Statement_of_Requirements_BWMS.docx

DOCX document 19 KB Posted

Attached to
Ballast Water Treatment System Federal contract opportunity
Solicitation number
1305M2-18-Q-NMAN-0059
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

Statement of Requirements

View the file

Other files for this federal contract opportunity

Other files attached to Ballast Water Treatment System, newest first.
File Type Posted
529-6233819_Reference_2.pdf PDF
521-6631018_Reference_1.pdf PDF
RFQ_1305M2-18-Q-NMAN-0059_BWMS.pdf PDF
Fire_-AM-_Ballast_Pump_Reference_3.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ballast Water Management System June 2018

NOAA REQUIREMENTS: Ballast Water Management System

1.0 Background: The National Oceanic and Atmospheric Administration (NOAA), Eastern Region Acquisition Division on behalf of Office of Marine and Aviation Operations (OMAO) requires the purchase of a Ballast Water Management System that complies with 33 CFR 151.1510 and 151.2025 which states vessels are required to install and operate a Ballast Water Management System (BWMS) that has been approved by the U.S. Coast Guard under 46 CFR part 162. In order to comply, OMAO intends to purchase a Ballast Water Management System that complies with these regulations on vessels for which these regulations pertain.

This Statement of Requirements for a BWMS is specific to NOAA Ship OKEANOS EXPLORER. OMAO expects to purchase four (4) additional systems as options that will be of a similar size and scope as the OKEANOS EXPLORER over the next five (5) years.

1.1 SCOPE: NOAA Ship Okeanos Explorer Ballast Water Management System

2.0 References:

2.1 Drawing 623-3819 – Bilge and Ballast System Diagram

2.2 Drawing 663-1018 – Firemain System Arrangement

2.3 Aurora Pump – Fire & Ballast Pump Technical Manual

3.0 Government Furnished Material:

None.

4.0 BWMS Requirements:

4.1 The Ballast Water Management/Treatment System shall comply with 33 CFR 151.1510 and 33 CFR 151.2025 and have approval by the U.S. Coast Guard under 46 CFR 162. The BWMS shall:

4.1.1Have Full Approval of the U.S. Coast Guard IMO approval
4.1.2Be of the Ultraviolet/Filtration Type
4.1.3Be capable of operating at pressures between 95
and 140 psi
4.1.4Be capable of operating at flow rates between
35 and 90 m3/hour
4.1.5Have Remote Control Panel Capabilities
4.1.6Be able to fit into a space 96 inches (Wide),

36 inches (deep), 88 inches tall

4.1.7Consume no more than 25 kW of power
4.1.8Have a Backflush filter pump
4.1.9Have Bypass capabilities
4.1.10Be able to convert shipboard power (450v, 60

Hz) power to power requirements necessary to operate system.

4.2. Manufacturer Requirements. The Manufacturer shall:

4.2.1Provide technical support for equipment and spare parts available within 24 hours for NOAA ships homeported on the East Coast, West Coast, and Gulf Coast.
4.2.2Provide a system the manufacturer has in production with an historic record of having been fully tested and successfully installed on a minimum of 10 vessels of equal or larger size than NOAA Ship OKEANOS EXPLORER.
4.2.3Provide the manufacturer’s recommended allotment of spares for the BWMS and all documentation associated with the parts.

5.0 Quality Assurance and Warranty.

5.1 The COR will conduct an inspection of compliance with the requirements upon receipt.

5.2 Warranty: The unit shall be warranted, free of defects in materials or workmanship for at least one year following installation on the vessel. Note: The warranty does not start FOB the factory, but starts following installation and testing on the vessel.

6.0 Documentation. The following documentation shall be

provided. (All digital copies shall be in Microsoft WORD or Adobe PDF format. All documentation is to be in English without Redundant information in other languages.)

6.1 U.S. Coast Guard certificate of approval for the Filtration +UV System Type.

END OF STATEMENT OF REQUIREMENTS