Atch 3 Gavins Pt Pond Liners Submittals

View the file

Other files for this federal contract opportunity

Other files attached to INSTALLATION OF GEOMEMBRANE LINERS, newest first.
File Type Posted
Sol_140F0619R0006_Amd_0004.pdf PDF
Garvins_Pt_Pond_Liner_Spec_02540_Revised.pdf PDF
Sol_140F0619R0006_Amd_0003.pdf PDF
Sol_140F0619R0006_Amd_0002.pdf PDF
Sol_140F0619R0006_Amd_0001.pdf PDF
Atch_4_DBA_Wage_Det_Yankton_SD.pdf PDF
Atch_1_Gavins_Pt_Pond_Liners_Specifications.pdf PDF
Sol_140F0619R0006.pdf PDF
Atch_5_Gavins_Pt_Pond_Liners_Past_Perf_Quest.doc DOC document
Atch_2_Gavins_Pt_Pond_Liners_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHEET 1 OF 3

A - Approved as Submitted.

B - Approved, Except as Noted. No Resubmission Required.

C - Approved, Except as Noted. Resubmission Required.

D - No Action Taken. See Comments. Resubmission Required.

E - disapproved. See Comments. Resubmission Required.

PROJECT NAME: Replace Fish Pond Liners ENGR. PROJECT NO.: 18-026 LOCATION: Gavins Point National Fish Hatchery CONTRACT NO.:

CONTRACTOR:

Spec.

Section Number

Spec.

Paragraph No.

Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)

Contractor's Submittal Number

Date Submitted

Action Taken

Date Resubmitted

Action Taken Comments

01300 1.02 A Contractor's construction schedule

01300 1.03 C Samples

01300 1.04 A Manufacturer's cut sheets containing detailed specifications and performance data

01300 1.05 C As-built drawings

01300 1.07 A Guarantees, warranties, and certificates per Section 01700

01400 1.03 A.1 Name & Qualification of Testing Laboratory

02220 1.05 A Certified test results for compaction

02540 1.03 A Manufacturer's Product Data

02540 1.03 B Shop Drawings

02540 1.03 C Samples

02540 1.03 D Installation Instructions

02540 1.03 E Manufacturer's Certification

02540 1.03 F Manufacturer's Warranties

02540 2.02 B Approval in Writing of Vendor

PROJECT SUBMITTAL LIST

SHEET 2 OF 3

B - Approved, Except as Noted. No Resubmission Required.

C - Approved, Except as Noted. Resubmission Required.

D - No Action Taken. See Comments. Resubmission Required.

E - disapproved. See Comments. Resubmission Required.

PROJECT NAME: Replace Fish Pond Liners ENGR. PROJECT NO.: 18-026 LOCATION: Gavins Point National Fish Hatchery CONTRACT NO.:

CONTRACTOR:

Spec.

Section Number

Spec.

Paragraph No.

Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)

Contractor's Submittal Number

Date Submitted

Action Taken

Date Resubmitted

Action Taken Comments

SHEET 3 OF 3

B - Approved, Except as Noted. No Resubmission Required.

C - Approved, Except as Noted. Resubmission Required.

D - No Action Taken. See Comments. Resubmission Required.

E - disapproved. See Comments. Resubmission Required.

PROJECT NAME: Replace Fish Pond Liners ENGR. PROJECT NO.: 18-026 LOCATION: Gavins Point National Fish Hatchery CONTRACT NO.:

CONTRACTOR:

Spec.

Section Number

Spec.

Paragraph No.

Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)

Contractor's Submittal Number

Date Submitted

Action Taken

Date Resubmitted

Action Taken Comments