140G0320Q0155 Amendment 5 - Final Q and A_0005.pdf
PDF 113 KB Posted
- Attached to
- DESIGN-BUILD CONCRETE ADA RAMPCONSTRUCTION PROJE Federal contract opportunity
- Solicitation number
- 140G0320Q0155
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140G0320Q0155_Amd_0005.pdf | ||
| Sol_140G0320Q0155_Amd_0004.pdf | ||
| Sol_140G0320Q0155_Amd_0003.pdf | ||
| Sol_140G0320Q0155_Amd_0002.pdf | ||
| Sol_140G0320Q0155_Amd_0001.pdf | ||
| Sol_140G0320Q0155.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140G0320Q0155 Amendment 5 P. 2 of 2
Solicitation 140G0320Q0155 Amendment 5 – Poured Concrete ADA Ramp Vendor Questions and USGS Responses
QUESTION: Do we need to follow the American barricades Act and the American Disabilities Act in design and installation?
ANSWER: The design must be compliant with both the Architectural Barriers Act and the American
Disabilities Act.
QUESTION: Does the concrete need to be broom finish?
ANSWER: Yes.
QUESTION: Do we have to strip the existing coating currently on the staircase?
ANSWER: On the stairs, no; on the platform, yes.
QUESTION: If so, do we have to recoat the entire newly poured concrete?
ANSWER: No
QUESTION: Are we being allowed to tie into existing staircase to create new landing and then ramp detail?
ANSWER: Yes
QUESTION: Does the garden area in questions need to be graded back to the height of the current asphalt curb?
ANSWER: This is design dependent.
QUESTION: During design stage will we be allowed extra time for proper survey details and access to the building to determine all threshold heights?
ANSWER: Yes
QUESTION: Are the quotes really due on Labor Day?
ANSWER: Yes; this is to allow maximum time to the vendors. The Contracting Officer will look at them Tuesday morning.