Questions_0001.docx

DOCX document 15 KB Posted

Attached to
7J--DOVER PACS SECURITY SYSTEM Federal contract opportunity
Solicitation number
140G0124Q0035
Issued by
Department of the Interior US Geological Survey Office of Acquisitions and Grants

About this file

This document contains questions and answers regarding requirements for installing a personnel access control and alarm system, as well as details of a related federal contract opportunity. The questions and answers indicate that ceilings are suspended through most of the building but the warehouse is open. No existing cable trays or wiring can be utilized. A UPS with sufficient time and power duration is required. Only equipment that can interact seamlessly with the Lenel OnGuard system will be considered. Plenum wire is acceptable. Exterior cameras are not included. Readers must be FICAM compliant and the system must be cyber secure.

The federal contract opportunity is a small business set-aside to install the personnel access control system at the Maryland-Delaware-District of Columbia Water Science Center in Dover, Delaware. The NAICS code is 334118 with a size standard of 1,000 employees. A site visit is scheduled for November 30th and quotes are due by December 8th. Vendors must register in SAM to be eligible for award of the purchase order under solicitation 140G0124Q0035.

View the file

Other files for this federal contract opportunity

Other files attached to 7J--DOVER PACS SECURITY SYSTEM, newest first.
File Type Posted
Sol_140G0124Q0035_Amd_0001.pdf PDF
USGS_Indoor_Survey_-_Dover_(02-10-22)_0001.pdf PDF
Wage_Determination_2015-4271.pdf PDF
Statement_of_Work_MDDEDC.docx DOCX document
Sol_140G0124Q0035.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers

Are Ceilings Suspended? Or Hard Lid?

Ceilings are suspended through most of the building, the warehouse is open.

Are there existing Cable Trays for wiring above ceilings? No Cable trays.

Can Existing Wiring be utilized? There is no existing wiring that can be used.

Is a “UPS” required? If so, What Time/Power Duration is required? Yes

Are “Or Equal” Equipment substitutions allowed? Equipment substitutions will only be allowed if they can interact seamlessly with the Lenel OnGuard system in Baltimore.

Is “Plenum Wire” acceptable? Plenum wire is acceptable.

Is “After Hours Access” for said work, available to contractor at no add’l cost to the Gov’t? No

What is the height of Exterior Cameras? (If any) Cameras Are not included.

Please provide a list of equipment to be installed. Refer to the Statement of Work

Is there an incumbent vendor who has been servicing the existing system? N/A

If so, what is the most current contract number and amount? N/A

Is there any requirement for the readers to be FICAM-compliant? Readers must be FICAM compliant.

Are there any requirements for the system to be cyber-secure? System must be cyber secure (SSL/TLS latest version, Certificates must be issued through a valid certificate authority, Single sign-on or PIV enabled login)