B09_Amendment_P00001_Q_A_0001.pdf
PDF 210 KB Posted
- Attached to
- GOLDIE DIVIDE CHIPPING PROJECT Federal contract opportunity
- Solicitation number
- 140L3723Q0113
About this file
This document contains questions and answers regarding Solicitation Number 140L3723Q0113 for the Goldie Divide Chipping Project being carried out by the Bureau of Land Management Idaho Region. The solicitation seeks a contractor to chip piles of cut logs from late summer/fall 2021 located within the project area. Acceptable chipping methods include track chippers, mobile tub grinders, or chippers fed by equipment. Masticators or head grinders are not allowed. The performance period runs from May 31 to July 31, 2024 to avoid disturbing nesting northern long-eared bats. The contractor must complete 95% of piles, excluding some in inaccessible steep or small areas. Interim payments will be made at 25%, 50%, 75%, and 100% completion. The contractor is responsible for mobilization and road damage but not preexisting conditions. No protected species are expected to impact work but operations remain subject to wildlife regulations. Existing gates and designated routes must be used to cross fences. No bonds are required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L3723Q0113_Amd_0002.pdf | ||
| Sol_140L3723Q0113_Amd_0001.pdf | ||
| A06_Goldie_Divide_-_chipping_overview_map.pdf | ||
| A04_SOW.pdf | ||
| Sol_140L3723Q0113.pdf | ||
| WY_WD_1979-0948_Rev__67.pdf | ||
| Clauses_140L3723Q0113.pdf | ||
| A06_Goldie_Divide_-_chipping_unit_map.pdf | ||
| B03_WD_2015-5411_Crook.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
BUREAU OF LAND MANAGEMENT
Fire and Aviation 3833 S Development Ave
Boise, Idaho 83705-5354
SOLICITATION Q&A August 8, 2023
Goldie Divide Chipping Solicitation Number 140L3723Q0113
CONTRACTOR QUESTIONS GOVERNMENT RESPONSE
1. Is the timeframe adjustable if there are weather issues?
1. End of performance period is set in stone due to NLEB ESA requirements for timing shutdown, this period would exceed a 30-day act of God, i.e., June 1st to July 31st no operations. If CO is comfortable an act of God 30 day maybe added after July 31st up to 1 year cutoff. However, understand the MOb costs in and out are solely responsibility of contractor, and government believes POP is sufficient for work completion short of an act of God.
2. What is your definition of rotting logs? 2. Bark off soft logs decayed to cores, often deformed and unable to be picked up by machinery efficiently. Grey bark off solid logs that could be picked up efficiently not considered rotting.
3. When were the piles cut? 3. Piles cut late summer fall of 2021.
4. What is the history of previous projects in this area?
4. Only history we have is the cost of manual cut and pile, which is not relevant to this project.
5. Will partial payments be allowed? 5. Yes, interim payments will be allowed at 25%, 50%, 75%, 100% of acres fully completed to spec.
6. The contract deadline states May 31, 2024. Can this be extended to July 31, 2024?
6. No May 31 is set due to no operations during NLEB an ESA endangered species pupping season June 1st to July 31st.
7. Is there any road maintenance required with this project?
7. No, not unless contractor continues to work during thaw break-up or excessively wet times and severely and negligently damages road (i.e., equipment degrading two-track to point of not being drivable once dry), contractor shall be expected to blade/return road to condition found prior to start of project. As SOW states work expected when reasonable dry or frozen, this clay area can be a little greasy after rainfall, normal rutting and use is not a concern of the government.
8. Can masticators be used or is the scope of work specific for track chippers?
8. No, as SOW states no masticators or head grinders. This is not the finished product the government is looking for. However, mobile tub grinder/chipper and feeding by equipment can also be utilized instead of track chippers, as long as SOW specifications for chips, and no chip areas are followed.
9. There are drainages within the work area which either exceed 35% slope or are otherwise inaccessible to tracked equipment. There are some piles within these inaccessible areas, will they be excluded?
9. Government is aware of small peripheral areas and individual piles in spots that equipment cannot get to, rather than confuse project map by delineating these individual piles out, which do not spatially amount to much, the government considered these addressed thru the 95% or better final product.
10. Are there any hydraulic, archaeological, or other sensitive sites present which will need to be avoided?
10. No, all resource concerns on projects are excluded or mitigated prior to project going to contract, on this project all operable areas are part of contract.
11. Are there any protected species present in the area which could result in shut down of operations due to their discovery? (i.e., nesting birds etc.)
11. There are no sensitive species present that have not been addressed during NEPA, and the government does not foresee any issues with sensitive species. All listed species have gone under consultation with USFWS for project scope as required by ESA and mitigation included (no ops June 1st to July 31st). But all stipulations regarding threatened and endangered species are subject to change and possible re-initiation of consultation based on changing policy, species status and regulations of USFWS which would be out of the control of BLM and local field office.
12. There is cross fencing throughout the project area. Can the contractor cut the fence in necessary locations to pass through with equipment, if the contractor immediately repairs the fence after passing through?
12. No, BLM has installed gates in key locations and cross fencing has gates on existing two-tracks throughout project area. BLM staff is happy to meet onsite to awarded contractor and point out the sufficient crossing points.
13. Are bonds required? 13. No