DEAN_S_DAM_BID_SCHEDULE_mjm.pdf
PDF 8 KB Posted
- Attached to
- DEAN S DAM RECONSTRUCTION Federal contract opportunity
- Solicitation number
- 140L3619R0004
About this file
DEAN S DAM BID SCHEDULE
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PP_Questionnaire.pdf | ||
| DEAN_S_DAM_TECH_SPECS_mjm.pdf | ||
| DB_Wage_Determination_MT20180070.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item
No. Description Unit Price Total Cost
1 Mobilization & Preparatory Work 1 LS
2 Topsoil Stripping & Replacement 1 LS
3 Outlet Demolition 1 LS
4 Common Excavation 5,944 CY
5 Muck Excavation 600 CY
6 Compacted Embankment 6,420 CY
7 Filter Sand 248 CY
8 Drain Gravel 114 CY
9 Road Gravel 131 Ton
10 Riprap Slope Protection 170 Ton
11 Outlet Basin 1 LS
12 Spillway Tower and Low-Level Inlet 1 LS
13 Outlet Conduit 1 LS
14 Stabilization Fabric 900 SY
15 Lime Amended Backfill 664 CY
16 Water Control/Dewatering 1 LS
TOTAL BASE BID
Total Bid (words):
DEAN S DAM RECONSTRUCTION
SCHEDULE OF ITEMS
Quantity*
*Quantities are not guaranteed. Measurement and payment for each Bid Item is defined in Section 01150, Measurement and Payment.
TOTAL BID PRICE
\\BIL-FS\BIL-projects\26\21710-01\55Specs\BidForm.xlsx