Question_&_Answers_1.docx
DOCX document 12 KB Posted
- Attached to
- Construction -Black Kettle Replacement Fishing/Boating Dock Federal contract opportunity
- Solicitation number
- 1283D519Q4001
About this file
Question & Answers 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question_&_Answers_3.docx | DOCX document | |
| Question_&_Answers_2.docx | DOCX document | |
| Solicitation_-_Black_Kettle_Fishing_and_Boat_Dock_Replacement.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) What kind of water level changes do these lakes experience?
a) Do they fluctuate more than 6-8’?
They fluctuate at most 6’
2) What is the water depth where the ponds will be installed?
Water depth is 5-10 feet
3) Our dock production schedule is out to November right now. What is the expected completion date for these docks? Is there some flexibility in the dates?
We are flexible on delivery/install dates.