1._Project_Specs_FSSS_Underwood.pdf
PDF 864 KB Posted
- Attached to
- Underwood Road Patching & Chip Sealing Federal contract opportunity
- Solicitation number
- 129AC718Q0042
About this file
Project Specs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 3._Underwood_PAL_Fire_Plan.pdf | ||
| 2._Underwood_paving_maps_final.pdf | ||
| 4._CA9,_mod_7,_04062018.pdf | ||
| RFQ_Underwood_Mtn_Chipseal_129AC718Q0042_Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNDERWOOD ROAD PATCHING & CHIPSEALING
129AC718Q0042
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02(a) Government-provided sources
105.02(a) Contractor-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.02 Protection and Restoration of Property and Landscape
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
151 - Mobilization
155 - Schedules for Construction Contracts
155 Delete
156 - Public Traffic
171 - Weed and Disease Prevention
301 - Untreated Aggregate Courses
301 Title Change
301.05 Compacting
301.10 Payment
404 – Minor Hot Asphalt Concrete
404 Deletions
404.01 Description
404.02 Materials
404.03 Maintenance Requirements
404.04 Measurement
404.05 Payment
409 - Asphalt Surface Treatment
409.02 Material
409.06 Weather
409.06 Date & Time
409.13 Acceptance
Table 409-4 Sampling and Testing Requirements
412 - Asphalt Tack Coat
635 - Temporary Traffic Control
635.03 General
702 – Asphalt Material
702.01 Asphalt Binder
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the FAR (Federal Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007 http://www.nist.gov/
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
101.04_nat_us_11_06_2007
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.02(a) Contractor-provided sources.
All material (e.g., soil, gravel, sand, borrow, aggregate, etc.) transported onto National Forest
System land or incorporated into the work will be weed-free. The Contracting Officer may request written documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor.
A Forest Service weed specialist will inspect proposed sources to determine weed-free status.
Provide the Contracting Officer written notification of proposed material sources __5__ days prior to use. Written approval of the specific source will be provided to the contractor. If weed species are present in the proposed source, appropriate mitigation measures may allow conditional use of the source as required by the Contracting Officer.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.10_05_us_05_04_2007
107.02 Protection and Restoration of Property and Landscape
Add the following:
Meet the requirements chapters 10, 11, and 12.2 in their entirety of “Water Quality Management for National Forest System Lands in California Best Management Practices” dated September
2000.
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
Exact time and location of spill including a description of the area involved.
Containment procedures.
Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
151 - Mobilization
151.00_01_us_10_11_2006
Delete Section 151 in its entirety and replace with the following.
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.
Construction Requirements
Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.
Notify the CO in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the CO.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either
Contractor or Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.
Measurement
151.02 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.
Measure mobilization according to Subsection 109.02.
Payment
151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule.
Payment will be full compensation for the work prescribed in this Section. See Subsection
109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5
Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
Include all costs associated with the initial cleaning of equipment in the unit bid price for
Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.00_nat_us_04_17_2007
Delete Section 156 in its entirety and replace with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Construction sign panels 633
Retro-reflective sheeting 718.01
Temporary concrete barrier 618
Temporary plastic fence 710.11
Temporary traffic control devices 718.22
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed _4_ hours at any one time followed by an open period of no less than _15__ minutes.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the
MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting
Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services
Association, the National Safety Council, the International Municipal Signal
Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).
Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least
10 days in advance.
Table 156-1
Temporary Road Closures
Road
Number
From
Terminus
To
Terminus
Maximum
Consecutive
Days of
Closure
Minimum
Consecutive
Days Open
N/A N/A N/A N/A N/A
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.
171 - Weed and Disease Prevention
171.00_nat_us_03_30_2005
Description
171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest
System lands.
Material
171.02 Conform to the following Subsection:
Water 725.01
Construction Requirements
171.03 General . Notify the CO in writing at least 5 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Perform all work at a location designated on the plans or other locations approved in writing.
Provide the CO with an opportunity to monitor the washing and inspection.
171.04 Equipment. Use a high pressure washing system.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment.
Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.
Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
171.08 Do not measure weed prevention for payment.
Payment
171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for
Section 151-Mobilization.
301 - Untreated Aggregate Courses
301.00_nat_us_03_03_2005
301 Title Change.
Change the title to: Section 301 Aggregate Courses
301.05_nat_us_05_17_2005
301.05 Compacting
Delete and replace with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box
7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box
7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
301.10_nat_us_03_03_2005
301.10 Payment
Delete the following:
“adjusted according to Subsection 106.05”
404 – Minor Hot Asphalt Concrete
404.02_nat_us_07_03_2007
404 Deletions
Delete and replace the complete specification
404.01 Description
a. This work consists of patching potholes, deep patching of asphalt surfaces, skin patching of asphalt surfaces, and patching asphalt berms.
b. The work includes preparing the area to be patched, furnishing and placing all necessary materials.
404.02 Materials
Materials used for asphalt patching shall conform to the requirements in Sections 702.
Bituminous mixtures shall be approved by the Government.
404.03 Maintenance Requirements
a. Deep Patching
1. Existing materials shall be removed to a minimum of two (2) inches below the bottom of the asphalt surfacing or as necessary to reach firm support, but limited to maximum eighteen (18) inches depth. If firm support for a patch is not available, the hole shall be barricaded and the Government shall be notified. Prior to the Contractor placing any materials, Government will decide on any corrections to be made.
2. The edges of the prepared hole shall be extended to form a vertical face in non-fractured asphalt surfacing. The prepared hole shall be rectangular in shape and cleaned of all loose material. The bottom and faces shall be sprayed with an emulsified asphalt.
3. Prepared holes shall be patched or barricaded immediately.
4. The hot bituminous mixture shall be placed and compacted thoroughly with hand tampers, mechanical tampers, or rollers.
5. Finished surface shall be compacted with suitable vibratory roller. Upon completion, the compacted patch shall be between one quarter (1/4) inch and one half (1/2) inch above the level of the adjacent pavement.
b. Skin Patches
1. Prior to skin patching, potholes shall be patched.
2. Minor depressions, light raveling, or surface checking at scattered locations shown on the drawings or marked on the ground shall be treated by applying a skin patch.
3. Prior to skin patching, the surface shall be cleaned of loose and deleterious material, then sprayed with emulsified asphalt at the rate of 0.1 gallons per square yard. The emulsified asphalt tack coat will be considered incidental to the patching materials. No bituminous mixture shall be placed until the prepared surface is approved by the Government.
4. Hot bituminous mixture shall be distributed uniformly in layers not to exceed two (2) inches compacted depth. When multiple layers are ordered, joints shall be offset at least six (6) inches between layers.
5. Each layer shall be compacted with suitable vibratory roller.
6. The completed patch shall not have abrupt transitions which adversely affect the steering of a passenger car. The surface must be at least as smooth as the adjacent pavement after twenty-four (24) hours of exposure to traffic.
c. Potholes
1. Surfacing material, loose aggregate, and other debris shall be removed from potholes prior to patching.
2. The cleaned pothole shall be sprayed with emulsified asphalt.
3. The prepared pothole shall be filled with a hard setting hot bituminous mixture and compacted with hand tampers, mechanical tampers, or wheel rolled by deliver vehicles. The finished patch shall not protrude more than one half (1/2) inch above the adjacent surface.
d. Disposal
All materials removed from potholes, patches, and berms shall be disposed of in areas designated by the Government.
404.04 Measurement
a. Bituminous Mixture
1. Ton Measure – The quantity of mixture will be the number of tons in the accepted work. Bituminous materials incorporated into the mixture will be incidental to the item. Any material rejected in the field as not meeting specifications shall be deducted based on estimated quantities. Rejected quantities shall be reconciled between the Government and the Contractor each day. If not reconciled each day, the Government’s figures will apply.
b. The following work and materials are incidental:
1. Cleaning of surfaces.
2. Watering and compaction of aggregate.
3. Compaction of bituminous mixture.
4. Material removal and disposal.
5. Emulsified asphalt for tack coat.
6. Crushed aggregate backfill material.
404.05 Payment
a. The accepted quantities will be paid for at the contract unit price shown in the
Schedule of Items.
b. Payment will be made under:
Pay Item Pay Unit
Hot Asphalt Mix Ton
409 - Asphalt Surface Treatment
409.02_nat_us_05_12_2004
409.02 Material.
When designated, conform to applicable State department of transportation asphalt cement or emulsified asphalt requirements.
409.06_nat_us_05_12_2004
409.06 Weather.
Delete the first paragraph and replace with the following:
Apply surface treatments with aggregate only when ambient air and surface temperatures are above 60 °F and rising in the shade, when the weather is not foggy or rainy, and when rain is not forecast for at least 24 hours after application.
409.06 Date & Time.
Add the following.
Construct fog seal and single-course surface treatments between June 1st and September 1st and multiple-course surface treatments between June 1st and September 1st.
409.13 Acceptance
Delete the 2nd paragraph and replace with the following:
Aggregate gradation for asphalt surface treatment will be evaluated under Subsection 106.04.
Table 409-4 Sampling and Testing Requirements.
Delete the last cell (4th) under Sampling Frequency and replace with the following:
1 per tanker truck and 1 per trailer
Delete the 2nd and 3rd cell under Type of Acceptance and replace with the following:
Measured and tested for conformance (106.04)
412 - Asphalt Tack Coat
412.07_nat_us_07_03_2007
412.07 Acceptance
Delete the first paragraph and replace with the following:
Emulsified asphalt will be evaluated under Subsections 106.02, 106.03, and 702.07.
635 - Temporary Traffic Control
635.03_nat_us_05_13_2004
635.03 General.
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
702 – Asphalt Material
702.01 Asphalt Binder
Delete the first sentence add the following:
Performance graded (PG) asphalt binder shall conform to the following Standard
Specifications, State of California:
Performance Graded Asphalt Binder
Specification
Grade
Property AASHTO
Test
Method
PG
58-22a
64-10
64-16
64-28
70-10
Original Binder
Flash Point, Min. °C T48 230 230 230 230 230
Solubility, Min. % b T44 99 99 99 99 99
Viscosity at 135°C, c
Max., Pa·s
T316
3.0
Dynamic Shear, Test Temp. at 10 rad/s, °C
Min. G*/sin(delta), kPa
T315
1.00
RTFO Test e, Mass Loss, Max., %
T240
RTFO Test Aged Binder
Dynamic Shear, Test Temp. at 10 rad/s, °C
Min. G*/sin(delta), kPa
T315
2.20
Ductility at 25°C
Min., cm
T51
PAV f Aging, Temperature, °C
R28
RTFO Test and PAV Aged Binder
Dynamic Shear, Test Temp. at 10 rad/s, °C
Min. G*sin(delta), kPa
T315
22 d
31 d
28 d
22 d
34 d
Creep Stiffness, Test Temperature, °C
Max. S-value, MPa
Min. M-value
T313
-12
0.300
-6
-18
0.300
Notes:
a. For use as asphalt rubber base stock for high mountain and high desert area.
b. The Engineer will waive this specification if the supplier is a Quality Supplier as defined by the Department's "Certification Program for Suppliers of Asphalt."
c. The Engineer will waive this specification if the supplier certifies the asphalt binder can be adequately pumped and mixed at temperatures meeting applicable safety standards.
d. Test the sample at 3°C higher if it fails at the specified test temperature. G*sin(delta) shall remain 5000 kPa maximum.
e. "RTFO Test" means the asphaltic residue obtained using the Rolling Thin Film Oven
Test, AASHTO Test Method T240 or ASTM Designation: D 2872.
f. "PAV" means Pressurized Aging Vessel.