Amendment 002

View the file

Other files for this federal contract opportunity

Other files attached to Tatham Ridge Fuels Project, newest first.
File Type Posted
Tatham_Fire_Plan.pdf PDF
Amendment_001_129AC718Q0048.pdf PDF
Maps.pdf PDF
77-0727,_rev._55,_04092018.pdf PDF
Tatham_Ridge_solicitation,_129AC718Q0048.pdf PDF
Tatham_Ridge_solicitation,_129AC718Q0048.pdf PDF
Maps.pdf PDF
77-0727,_rev._55,_04092018.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

129AC718Q0048

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

9AC7

REDDING CA 96002

3644 AVTECH PARKWAY SUITE 180

R5 NO-CAL ACQ SERVICE AREA NCASA

USDA FOREST SERVICE

07/02/20180002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/27/2018

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return ______1____________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

KATHERINE E. PASINI

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

TATHAM RIDGE THIN AND HAND PILE

MENDOCINO NATIONAL FOREST

Amendment 2 hereby removes and replaces page 25 with the attached amended page 25.

Response due date is hereby extended until 1:30pm on Thursday August 2, 2018.

All other requirements remain unchanged.

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

7/30/2018

X

Tatham Ridge Fuels Project, 129AC718Q0048 Amended Page 25

Retain all existing downed logs (20 inches in diameter or greater at the large end and at least 10 feet in length not to exceed 4 logs per acre). Snags shall not be cut unless they present an immediate hazard to operations in the project area. Cut snags shall be left in place on the ground.

All trees over 12 feet tall that are not cut shall be pruned of lower branches. Branches shall be pruned from the ground to 6 feet high. Pruning shall be conducted in such a way that there is no damage to the main stem of the tree.

All cut material over 1 inch in diameter shall be piled (except for cut snags), unless terrain and tree spacing does not allow for proper pile location. Sections of tree boles over 10 inches in diameter may be bucked to 6—8 feet sections, and stacked separately from the burn pile and/or scattered on the forest floor. No “jackstrawing” of cut and scattered logs shall be allowed. All piles shall be constructed by laying limbs, stems, cut boles, and other slash in the pile so as to be parallel with each other and up and down the slope to prevent material from rolling downhill during pile ignition. Each pile shall include an area of small sized slash near the bottom of the pile to provide kindling for prompt ignitions and to aid in combustion of larger slash.

Maximum pile size shall be 6 feet in diameter by 6 feet in height. All material shall be cut to a length such that it can be placed in a pile without exceeding these maximum dimensions (see Pile Construction figure below). There may be instances where larger piles are acceptable. For example, in a large opening, 50 feet in diameter, a pile may be 10 feet in diameter by 6 feet high. The Contractor shall contact the COR if suitable locations are found for approval to create these larger piles. In other areas, it may be beneficial to remove a leave tree if too much cut material is present and create a larger opening for a larger pile. The COR shall be contacted to give approval of such locations.

Other suitable and preferred locations are on existing skid trails scattered throughout the units. Piles shall be constructed at least 15 feet apart, unless the COR gives his/her consent. All hand piles shall be covered with 4ft X 4ft, 6 mil thick plastic to promote drying and ignitions. Brush/slash shall be piled on the plastic to ensure it stays in place. Piles shall be placed so that flames from the pile will not impact leave trees.

Piles shall not be closer than 10 feet from leave trees and felled snags. Piles shall not be closer than 20 feet from unit boundaries, edges of roads or trails, meadows, or private ground. Piles shall be located a minimum of 5 feet away from stream channels, springs, or seeps. Not all water features within the project area have been identified therefore pile locations shall be determined as water features are discovered. Pile locations may be approved by the COR or other designated Government representative in the field. Slash shall not be piled or placed on logs, on stumps larger than 2 feet in diameter, in ditches, against trees, or left within 25 feet of roads. All open roads shall be kept free of thinning slash.

11. Inspections

Measurable Performance Standard in Visual Inspection Procedures

Amend 2_Tatham Ridge working solicitation rev 7-25-18.pdf
1. FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
2. FAR 52.212-4 Contract Terms and Conditions—Commercial Items (Jan 2017)
3. FAR 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders - Commercial Items (JAN 2018)
4. AGAR 452.215-73 Postaward Conference (NOV 1996)
5. Employment of Eligible Workers
Employment of Eligible Workers
Workforce Certification
H-2B Workers: (http://www.foreignlaborcert.doleta.gov/)
MSPA Workers: (http://www.dol.gov/whd/mspa/)
6. Scope of Contract
7. Location and Access
Location
Access
8. Period of Performance
9. Unit Descriptions (Mandatory Units)
Optional Units
10. Specific Work Requirements
Thinning Prescription:
Snags and Logs:
11. Inspections
12. Acceptable Quality Level (AQL)
13. Re-inspection and Acceptance
14. Penalties and Incentives
15. Unique Factors
Motorized Equipment.
Safety
Protection, Use and Maintenance of Improvements
Landscape Preservation
Endangered Species
Preservation of Historical and Archeological Resources
Special Situations
Environmental Interruption of Work
16. Definitions
17. Government-Furnished Property
18. Contractor Personnel and Equipment
Contractor On-Site Representative
Work Foreman
Contractor Employees
Subcontractors
19. Acceptable Quality Level for Tasks and Critical Subtasks
20. Means and Methods of Quality Measurement
Contractor Quality Control
Rework of a Unit
Government Re-inspection upon Contractors Request
Acceptance
21. Penalties and Incentives
22. Contract Administration Data
Notice to Proceed
Invoices
Final Cleanup
Contract Release
Contractor Performance Assessment Reporting System (CPARS)
23. List of Attachments and Exhibits
24. 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)
25. FAR 52.216-1 Type of Contract. (APR 1984)
26. FAR 52.237-1 Site Visit (Apr 1984)
27. Organized Site Visit
28. AGAR 452.219-70 Size Standard and NAICS Code Information. (SEP 2001)
29. Electronic Submissions
30. Supplemental Instructions for Submission of Offers and Other Information
31. Evaluation Criteria
32. Award Determination
33. FAR 52.212-3 Offeror Representations and Certifications-Commercial Items (NOV 2017)