A-11_Attachment_7_Questions_&_Answers.docx
DOCX document 12 KB Posted
- Attached to
- Sage Habitat Improvement Mastication Project Federal contract opportunity
- Solicitation number
- 1282MK18R0002
About this file
Attachment 7 - Questions & Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A-11_1282MK18R0002_Amend0001.pdf | ||
| A-11_Attachment_5_ExperienceQuestionnaire.docx | DOCX document | |
| A-11_Attachment_3_Photographic_Images.pdf | ||
| A-11_Attachment_6_Employment_of_Eligible_Workers.docx | DOCX document | |
| A-11_Attachment_4_Fire_Control_Plan.pdf | ||
| A-11_Attachment_1_Maps.docx | DOCX document | |
| A-11_Attachment_2_Wage_Determination.pdf | ||
| A-11_1282MK18R0002.pdf | ||
| A-11_1282MK18R0002.pdf | ||
| A-11_Attachment_1_Maps.docx | DOCX document | |
| A-11_Attachment_3_ExperienceQuestionnaire.docx | DOCX document | |
| A-11_Attachment_4_Photographic_Images.pdf | ||
| A-11_Attachment_2_Wage_Determination.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 7 – Questions & Answers Solicitation #: 1282MK18R0002
Question 1: Can tracks (rubber or other) be used on this project?
Answer: The requirement for this contract is rubber tires.
Question 2: Is a site visit planned?
Answer: No site visit is planned. Pictures and maps have been provided. You may be able to access the area by snowmobile, skis or snowshoes. We feel that the photos and maps give a good depiction of the area.
Question 3: Has a contractor performed similar work to this for the Government in the past?
Answer: Similar work has been completed in the past: AG-82D7-C-17-0002. There may be changes in requirements, terrain and cover types.
Question 4: Are photos and maps of the project available?
Answer: Yes, they are posted on www.FBO.gov, Attachment 1 and Attachment 3.
Question 5: Is the Period of Performance 07/15/18 to 08/26/18 for the primary Item 1 for 168 acres, or is this time to cover the entire project (Items 1 through 3).
Answer: We believe that the entire project (Items 1, 2, and 3 if awarded) can be done in the allotted time period