Specifications.docx

DOCX document 145 KB Posted

Attached to
Mimbres Admin Site Water Tank Replacement Federal contract opportunity
Solicitation number
12837120Q0086
Issued by
Department of Agriculture Forest Service R3-Southwestern Region

View the file

Other files for this federal contract opportunity

Other files attached to Mimbres Admin Site Water Tank Replacement, newest first.
File Type Posted
WD NM20200012 02142020.pdf PDF
SF 1442.pdf PDF
Sol_12837120Q0086.docx DOCX document
Mimbres Water Tank Site Map.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gila

Specifications Package

Project:Mimbres AS Water Tank Replacement
District:Wilderness Ranger District
Region:Southwest Region 03
Project Address:Wilderness Ranger District
3697 Highway 35 N

Mimbres, NM 88049

Mimbres AS Water Tank Replacement

21 | Page Table of Contents

SUBMITTAL REGISTER3
SECTION 00 01 15 – LIST OF DRAWINGS AND SPECIFICATIONS5
SECTION 00 50 00 – CONTRACTING FORMS AND SUPPLEMENTS7
SECTION 01 11 00 – SUMMARY OF WORK13
SECTION 01 14 00 – WORK RESTRICTIONS15
SECTION 01 22 13 – UNIT PRICES MEASUREMENT AND PAYMENT17
SECTION 01 33 00 – SUBMITTAL PROCEDURES20
SECTION 01 42 13 – ABBREVIATIONS AND ACRONYMS25
SECTION 01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL27
SECTION 01 77 00 – CLOSEOUT PROCEDURES28
SECTION 01 78 00 – CLOSEOUT SUBMITTALS30
SECTION 09 91 13 – EXTERIOR PAINTING31
SECTION 31 23 16 – EXCAVATION33
SECTION 31 23 23.13 – BACKFILL35
SECTION 31 23 23.23 – COMPACTION38
SECTION 33 05 16.13 – PRECAST CONCRETE UTILITY STRUCTURES40
SECTION 33 05 26 – UTILITY IDENTIFICATION42
SECTION 33 11 13.23 – PLASTIC PUBLIC WATER UTILITY DISTRIBUTION PIPING43
SECTION 33 12 16 – WATER UTILITY DISTRIBUTION VALVES47
SECTION 33 13 00 – DISINFECTING OF WATER UTILITY DISTRIBUTION49
SECTION 33 16 13 – ABOVEGROUND WATER UTILITY STORAGE TANKS51

SUBMITTAL REGISTER

Contract Document Reference
Description

Item Submitted

Paragraph
Submittal Type (1)
For (2)
No. of Copies
Contractor
Government Action
Specification Section Number
Drawing Sheet Number
Variance (Y/N)
Date Submitted
Date Returned
Action Code (3)
Reviewed By

01 14 00

Construction Schedule
1.3
SD-01
GA
2

01 78 00

As-Built Drawings
1.3.A
SD-11
GA
2

09 91 13

Exterior Paint Data
2.1.A
SD-03
FIO
2

09 91 13

Exterior Primer Data
2.1.A
SD-03
FIO
2

09 91 13

Exterior Paint Color Samples
2.1.C
SD-04
GA
2

31 23 23.13

Select Backfill Material
2.1.C
SD-03
FIO
2

31 23 23.13

Bedding Course Material
2.1.H
SD-03
FIO
2

31 23 23.23

Lab Moisture-density Tests
3.1.A
SD-06
FIO
2

31 23 23.23

Field Compaction Tests
3.3.B
SD-06
FIO
2

33 05 16.13

Precast Concrete Box
2.1.A
SD-03
FIO
2

33 11 13.23

HDPE Piping
2.2.A
SD-03
FIO
2

33 11 13.23

HDPE Joint Fusion Certificate
3.2.A.3
SD-07
GA
2

33 11 13.23

Pressure Test Results
3.4.M
SD-06
FIO
2

33 13 00

Disinfection Test Report
3.2
SD-06
FIO
2

33 16 13

Tank Design Certification
2.1.A
SD-07
FIO
2

33 16 13

Tank NSF/ANSI 61 Certification
2.1.B
SD-07
FIO
2

33 16 13

Tank Welder Certification
2.1.C
SD-07
FIO
2

33 16 13

Tank Warranty Certificates
2.1.D
SD-07
FIO
2

33 16 13

Tank Component Colors
3.3
SD-04
GA
2

33 16 13

Tank, Foundation & Anchoring
2.2
SD-02
GA
2

(3) Action Codes:

A – Approved B – Approved, except at noted (no resubmission) C – Approved, except as noted (resubmission req’d) D – Will be returned by separate correspondence E – Disapproved (resubmission req’d) F – Receipt Acknowledged (no resubmission) X – Receipt Acknowledged, does not comply with contract requirements, as noted (resubmission req’d)

(1) Submittal Type:

SD-01 – Preconstruction

SD-02 – Shop DrawingsSD-07 – Certificates
SD-03 – Product DataSD-08 – Manufacturer’s Instructions
SD-04 – SamplesSD-09 – Manufacturer’s Field Reports
SD-05 – Design DataSD-10 – O&M Data
SD-06 – Test ReportsSD-11 – Closeout

(2) For:

FIO – For Information Only GA – Government Approval

SECTION 00 01 15 – LIST OF DRAWINGS AND SPECIFICATIONS

GENERAL

LIST OF DRAWINGS

Drawings: Drawings consist of the Contract Drawings and other drawings listed on the Table of Contents page of the separately bound drawing set titled Mimbres AS Water Tank Replacement, dated 03/01/2020, as modified by subsequent Addenda and Contract modifications.

List of Drawings: Drawings consist of the following Contract Drawings and other drawings of type indicated:

SHEET 1 – TITLE SHEET

SHEET 2 – EXISTING SITE PLAN & DEMO

SHEET 3 – NEW TANKS SITE PLAN

SHEET 4 – CONSTRUCTION DETAILS

LIST OF SPECIFICATIONS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

Section 00 01 15LIST OF DRAWINGS AND SPECIFICATIONS
Section 00 50 00CONTRACTING FORMS AND SUPPLEMENTS

DIVISION 01 – GENERAL REQUIREMENTS

Section 01 11 00SUMMARY OF WORK
Section 01 14 00WORK RESTRICTIONS
Section 01 22 13UNIT PRICES MEASUREMENT AND PAYMENT
Section 01 33 00SUBMITTAL PROCEDURES
Section 01 42 13ABBREVIATIONS AND ACRONYMS
Section 01 74 19CONSTRUCTION WASTE AND MGMT DISPOSAL
Section 01 77 00CLOSEOUT PROCEDURES
Section 01 78 00CLOSEOUT SUBMITTALS

DIVISION 09 – FINISHES

Section 09 91 13 EXTERIOR PAINTING

DIVISION 31 – EARTHWORK

Section 31 23 16EXCAVATION
Section 31 23 23.13BACKFILL
Section 31 23 23.23COMPACTION

DIVISION 33 – UTILITIES

Section 33 05 16.13PRECAST CONCRETE UTILITY STRUCTURES
Section 33 05 26UTILITY IDENTIFICATION
Section 33 11 13.23PLASTIC PUBLIC WATER UTILITY DIST. PIPING
Section 33 12 13.13WATER SUPPLY BACKFLOW PREVENTER ASSEMBLIES
Section 33 12 16WATER UTILITY DISTRIBUTION VALVES
Section 33 12 19WATER UTILITY DISTRIBUTION HYDRANTS
Section 33 13 00DISINFECTING OF WATER UTILITY DISTRIBUTION
Section 33 16 13ABOVEGROUND WATER UTILITY STORAGE TANKS

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 00 01 15

SECTION 00 50 00 – CONTRACTING FORMS AND SUPPLEMENTS

1. GENERAL

SUMMARY

This section consists of standard forms required during the course of the project. It is not intended to be a full and complete list of forms, but typical forms used during a project.

All forms are attached to this specification section. Electronic copies available upon request.

PRE-CONSTRUCTION FORMS

Standard Form (SF) 1413 – STATEMENT AND ACKNOWLEDGMENT Required for each individual subcontractor for the project.

Must be submitted prior to the subcontractor(s) starting a feature of work, and approved in writing by the Contracting Officer.

PROGRESS AND FINAL PAYMENT FORMS

FAR 52-232-5 – PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTACTS

Required with submission of all progress and final payments.

WH-347 – CERTIFIED PAYROLL

Required weekly and submitted with all payment requests.

Contractor-developed forms may be used in lieu of, but must contain, at minimum, all information as required on WH-347.

CLOSEOUT FORMS

All those required under Section 1.3.

FSH 6309.11 – CONTRACT RELEASE FORM

Required at the time of final payment submission for all contracts.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 00 50 00

SECTION 01 11 00 – SUMMARY OF WORK

1. GENERAL

SUMMARY

Work for this project consists of: Remove and dispose the existing 2 each 5,000 gallon fiberglass tanks, accessories, and associated drain and supply lines Then install one new 11,000 gallon steel water tank with required foundation, safety features, and new water valves and lines to tie into existing drain and supply lines.

LOCATION

The project work is located at the Mimbres Administrative Site, Grant County, New Mexico. From Silver City, take US-180 east 7 miles and turn left onto NM-152 to San Lorenzo, NM. Continue north 11 miles, the Ranger Station will be on the left side of the road. The water tank is on the hill behind the Ranger Station.

GENERAL SITE CONDITIONS

The tank sits on top of the hill, access to the tank will be through the horse corral. There is a steep hill side that will need to be travelled to get to where the tank will be installed.

FIELD VERIFICATION

Field verify all new and existing dimensions and project conditions affecting the work of the project prior to starting the work. If there are any discrepancies from the contract drawings and specifications, notify the Contracting Officer before proceeding with the work.

EXISTING UTILITIES

Locate and prevent damage to known utilities. If damage occurs to known utilities, repair at no cost to the Government.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 01 11 00

SECTION 01 14 00 – WORK RESTRICTIONS

1. GENERAL

SUMMARY

This section covers general and specific work restrictions at the project site.

USE OF PREMISES

Staging area for equipment, materials, and supplies is in the boneyard of the Ranger Station. The area is enclosed by the perimeter fence of the Ranger Station, however the Government does not guarantee this to be a fully secure site.

Limit use of premises to work in within the travel and construction limits. Do not disturb portions of the project site beyond where the travel and construction limits are indicated.

Keep roadways and entrances clear and available to Government employees and vehicles, emergency vehicles, and the public at all times. Do not use these areas for parking or storage of materials.

Provide adequate signing and barricades, and take necessary safety measures to protect the public during all construction operations, per MUTCD and OSHA. Minimize disturbance of all undisturbed areas.

Overnight camping is available at either Mimbres District Office or Lake Roberts Recreation Area. Coordinate with the Wilderness Ranger District for overnight stays at designated areas at the lake. Accommodations are available in the area but are a distance from the construction site.

WORK SCHEDULING

Normal working hours for construction activities are regular business hours.

Request for additional work hours requires written approval from the Contracting Officer 7 days in advance of the proposed work period.

Coordinate major construction activities and the sequence of work with the Contracting Officer at the pre-construction conference.

Depending on conditions, normal fire restrictions may apply to activities associated with this project. Refer to the fire plan for mandatory requirements for different fire restrictions.

UTILITIES

WATER

Available onsite, dependent upon stage of construction.

ELECTRIC

Not available at the water tank location.

SEWER

There is an RV dump stations located at the campground.

PRESERVATION OF NATURAL FEATURES

Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damages trees and plants, at no additional cost to the Government.

Do not remove, injure, or destroy trees or other plants without prior approval, or as indicated in the contract.

Carefully supervise excavating, grading, backfilling, and other construction operations near trees to prevent damage.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 01 14 00

SECTION 01 22 13 – UNIT PRICES MEASUREMENT AND PAYMENT

1. GENERAL

SUMMARY

This section explains, in general, what is the basis of payment for work items listed in the Schedule of Items.

Work: Furnish all labor, materials, equipment, and other incidentals necessary to successfully complete the project, or any portion of it, and carrying out all duties and obligations imposed by the contract by the Contractor.

Payment:

For each individual item in the Schedule of Items, full compensation for all work related to the particular item will be made in accordance with these specifications, as shown on the drawings, and as staked in the field.

Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials is considered incidental or as included in the payment for items shown.

DETERMINATION OF QUANTITIES

Perform, or cause to be performed, all measurements of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.

Quantity Measurements:

Make all measurements for computation of quantities for all work items except those specified for payment by Actual Quantity (AQ), Designed Quantity (DQ), or Lump Sum Quantity (LSQ).

Compute the quantities for periodic progress payments; the Contracting Officer will compute the quantities for final payment based on measurements taken by the Contractor and recommended by the COR.

All Contractor measurements are subject to verification by the Government.

Verify, in writing, as to the accuracy of the measurements and computations submitted.

UNITS OF MEASUREMENT

Each (EA): One complete unit, which may consist of one or more parts.

Linear Foot (LF): As applicable, measure the work along its length from end-to-end; parallel to the base or foundation; along the top; along the front face; or along the invert. Do not measure overlaps.

Lump Sum (LS): Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item. The quantity is designated as “All.” Estimated quantities of lump sum work shown in the contract are approximate.

METHOD OF MEASUREMENT

One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

Actual Quantities (AQ):

Estimated quantities which are determined from actual measurements of completed work.

Design Quantities (DQ):

Quantities determined by the Contracting Officer as noted on the Schedule of Items.

Lump Sum Quantities (LSQ):

Quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. It is not measured.

DEFINITION OF BID ITEMS

Definition of Bid Item No. B1.1 Description: Mobilization and bonding, one-time fee.

Measurements And Payment: LSQ, Lump Sum (LS) Definition of Bid Item No. B2.1 Description: Remove and dispose of existing ten thousand (10,000) gallon steel tank, two each five thousand (5000) gallon fiberglass tanks.

Measurements And Payment: LSQ, Lump Sum (LS) Definition of Bid Item No. B3.1 Description: Install foundation and anchoring systems per the drawings and specifications. Sizing and code requirements remain the same for the type of tank proposed, and resulting foundation would remain the same.

Measurements And Payment: LSQ, Each (EA) Definition of Bid Item No. B4.1 Description: Install new bolted or welded potable-water steel storage tank with interior epoxy coating system, per the drawings and specifications.

Measurements And Payment: LSQ, Each (EA) Definition of Bid Item No. B5.1 Description: Install 2 inch drain lines per drawings and specifications, to include transition couplings and fittings, tees, bends, utility bedding, and all other incidentals.

Measurements And Payment: DQ, Linear Foot (LF) Definition of Bid Item No. B6.1 Description: Install 2 inch drain line valves and valve boxes per drawings and specifications.

Measurements And Payment: LSQ, Each (EA) Definition of Bid Item No. B7.1 Description: Install 4-inch PVC supply lines per drawings and specifications, to include transition couplings and fittings, tees, bends, utility bedding, and all other incidentals.

Measurements And Payment: DQ, Linear Foot (LF) Definition of Bid Item No. B8.1 Description: Re-install the existing level control system and tank floats per drawings and specifications.

Measurements And Payment: LSQ, Lump Sum (LS) Definition of Bid Item No. B9.1 Description: Pressure testing and disinfection per drawings and specifications.

Measurements And Payment: LSQ, Lump Sum (LS)

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 01 22 13

SECTION 01 33 00 – SUBMITTAL PROCEDURES

1. GENERAL

SUMMARY

This section includes administrative and procedural requirements for submitting shop drawings, product data, samples, and other miscellaneous submittals.

SECTION REQUIREMENTS

SPECIFIED PRODUCTS

When a product, model number, part number, etc. is specified herein, it is implied a substitute product with the same performance specifications may be submitted as an Approved Equal, subject to final approval by the Contracting Officer.

DEFINITIONS

Submittal Descriptions (SD): Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals: Submittals which are required prior to start of construction work, issuance of contract notice to proceed, or commencing work at the site. This includes, but not limited to:

List of proposed Subcontractors (SF Form 1413) Construction progress schedule Health and safety plan Work plan Quality Control (QC) plan Bonding

SWPPP

SD-02 Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance, and other characteristics of materials, systems or equipment for some portion of the work.

SD-04 Samples:

Fabricated or un-fabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer’s standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

SD-05 Design Data:

Design calculations, mix designs, analyses or other data pertaining to a part of the work.

Design submittals, design substantiation submittals and extensions of design submittals.

Design calculations, mix designs, analyses or other data pertaining to a part of the work.

SD-06 Test Reports:

Reports signed by authorized official of testing laboratory that a material, product, or system identical to the material, product, or system to be provided has been tested in accord with specified requirements.

Reports of tests required to be performed by the Contractor on an actual portion of the work prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on a sample taken from the job site, on portion of work during or after installation.

SD-07 Certificates: Statements printed on the manufacturer’s letterhead and signed by responsible officials of manufacture of product, system, or material attesting that the product, system, or material meets specification requirements. Must be dated after award of the project contract and clearly name the project.

SD-08 Manufacturer’s Instructions: Preprinted material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.

SD-09 Manufacturer’s Fields Reports:

Documentation of the testing and verification actions taken by manufacturer’s representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer’s standards or instructions.

Documentation must be signed by an authorized official of a testing agency laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.

SD-10 Operation and Maintenance Data:

Data that is furnished by the manufacturer, or the system provider, to the product, system, or equipment operating and maintenance personnel, including manufacturer’s help and product line necessary to maintain the product, system, or equipment.

SD-11 Closeout Submittals:

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract, such record drawings and as-built drawings.

VARIATIONS

Variations from contract requirements require Governmental approval pursuant to contract clause FAR 52-236-21 and will be considered where advantageous to the Government.

Highlight, encircle, or otherwise identify deviations from the contract documents on submittals.

PRODUCTS

Government Approval (GA) Submittals Written and graphic information that requires Contracting Officer’s responsible action.

For Information Only (FIO) Submittals Written information that does not required Contracting Officer’s approval.

Submittals may be rejected for not complying with requirements.

EXECUTION

GENERAL

Review each submittal and check for compliance with the contract documents. Note corrections and field dimensions.

Review Notifications:

The Contracting Officer review will be completed and returned within 14 calendar days after date of submissions.

If a submittal is marked as “Disapproved” or “Does not comply”, resubmit with appropriate corrections. No work shall proceed for this item until resubmittal is approved.

Contracting Officer will not review submittals that do not bear the Contractor’s signature and will return them without actions.

Use the attached cover form 4025-R for submittals.

END OF SECTION 01 33 00

SECTION 01 42 13 – ABBREVIATIONS AND ACRONYMS

1. GENERAL

CONTRACTING

CO – Contracting Officer COR – Contracting Officer’s Representative FAR – Federal Acquisition Regulation FIO – For Information Only FSH – Forest Service Manual GA – Government Approval SF – Standard Form

AGENCIES

ADEQ – Arizona Department of Environmental Quality ADWR – Arizona Department of Water Resources COE – Corps of Engineers MAG – Maricopa Association of Governments OSHA – Occupational Safety and Health Administration USFS – United States Forest Service

OTHER

MUTCD – Manual on Uniform Traffic Control Devices SP – Standard Practice SWPPP – Stormwater Pollution Prevention Plan

TECHNICAL AND PROFESSIONAL GROUPS

AASHTO – American Association of State Highway and Transportation Officials ACI – American Concrete Institute ANSI – American National Standards Institute APA – American Plywood Association ASSE - American Society of Safety Engineers ASTM – American Society for Testing and Materials AWWA – American Water Works Association CCRL – Cement and Concrete Reference Laboratory CRSI – Concrete Reinforcing Steel Institute MPI – Master Painter’s Institute MSS – Manufacturers Standardization Society of the Valve and Fittings Industry NIST – National Institute of Standards and Technology NFPA – National Fire Protection Association NSF – National Sanitation Foundation SSPC – Society for Protective Coatings UL – Underwriters Laboratories

UTILITIES

HDPE – High Density Polyethylene NPS – Nominal Pipe Size PVC – Polyvinyl Chloride SDR – Standard Dimension Ratio

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 01 42 13

SECTION 01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

1. GENERAL

SUMMARY

This section covers the management and disposal of all construction-related debris as a result of ongoing project activities.

PRODUCTS (NOT USED)

EXECUTION

REMOVAL OF MATERIAL

Construct adequate debris shields to contain debris within the construction limits. Do not permit debris to enter waterways, travel lanes open to public traffic, or areas designated not to be disturbed.

Raze and remove all foundations, structures, utilities, and other obstructions interfering with the work and not designated to remain.

Except in excavation areas, backfill and compact cavities left by structure and vegetation removal with backfill material of the finished ground.

DISPOSAL OF MATERIAL

Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

Dispose of hazardous material according to Federal, State, and local regulations, and furnish a copy of all disposal permits.

END OF SECTION 01 74 19

SECTION 01 77 00 – CLOSEOUT PROCEDURES

1. GENERAL

SUMMARY

This section includes administrative and procedural requirements for contract closeout.

SECTION REQUIREMENTS

SUBSTANTIAL COMPLETION PROCEDURES

Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

Submittals Prior to Substantial Completion: Before requesting Substantial Completion inspection, submit all required submittals.

Procedures Prior to Substantial Completion: Before requesting Substantial Completion inspection, complete the following:

Complete startup and testing of systems and equipment.

Perform preventive maintenance on equipment used prior to Substantial Completion.

Remove temporary facilities and controls.

Complete final cleaning requirements, including touchup painting.

Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, the Contracting Officer will proceed with inspection or advise Contractor of unfulfilled requirements. The Contracting Officer will prepare the certification of Substantial Completion after inspection or will advise Contractor of items that must be completed or corrected before certificate will be issued.

FINAL COMPLETION PROCEDURES

Submittals Prior to Final Completion: Before requesting inspection for determining final completion, submit certified copy of Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by the Contracting Officer, indicating all items have been corrected and fixed.

Submit a written request for final inspection for acceptance. On receipt of request, the Contracting Officer will either proceed with inspection or notify Contractor of unfulfilled requirements.

Re-inspection: Request re-inspection when the work identified in previous inspections as incomplete is completed or corrected.

PRODUCTS (NOT USED)

EXECUTION

CLEANING

Complete the following cleaning operations before requesting inspection for certification of Substantial Completion:

Clean Project site, yard, and grounds, in areas disturbed by construction activities. Sweep paved areas; remove stains, spills, and foreign deposits. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

DEMONSTRATION AND TRAINING

Engage qualified instructors to instruct Government personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. Include a detailed review of the following:

Include instruction for basis of system design and operational requirements, review of documentation, emergency procedures, operations, adjustments, troubleshooting, maintenance, and repairs.

END OF SECTION 01 77 00

SECTION 01 78 00 – CLOSEOUT SUBMITTALS

1. GENERAL

SUMMARY

This section includes requirements for closeout submittals.

SECTION REQUIREMENTS

Submittals:

As-Built Drawings (SD-11, Closeout), GA

CLOSEOUT SUBMITTALS

As-Built Drawings: Provide and maintain two print copies of the drawings. Show what was changed, how it was changes, where item(s) were relocated and change related details.

Markup Guidelines:

The working as-built markup drawings must be neat, legible, and accurate as follows:

Use base colors of red, green and blue:

Special (Blue) – items requiring special information, coordination, or special detailing or detailing notes.

Deletions (Red) – Over-strike deleted graphic items (lines), lettering in notes and leaders.

Additions (Green) – Added items, lettering in notes and leaders.

Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.

Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on other sheets.

Final Submittal:

Submit two prints, 11” x 17”, and complete set of as-built drawings.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 01 78 00

SECTION 09 91 13 – EXTERIOR PAINTING

1. GENERAL

SUMMARY

This section includes requirements for exterior painting of metal surfaces.

SECTION REQUIREMENTS

Submittals:

Paint Data, including printout of MPI’s “MPI Approved Products List” (SD-03, Product Data), FIO Exterior Primer (SD-03, Product Data), FIO Exterior Paint Color Samples (SD-04, Samples), GA Extra Materials: Deliver to Contracting Officer 1 gal. of each color and type of finish-coat paint used on Project, in containers, properly labeled and sealed.

PRODUCTS

PAINT

MPI Standards: Provide materials that comply with MPI standards indicated and listed in its "MPI Approved Products List."

Primer, Alkyd, Anticorrosive: MPI #79.

Primer, Quick Dry, for Aluminum: MPI #95.

Alkyd, Exterior Flat (Gloss Level 1): MPI #8.

Alkyd, Exterior, Semigloss (Gloss Level 5): MPI #94.

Material Compatibility: Provide materials that are compatible with one another and with substrates.

For each coat in a paint system, provide products recommended in writing by manufacturers of topcoat for use in paint system and on substrate indicated.

Colors:

Tank: Brown (Federal Standard Color 20059) or Green. Submit for approval.

Ladder, cage, overflow piping, etc.: To be determined. Submit for approval.

EXECUTION

PREPARATION

Comply with recommendations in MPI's "MPI Architectural Painting Specification Manual" applicable to substrates indicated.

Mask items that cannot be removed. Reinstall items in each area after painting is complete.

Clean and prepare surfaces in an area before beginning painting in that area.

APPLICATION

Comply with recommendations in MPI's "MPI Architectural Painting Specification Manual" applicable to substrates indicated.

Paint exposed new surfaces, unless otherwise indicated.

Do not paint prefinished items, items with an integral finish, operating parts, and labels unless otherwise indicated.

Apply paints according to manufacturer's written instructions.

Use brushes only where the use of other applicators is not practical.

Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color breaks.

If undercoats or other conditions show through topcoat, apply additional coats until cured film has a uniform paint finish, color, and appearance.

EXTERIOR PAINT APPLICATION SCHEDULE

Steel:

Semigloss, Alkyd enamel: Two coats with 1.5 mil thickness each over 2.0 mil thick alkyd anticorrosive primer: MPI EXT 5.1A.

Aluminum:

Semiglass, Alkyd enamel: Two coats over quick-drying primer for aluminum: MPI EXT 5.4F.

END OF SECTION 09 91 13

SECTION 31 23 16 – EXCAVATION

1. GENERAL

SUMMARY

This section includes excavation requirements for pavements, walkways, utilities, and other related activities.

SECTION REQUIREMENTS

Unauthorized excavation consists of excavation below subgrade elevations or beyond indicated lines and dimensions without direction by the Contracting Officer. Unauthorized excavation, as well as remedial work directed by the Contracting Officer, shall be without additional compensation.

It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans, specifications, and Pre-work Conference, and to employ necessary measures to permit construction to proceed.

PRODUCTS (NOT USED)

EXECUTION

INSPECTION

Location of the existing utilities indicated is approximate. Physically verify location and elevation of the existing utilities indicated prior to starting construction.

Movement of construction machinery and equipment over pipes during construction is at the Contractor’s risk. Repair, or remove and provide new pipe for existing or newly installed pipe that has been displaced or damaged.

Protect and maintain erosion and sedimentation controls during earthmoving operations.

Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.

EXCAVATION

Explosives: Do not use explosives.

Excavate to subgrade elevations. Material to be excavated will be classified as earth and rock. Do not excavate rock until it has been classified and cross sectioned by the Contracting Officer. The Contract Sum will be adjusted for rock excavation according to unit prices included in the Contract Documents.

Utility Trenches: Excavate trenches to indicated slopes, lines, depths, and invert elevations. Shape subgrade to provide continuous support.

Remove waste materials, including unsatisfactory soil, trash, and debris, and legally dispose of them off Owner's property.

END OF SECTION 31 23 16

SECTION 31 23 23.13 – BACKFILL

1. GENERAL

SUMMARY

This section includes requirements for various backfill materials.

SECTION REQUIREMENTS

Reference Sections:

03 23 23.23 – COMPACTION

Submittals:

Select backfill/fill (SD-06, Test Reports), GA Bedding course (SD-03, Product Data), GA

PRODUCTS

SOIL MATERIALS

Satisfactory Soil: ASTM D 2487 Soil Classification Groups GW, GP, GM, SW, SP, and SM; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, or other deleterious matter.

Unsatisfactory Soil: ASTM D 2487 Soil Classification Groups GC, SC, CL, ML, OL, CH, MH, OH, and PT.

Select Backfill and Fill: Satisfactory soil materials, with properties as shown in Subsection F below.

General aggregate base course: ADOT Class VI Base Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed stand; per ASTM D 2940, with the properties as shown in Subsection E below:

Select and Base Materials Properties (MAG January 2015 Edition):

Sieve Analysis

Test Methods AASHTO T-27, T-11

Sieve Size
Accumulative Percentage Passing Sieve, by Weight
Select Material
Base
Type A
Type B
3 inch
100
------
------
1-1/2 inch
------
100
100
1 inch
------
------
90 – 100
No. 4
30 – 75
30 – 70
38 – 65
No. 8
20 – 60
20 – 60
25 – 60
No. 30
10 – 40
10 – 40
10 – 40
No. 200
0 – 12
0 – 12
3 – 12

If Select and Base materials do not meet gradation as shown in Subsection E above, material may be approved at the Government’s discretion if the R-Value is at least 70, when determined by test method AASHTO T-190.

Utility Bedding Course: Same as Base Course Drainage Course: Narrowly graded mixture of washed crushed stone or crushed or uncrushed gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and zero to 5 percent passing a No. 8 sieve.

MISCELLANEOUS MATERIALS

Synthetic Fiber Filter Fabric: Consists of thermoplastic, non-woven fabric, and forms a mat of uniform quality. Provide fabric designed for the applicable feature of work.

EXECUTION

GENERAL

Unless otherwise noted or indicated, place backfill and fill in horizontal layers not more than 8 inches in loose depth at optimum moisture content Do not backfill against concrete less than 7 days old or until 80 percent of the design strength is achieved.

Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent backfill materials.

Bring backfill up evenly on all sides of the structure, and extend each layer to the limits of the excavation or to natural grand.

SUBGRADE PREPARATION

Meet compaction densities as required in Section 31 23 23.23 – COMPACTION, for prepared subgrade.

Remove unsatisfactory material on surfaces to receive fill or in excavated areas, and replace with satisfactory materials as directed by the Contracting Officer.

Scarify the surface to a depth of 6 inches, or to a depth as indicated on the drawings, before the fill is started.

Plow, step, bench, or brake up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material.

When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inches, pulverize, and compact to the specified density.

When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inches and compacted as specified for the adjacent fill.

UTILITY TRENCHES

Place, compact, and shape bedding course to provide continuous support for pipes and conduits over rock and other unyielding bearing surfaces and to fill unauthorized excavations.

Hand-place and compact initial backfill of satisfactory soil material, free of particles larger than 1 inch, to a height of 12 inches over the utility pipe or conduit. Place and compact final backfill of satisfactory soil material to final subgrade.

END OF SECTION 31 23 23.13

SECTION 31 23 23.23 – COMPACTION

1. GENERAL

SUMMARY

This section includes compaction requirements for the foundations of the water storage tanks

SECTION REQUIREMENTS

Reference Sections:

31 23 23.13 - BACKFILL

Submittals:

Laboratory moisture-density reports (SD-06, Test Reports), FIO Field compaction test results (SD-06, Test Reports), FIO

PRODUCTS

Utilize the proper compaction methods and equipment to suit the material and conditions encountered.

At minimum, the laboratory moisture-density testing reports shall contain the following:

Laboratory’s name.

Date, time, and specific location from which sample was taken and name of person who collected the sample.

Moisture-Density Curve plotted on graph paper to as large a scale as is practical with all points used to derive the curve being clearly visible.

Designation of the test method used.

The optimum density and moisture content.

A description of the sample.

The date the test was performed and the person who performed the test.

The Project name, identification, and Contractor’s name.

The signature of a responsible officer of the Testing Laboratory certifying to the information contained in the report.

At minimum, the field compaction density testing reports shall contain the following:

Laboratory’s name.

Date, time, and depth from which the test was made and name of person who performed the test.

Designation of the test method used.

Designation of the material being tested.

Test number.

In place dry density and moisture content.

Optimum density and moisture content.

Percentage of optimum density achieved.

The Project name, identification, and Contractor’s name.

The signature of a responsible officer of the Testing Laboratory certifying to the information contained in the report.

EXECUTION

INSPECTION

Determine optimum moisture content and maximum density according to AASHTO T 99, Method C (Modified Proctor).

Verify that layers of material are no thicker than the maximum thickness specified.

Moisten or dry each layer of material to achieve optimum moisture content.

Do not begin compaction operations until conditions are satisfactory.

Do not compact in freezing weather or when materials to be compacted are frozen, too wet or moist, or too dry.

Protect pipes, structures, and all other subsurface work from displacement or injury during compaction operations.

GENERAL

Compact each bedding, subgrade, and subbase layer under structures, building slabs, pavements, and walkways to 95 percent of maximum dry unit weight according to ASTM D 698; elsewhere to 85 percent, unless otherwise specified on approved foundation drawings.

Compact each lift before placing overlaying lift, to include foundation.

Re-excavate, re-compact, and re-test material layers that do not meeting compaction densities at no cost to the Government.

FIELD QUALITY CONTROL

Allow testing agency to inspect and test each subgrade and each fill or backfill layer and to verify compliance with requirements, when applicable.

Provide compaction testing for bedding, subgrade, and subbase layers in accordance with AASHTO T 310.

2 per lift, before placing next layer.

Re-excavate, re-compact, and re-test material layers that do not meeting compaction densities at no cost to the Government.

END OF SECTION 31 23 23.23

SECTION 33 05 16.13 – PRECAST CONCRETE UTILITY STRUCTURES

1. GENERAL

SUMMARY

This section includes requirements for utility and metering pre-cast concrete boxes.

SECTION REQUIREMENTS

Reference Sections:

31 23 23.13 – BACKFILL

31 23 23.23 – COMPACTION

Submittals:

Precast Concrete Box (SD-03, Product Data), GA

PRODUCTS

MATERIALS

Precast Concrete Valve/Meter Boxes and Utility Vaults Reinforced precast concrete in accordance with ASTM C 478.

Joints:

O-ring rubber gaskets in accordance with ASTM C 443.

Butyl rubber gaskets in accordance with ASTM C 990.

Cast iron cover, per ASTM A 48, Class 30B, marked “WATER.”

When installed on pavement or surfaced roads, meet live load rating of HS-20.

Paint all covers blue.

Free from fractures, large or deep cracks, blisters, or surface roughness or any other defects that may affect serviceability.

EXECUTION

GENERAL

0. Inspect structures immediately prior to placement in excavation to verify structures are internally clean and free from damage. Remove and replace damaged units.

Set precast structures bearing firmly and fully on a minimum of 3-inches of subbase material.

Set top of box cover 4 to 6 inches above natural grade. For paved, roadway, or pathway areas, set top flush with adjacent surface.

Place additional punch-outs as needed to provide for the required utilities located in the precast structure.

Seal punch-outs completely after specified piping or conduit is placed.

Adjustable or Stackable Boxes:

Install as needed to provide adequate depth as indicated in the drawings.

Lower, set level, and firmly position base section before placing additional sections.

Assemble multi-section boxes and structures by lowering each section into excavation.

Install rubber gasket joints between precast sections in accordance with manufacturer’s instructions.

END OF SECTION 33 05 16.13

SECTION 33 05 26 – UTILITY IDENTIFICATION

1. GENERAL

SUMMARY

This section includes requirements for the identification of underground utilities.

PRODUCTS

MATERIALS

Detectable Warning Tape: Acid- and alkali-resistance polyethylene film warning tape, manufactured for marking and identifying underground utilities, minimum 6 inches wide and 4 mils thick, continuously inscribed with black lettering, metallic core encased in a protective jacket for corrosion protection, detectable by metal detector when tape is buried up to 30 inches deep, fully colored and inscribed as follows:

Water Systems – Blue, “CAUTION: BURIED WATER LINE BELOW” Tracer Wire: UF insulated, #12 copper wire.

EXECUTION

TRACER WIRE

Install as indicated on the drawings and at a continuous length of tracer wire for the full length of each run of nonmetallic pipe. Attach wire to top of pipe at a maximum interval of 20 feet, in such manner that it will not be displaced during construction operations.

For water systems, clamp tracer wire to outlet drains, hydrants, curb stops, and air/vacuum valves with ground clamps sized for pipe at appurtenance.

DETECTABLE WARNING TAPE

Install at depth and location as indicated on the drawings.

END OF SECTION 33 05 26

SECTION 33 11 13.23 – PLASTIC PUBLIC WATER UTILITY DISTRIBUTION PIPING

1. GENERAL

SUMMARY

This section includes requirements for plastic water distribution piping, for potable water systems, outside of a building footprint.

SECTION REQUIREMENTS

Reference Sections:

31 23 23.13 – BACKFILL

31 23 23.23 – COMPACTION

33 05 26 – UTILITY IDENTIFICATION

33 13 00 – DISINFECTION OF WATER UTILITY DISTRIBUTION

Submittals:

HDPE Piping (SD-03, Product Data), FIO HDPE Joint Fusion Certification (SD-07, Certificates), GA Pressure Test Results (SD-06, Test Reports), FIO Delivery, Storage, and Handling:

Deliver piping with factory applied end-caps. Maintain end caps through shipping, storage, and handling to prevent pipe-end damage and to prevent entry of dirt, debris, and moisture.

Protect flanges, fittings, and specialties from moisture and dirt.

Store piping, fittings, and accessories to protect from direct sunlight. Support piping to prevent sagging and bending.

PRODUCTS

GENERAL

All waterlines, pipes, and fittings shall be new and unused, of the type, pressure rating or class, and size specified and as shown on the drawings, and in compliance with the Reduction of Lead in Drinking Water Act.

Comply with NSF 61 for materials for water-service piping and specialties, with piping bearing the label, stamp, or other markings by the specified testing agency.

Unless otherwise indicated, the minimum pressure requirement for piping, specialties, and fittings is 160 psig.

MATERIALS

HDPE Piping: PE-3408 as defined in ASTM D 1248, minimum cell classification 345464C per ASTM D 3350, SDR 9.

For pipe sizes larger than 2” diameter, provide in 40-foot lengths rather than rolls.

Dissimilar Pipe Couplings: Compression type, transition fittings from plastic piping to various pipes, Cepex performance series as manufactured by Cepex Holding, S.A., or approved equal.

EXECUTION

GENERAL

Before placing in position, clean pipe, fittings, valves, and accessories, and maintain in a clean condition.

Do not under any circumstances drop or dump pipe, fittings, valves, or any other water line material into trenches.

Cut pipe in a neat workmanlike manner accurately to length established at the site and work into place without springing or forcing.

Grade the pipeline in straight lines; avoid the formation of dips and low points.

Lay pipe such that the full length of each section of pipe and each fitting will rest solidly on the pipe bedding.

Excavate recesses to accommodate bells, joints, and couplings.

Keep trenches free of water until joints have been properly made.

Do not lay pipe when conditions of trench or weather prevent installation.

Do not exceed 5 degrees alignment, or the manufacturer’s recommended alignment offset, for adjacent joints, whichever is more stringent.

Penetrations:

Provide ductile-iron or Schedule 40 steel wall sleeves for pipe passing through walls of valve boxes and structures.

Fill annular space between walls and sleeves with rich cement mortar.

Fill annular space between pipe and sleeves with mastic.

Provide thrust blocks in the size and position as indicated in the drawings.

Provide tees at all branch connections to the main, and with the same diameter as the largest pipe connected to the tee.

When work is not in progress, securely close open ends of pipe and fittings.

Do not place pipe in the trench until the Contracting Officer approves the trench and bedding.

Backfill the pipe within 24 hours after installing the pipe in the trench, leaving the joints and one foot of pipe on each side of each joint until testing is complete.

INSTALLATION

HDPE Pipe Install in accordance with ASTM D 2774.

Jointing per ASTM D 2657m Technique I – Socket Fusion, or Technique II – Butt Fusion, and per the manufacturer’s written instructions.

Use certified HDPE jointing personnel or provide qualifications showing at least three years’ experience in HDPE fusion techniques.

CLEANING

Before testing, clean new water distribution piping systems and parts of existing systems that have been altered, extended, or repaired by high-pressure water jet or mechanical means.

Flush water lines or modifications of an existing water system, and all of the existing system immediately downstream, to remove sediment.

During flushing operations, operate all valves, hydrants, hose bibs, and other outlets.

Flush system with clean potable water until dirty water does not appear at points of outlet.

PRESSURE TESTING

Conduct piping tests before joints are covered and after thrust blocks, if required, have hardened sufficiently. Keep joints uncovered until testing is completed satisfactorily.

Furnish personnel, pump, pipe, gauge, measuring device, connections, and all other necessary apparatus for testing, and are subject to approval by the Contracting Officer.

Test all newly constructed portions of the water system, including water mains, service lines, fittings, valves, and hydrants. Test new water line extensions and modifications to an existing water system at the specified test pressure.

Provide and use only potable water.

Test water lines in sections not to exceed 2,000 linear feet in length or a maximum pressure differential of 30 psi in the test section.

Expansion Test Procedure Slowly fill each valve or plugged test section of pipe with water. Fill by means of a pump connected to a pipe. Operate all hydrants and taps to bleed entrapped air from test section. Operate pump continuously during bleeding operations, and such that the pump takes suction from a small auxiliary tank for measuring the water pumped into the test section.

Raise internal pressure of the system by pumping in water. Increase pressure in 50-psig increments and inspect each joint between increments. Raise internal pressure to a test pressure of 1.5 times the working pressure at the point of testing based on the elevation of the lowest point of the line or section under test, or other test pressure as approved by the Contracting Officer.

Allow the system to stabilize for three (3) hours at the test pressure before conducting the hydrostatic test. Make up liquid may be added during this time to return to test pressure.

After obtaining the approved test pressure, record the water level in the auxiliary tank.

Test Phase Procedure Begin test phase immediately after recording the water level, for two (2) hours.

Reduce the test pressure by 10 psi, and stop adding test liquid. If the pressure remains steady, within 5% of the target value, for one (1) hour, no leakage is indicated.

Verify leakage with the Contracting Officer.

Locate and replace any defective pipe, fittings, valves, joints, and hydrants as required, if there is leakage in excess of the above requires, at no cost to the Government, until the leakage is within the specified allowance.

All visible leaks are to be repaired regardless of the amount of leakage. Flush the system, and repeat the pressure test until leak is repaired.

The use of paints, asphalts, tars, enamels, or other types of pipe compounds to eliminate leaks is not permitted.

Backfill the water lines after the Contracting Officer approves the testing.

Furnish a written report to the Contracting Officer, describing the results of each test. Identify specific portions of pipeline tested, the pressure, the duration of the tests, and the amount of leakage.

DISINFECTION

Disinfect per 33 13 00 – DISINFECTING OF WATER UTILITY DISTRIBUTION

END OF SECTION 33 11 13.23

SECTION 33 12 16 – WATER UTILITY DISTRIBUTION VALVES

1. GENERAL

SUMMARY

This section includes requirements for water distribution valves and valve boxes.

SECTION REQUIREMENTS

Reference Sections:

31 23 23.13 – BACKFILL

31 23 23.23 – COMPACTION

Submittals:

Gate Valve (SD-03, Product Data), GA Delivery, Storage, and Handling:

Protect valves from moisture and dirt.

PRODUCTS

GENERAL

All water line valves and fittings shall be new and unused, of the type, pressure rating or class, and size specified and as shown on the drawings, and in compliance with the Reduction of Lead in Drinking Water Act, and NSF 61 certified.

Unless otherwise indicated, the minimum pressure requirement for valves and fittings is 160 psig.

MATERIALS

Gate Valve:

Greater than 2 inches: AVK Series 66, or…

This is the start of the file's text. The full file is on GovTribe.