Sol_140L3723Q0083_Amd_0002.pdf
PDF 277 KB Posted
- Attached to
- FY23 UPPER SLIP RD THINNING Federal contract opportunity
- Solicitation number
- 140L3723Q0083
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A04_SOW_-_Updated_6_23_23_0001.pdf | ||
| Sol_140L3723Q0083_Amd_0001.pdf | ||
| Price_Bid_Schedule.pdf | ||
| A06_UpperSlip_-_UnitMap.pdf | ||
| B03_WD_2015-5411_Johnson.pdf | ||
| A04_SOW_-_Upper_Slip_Rd.pdf | ||
| B08_Clauses_140L3723Q0083.pdf | ||
| Sol_140L3723Q0083.pdf | ||
| A06_Vicinitiy_Map.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L3723Q0083 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LFA
BOISE ID 83705
3833 S. DEVELOPMENT AVE.
BLM FA-NTL INTRAGCY FIRE CTR(FA250)
06/12/20230002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/12/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
FY23 Upper Slip Road Thinning
Period of Performance: 07/15/2023 to 12/31/2023
The purpose of amendment 0002 is to:
1. Provide Questions & Answers from site visit on 6/22/23.
2. Extend the deadline of the solicitation from 6/30/23 to 7/6/23, at 1500 MT.
3. Provide site visit roster with handwritten Q & A.
This amendment must be acknowledged in accordance with the solicitation.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Linda Neely
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140L3723Q0083/0002
All other terms and conditions remain the same.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Upper Slip Thinning Site Visit Notes 6/22/23
140L3723Q0083
1. Cut or leave dead trees over 10” DBH.
a) Everything over 10” DBH and under 4” DBH will not be cut.
2. Fixed price to salvage specs? Asking about purchasing of log decks and if there was a fixed price.
a) Log decks will be sold a�er service contract is complete.
3. What will the cost of the decked logs be?
a) Forester will appraise log decks at the comple�on of the service contract.
4. Can the logs be mas�cated rather than decked?
a) No, all material over 4” must be decked.
5. Can Unit 3 be mas�cated rather than lop and scater?
a) Yes, contract amendment 0001 has been executed to allow mas�ca�on.
6. Can slash piles be inside the deck loca�ons?
a) Yes, as long as they are 10 feet away from the log decks.
7. Will Unit boundaries be painted/marked?
a) Yes
8. How precise will the COR be when administering the DBH measurements on cut trees?
a) COR will ac�vely visit the site during opera�ons and ensure contractor is s�cking close to proper DBH measurements.
9. Will the landing areas be marked?
a) Yes, likely with flagging.
10. Can log decks be purchased/removed from the project area during the period of performance?
a) No, log decks will stay onsite un�l service contract is complete.
Upper Slip Thinning Site Visit Notes 6/22/23
140L3723Q0083