Question 1: Do you happen to know how access to the site for the project is looking and is there currently any snow accumulation?
Answer 1: Access is available. Roads to the site are gravel country roads, so contractors should expect muddy roads for the next coupe of weeks. Previously dry but currently snowing. No expectation of getting more than an inch or two out at the site and should melt off.
File details come from the government source that posted it. Updated .