Govt_Response_to_RFQ_No_Q0077_0001.docx
DOCX document 16 KB Posted
- Attached to
- BIA/SNR/SAN JUAN RIVER IRRIGATION PROG Federal contract opportunity
- Solicitation number
- 140A0924Q0077
About this file
This document appears to be a Government Response to Request for Quote (RFQ) No. 140A0924Q0077 issued by the Department of the Interior Bureau of Indian Affairs Navajo Region for the BIA/SNR/SAN JUAN RIVER IRRIGATION PROGRAM. The government has provided responses to several questions from the contractor regarding the contract requirements. Key details include that the government will provide a geodatabase schema for the contractor to update, a list of permittees and their contact information if available, and existing shapefiles for farm plot locations and structures that will need to be updated. The contractor will be required to conduct onsite visits with the permittees and local farm board members. The disturbance area for fence construction/upgrade is limited to 50 feet in width.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140A0924Q0077_Amd_0001.pdf | ||
| 1452_IEE.docx | DOCX document | |
| Book1_Price_Schdule.xlsx | XLSX spreadsheet | |
| BuyIndianRepresentation.pdf | ||
| Combined_Synsopsis_ArcGIS.docx | DOCX document | |
| Sol_140A0924Q0077.pdf | ||
| 20240904173212.pdf | ||
| 15-5445_SCA_San_Juan_County.txt | TXT text file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ No. 140A0924Q0077
· Will the BIA provide a schema for the contractor to create a geodatabase for data collection?
Govt. Response: Yes. The contractor will update the schema currently in place.
· Will the BIA provide a list of all permittees and their contact information?
Govt. Response: Yes, if available.
· Will the BIA provide existing shapefiles for farm plot locations and known structures?
Govt. Response: Yes, shapefiles will need to be updated to current farmland in production.
· Will the contractor be required to conduct onsite visits with the permittees to gather some of the information?
Govt. Response: Yes, and the local farm board member if available.
· Can we assume that the disturbance area for fence construction/upgrade has a width of no more than 50 feet?
Govt. Response: Yes.