REQUEST FOR PROPOSALS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12817319R0007_Amend_1.pdf | ||
| EXHIBITS_3_to_7.pdf | ||
| 2019_RETURN_PACKET_12817319R000__Black_Mesa.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
52.215-1 INSTRUCTIONS TO OFFERORS -- COMPETITIVE ACQUISITION (JAN 2017)
(a) Definitions. As used in this provision --
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.”
“In writing,” “writing,” or “written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time,” if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals.
(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages
(i) addressed to the office specified in the solicitation, and
(ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show --
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation;
and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, revision, and withdrawal of proposals.
(i) Offerors are responsible for submitting proposals, and any modification, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)
(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and --
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall --
(1) Mark the title page with the following legend:
This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed -- in whole or in part -- for any purpose other than to evaluate this proposal.
If, however, a contract is awarded to this offeror as a result of -- or in connection with -- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government’s right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend:
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government’s interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government’s best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency’s evaluation of the significant weak or deficient factors in the debriefed offeror’s offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(End of Provision)
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
12817319R0007
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
12/17/2018
PAGE OF PAGES
1 67
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
6. PROJECT NO.
7. ISSUED BY CODE 128173 8. ADDRESS OFFER TO
USDA FOREST SERVICE APACHE-SITGREAVES NATIONAL FORESTS
SUPERVISOR’S OFFICE – ACQUISITION MANAGEMENT
30 S. CHIRICAHUA DRIVE PO BOX 640
SPRINGERVILLE, AZ 85938
SAME AS BOX NO. 7
9. FOR INFORMATION
CALL:
A. NAME
WARREN ABBOTT
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(928) 333-6344
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
12817319R0007 – This solicitation is a 100 percent Total Small Business Set-Aside. NAICS 237310 $36.5 Million is size standard for small business.
The USDA Forest Service, Apache—Sitgreaves National Forests, Springerville, Arizona, has a requirement for Road Maintenance and Construction on an Indefinite Delivery / Indefinite Quantity (IDIQ). The Contracting Officer intends to make multiple awards from this solicitation to at least three (3) individual IDIQ contracts using Best Value – Tradeoffs evaluation factors.
The minimum guarantee per awarded contract will be $2,000 to satisfy the minimum requirement for life of the awarded contract. The maximum order limit for all combined awarded contracts awarded under this is $1,000,000. There is no guarantee that task orders will reach the maximum order limit. The Period of Performance for each awarded contract is from date of award through December 31, 2022 (subject to appropriated funding approved by Congress).
Payment and Performance bonds will be required upon award of task orders $30,000 and over.
All of this work is covered under the Davis-Bacon Act, for which the appropriate wage determinations have been incorporated into the solicitation package. This work may require specialized equipment, transports, safety, and tools.
11. The Contractor shall begin performance within 10 calendar days and complete it within time specified calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by 1600 MST (hour) local time JANUARY 22, 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
SAME AS 7 Electronic Funds Transfer via Invoice Processing Platform at www.ipp.gov
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award,
(b) the solicitation, and (c) the clauses, representations, certifications,
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO
SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print) Warren Abbott
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
CONSTRUCTION RFP SOL NO: 12817319R0007
UNIT: APACHE-SITGFREAVES N.F
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
CHECKLIST OF MINIMUM REQUIREMENTS
AND CERTIFICATION OF OFFER
_____CERTIFICATION OF PRICES OFFERED AND SUBMISSIONS FOR THIS REQUEST FOR PROPOSALS:
VENDOR COMPANY NAME: ___________________________________________________________
AUTHORIZED TO SIGN (NAME & TITLE): _________________________________________________
SIGNATURE: __________________________________________ DATE: _____________
_____ PROVIDE YOUR DUNS NUMBER ________________________ (INCLUDE DUNS # ON EACH PRICING PAGE)
_____PROVIDE YOUR BUSINESS EMAIL TO FACILITATE COMMUNICATIONS____________________________
_____ HAVE ACTIVE VENDOR RECORD FOR THE DUNS NUMBER ABOVE IN THE SYSTEM FOR AWARD
MANAGEMENT (SAM) HTTPS://WWW.SAM.GOV
_____ RESPOND WITH THE COMPLETE RETURN PACKAGE (SEE SECTION M FOR REQUIREMENTS). FAILURE TO PROVIDE THE REQUIRED INFORMATION FOR TECHNICAL CAPABILITY, PRICES, AND PAST PERFORMANCE, AND SUBSEQUENT SUBFACTORS, MAY RESULT IN YOUR OFFER BEING REMOVED FROM THE COMPETITIVE RANGE.
PART I— SCHEDULE OF ITEMS
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
All equipment and vehicle rates identified in Line Item Numbers 1 through 11 include operator and/or required crews. Line Item Numbers 12 through 15 do not include operator, unless otherwise stated. The Government only pays rates for actual running and operational time for the equipment. Stand-by, maintenance, and other forms of down time are not reimbursable. Attachment hourly rates are in addition to the regular rate of the equipment needed to operate the attachment.
VENDOR DUNS#____________________________
ITEM
NO. DESCRIPTION OF SUPPLIES/SERVICES ITEM UNIT UNIT PRICE
1 Loader
-A CAT 938 or equivalent, Minimum 3.5 CY Bucket Loader HR $___________
-B CAT 950 or equivalent, Minimum 4.0 CY Bucket Loader HR $___________
-C CAT 966 or equivalent, Minimum 5.0 CY Bucket Loader HR $___________
-D CAT 980 or equivalent, Minimum 7.0 CY Bucket Loader HR $___________
2 Motor Grader *MUST OFFER 2A MINIMUM*
-A CAT M Series or equivalent, 12 to 16 foot blade width, general road blading, aggregate placement, snow plowing Grader HR $___________
-B CAT M Series or equivalent, 12 to 16 foot blade width, heavy road maintenance (ML-2), rock trimmer support Grader HR $___________
3 Bulldozer *MUST OFFER 3C OR 3D MINIMUM*
-A CAT D3 Class or equivalent Dozer HR $___________
-B CAT D4 Class or equivalent Dozer HR $___________
-C CAT D5 Class or equivalent Dozer HR $___________
-D CAT D6 Class or equivalent Dozer HR $___________
-E CAT D7 Class or equivalent Dozer HR $___________
-F CAT D8 Class or equivalent Dozer HR $___________
VENDOR DUNS#____________________________
ITEM
NO. DESCRIPTION OF SUPPLIES/SERVICES ITEM UNIT UNIT PRICE
4 Mobile Rock Crusher
-A
Mobile rock crusher/trimmer, IronWolf 600/800/1000 series or IronWolf 700B Series, or equivalent, capable of crushing rock shelves, windrows of loose rock material, and minimum 12-inch boulders such that no more than 10% of the rocks in the final product exceed 3 inches when measured in any one direction (number of passes will vary based on rock type). Cutter head width must be between 78 and 120 inches, with the capability of crushing to a minimum roadbed depth of 6 inches.
Equipment is available to be rented from commercial source.
Mobile Rock Crusher HR $___________
Crusher Attachment Width: _______________________
Crusher Make/Model: ____________________________
Equipment Make/Model: _________________________
Minimum hours required, per task order, to award this line item: _________ HRS
5 Track Excavator *MUST OFFER 5B OR 5C MINIMUM*
-A CAT 303-305 Class or equivalent, 30 to 45 HP Excavator HR $___________
-B CAT 311-318 Class or equivalent, 92 to 120 HP Excavator HR $___________
-C CAT 320-329 Class or equivalent, 140 to 240 HP Excavator HR $___________
-E
CAT 311-329 Class or equivalent w/ Rock Hammer
Excavator HR $___________ Rock Hammer Size: _______________________lbs
Excavator Make/Model: ___________________
-F Attachment: [Thumb] [Thumb Bucket] [Compaction Wheel] (Circle All That Apply) Attachment HR $___________
6 Backhoe *MUST OFFER 6B MINIMUM*
-A CAT 415-416 Class or equivalent, 68 to 87 HP Backhoe HR $___________
-B CAT 420-430 Class or equivalent, 93 to 108 HP Backhoe HR $___________
-C CAT 420-450 Class or equivalent, 93 to 127 HP w/ Hammer Backhoe w/
Hammer HR $___________ Hammer Size: ________________lbs
-D Fixed Attachment: [Forks] [Gannon] [Hay Spears] (Circle All That Apply) Attachment HR $___________
-E Mechanical Attachment: [Compaction Wheel] [Thumb] (Circle All That Apply) Attachment HR $___________
-F Heavy Mechanical Attachment: [Milling] [Vibratory Compactor] (Circle All That Apply) Attachment HR $___________
ITEM
NO. DESCRIPTION OF SUPPLIES/SERVICES ITEM UNIT UNIT PRICE
7 Bobcat / Skid Steer Loader
-A CAT 226 - 236 Class or equivalent, 65 to 72 HP Skid Steer HR $___________
-B CAT 242 - 272 Class or equivalent, 73 to 106 HP Skid Steer HR $___________
-C Fixed Attachment: [Brush Bucket] [Forks] [Gannon] (Circle All That Apply) Attachment HR $___________
-D Mechanical Attachment: [Auger] [Grapple Bucket] [Tree Cutter] [Trencher] (Circle All That Apply) Attachment HR $___________
-E Heavy Mechanical Attachment: [Cold Planer] [Hydraulic Hammer] [Milling] (Circle All That Apply) Attachment HR $___________
8 Compactors
-A Pneumatic Roller
Compactor HR $___________ Model & Roller Width:__________________________________
-B Vibratory Sheeps Foot
Compactor HR $___________ Model & Roller Width:__________________________________
-C Vibratory Steel Wheel
Compactor HR $___________ Model & Roller Width:__________________________________
-D Mobile, Push-behind [Compacting Plate] [Rammer] (Circle All That Apply) Compactor HR $___________
9 Haulers and Transports *MUST OFFER 9A AND 9B MINIMUM*
-A Belly Dump, 20-25 CY capacity
Belly Dump HR $___________ Number Available: ________
-B Hauler / End Dump, 10-12 CY capacity
End Dump HR $___________ Number Available: ________
-C Hauler / End Dump, 10-12 CY capacity, rock bed
End Dump HR $___________ Number Available: ________
-D Hauler / End Dump, 20-25 CY capacity
End Dump HR $___________ Number Available: ________
-E Transport (incl. trailer and tractor), 20 to 29 TON Transport HR $___________
-F Transport (incl. trailer and tractor), 30 to 39 TON Transport HR $___________
-G Transport (incl. trailer and tractor), 40 to 50 TON Transport HR $___________
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
VENDOR DUNS#____________________________
ITEM
NO. DESCRIPTION OF SUPPLIES/SERVICES ITEM UNIT UNIT PRICE
10 Water Truck, Self-Drafting
-A Water Truck, Minimum 2000 to 3999 GAL Water Truck HR $___________
-B Water Truck, Minimum 4000 GAL Water Truck HR $___________
-C Additional Water Fee, per 1000 GAL Water 1000
GAL $___________
11 Service Vehicles
-A Truck/Pickup, four-wheel drive Truck HR $___________
-B Truck, Mechanic, fully equipped Truck HR $___________
-C UTV/ATV, all-wheel drive UTV HR $___________
-D UTV/ATV, all-wheel drive, with utility trailer, minimum 1 CY capacity
UTV w/ Trailer HR $___________
12 Miscellaneous Equipment
-B Concrete Mixer, Portable Mixer HR $___________
-C Crane, with Operator, Size:________ TON Crane HR $___________
-D Dumpster, Roll-Off, minimum 20 CY, per cycle (drop-off, haul-off, and dumping) Dumpster Cycle $___________
-E Generator, Size:____________ KW Generator HR $___________
-F Grid Roller, Size:____________ FT Grid Roller HR $___________
-G Light Tower Light Tower HR $___________
-H Trencher, Walk-Behind, with Operator Trencher HR $___________
-I Vacuum Truck, Pressurized, with Operator Vacuum Truck HR $___________
-J Welding Unit, to include cutting torches, arc welder, wire feed, grinders, and other required tools
Welding Unit HR $___________
-K Water Pump, 2-inch Water Pump HR $___________
-L Water Pump, 4-inch Water Pump HR $___________
-M Water Tower, Capacity:_________ GAL Water Tower HR $___________
-N Other Equipment:
Other Equipment HR $___________
-O Other Equipment:
Other Equipment HR $___________
-P Other Equipment:
Other Equipment HR $___________
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
ITEM
NO. DESCRIPTION OF SUPPLIES/SERVICES ITEM UNIT UNIT PRICE
13 Roadside clearing and brush removal
-A Chipper, Size:____________________________ (equipment only) Chipper HR $___________
-B Roadside chipping crew, minimum two personnel, to be paired with chipper
Chipping Crew HR $___________
-C Feller Buncher, with Operator, Size:_______________________ Feller Buncher HR $___________
-D Log Skidder, with Operator Size:_______________________ Log Skidder HR $___________
-E Sawyer Sawyer HR $___________
14 Labor and Crews
-A Driver, w/ Pilot Car Driver HR $___________
-B Laborer Laborer HR $___________
-C Crew, Traffic Control, minimum 2 workers and per MUTCD Crew HR $___________
-D Welder, certified Welder HR $___________
15 Concrete
-A Concrete slurry, 2 sack cement per CY concrete Concrete Slurry CY $___________
-B Concrete, 5 sack cement per CY concrete, 3000 PSI Concrete CY $___________
-C Concrete delivery haul surcharge Surcharge MI $___________
16 Payment and Performance Bonds
-A Actual cost for projects that exceed $30,000; when bonds are required by Contracting Officer Bonds Actual Cost
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C1 SCOPE OF WORK:
The USDA Forest Service, Apache—Sitgreaves National Forests, Springerville, Arizona, has a requirement for Road Maintenance and Construction on an Indefinite Delivery / Indefinite Quantity (IDIQ) for work on the Black Mesa Ranger District.
The Period of Performance for each awarded contract is from date of award through December 31, 2022 (subject to appropriated funding provided by Congress each fiscal year). The period of performance for awarded task orders is from contract award date through completion or December 31, 2022.
The minimum guarantee per awarded contract will be $2,000 to satisfy the minimum requirement over the life of the awarded contract (4 years). The maximum order limit for all combined awarded contracts awarded under this solicitation number is less than $1,000,000. The government does not guarantee that task orders will reach the maximum order limit.
In order for the awarded contractors to be able to successfully perform this work in a cost effective and timely manner, this solicitation is limited to contractors that maintain a base of operations within a 150 mile radius of Springerville, AZ.
The majority of the work consists of aggregate road maintenance, repair, and some construction. Other work may include clearing drainages, installation or removal of culverts and cattle guards, sign installation, mechanical equipment trail maintenance, concrete structures construction and concrete repair.
Contractors are not required to propose an offer for every line time in the Schedule. Contractors are required to respond to at least the base set of equipment (annotated in red) necessary to meet one of the technical acceptance factors. This equipment is listed below (and in the Schedule of Items):
Motor Grader (2A) CAT M Series or equivalent, 12 to 16 foot blade width, general road blading, aggregate placement, snow plowing
Bulldozer (3C) CAT D5 Class or equivalent OR (3D) CAT D6 Class or equivalent
Track Excavator (5B) CAT 311-318 Class or equivalent, 92 to 120 HP OR (5C) CAT 320-329 Class or equivalent, 140 to
240 HP
Backhoe (6B) CAT 420-430 Class or equivalent, 93 to 108 HP
Haulers and Transports (9A) Belly Dump, 20-25 CY capacity AND (9B) Hauler/End Dump, 10-12 CY capacity
C2 BASIS FOR AWARDS
The Contracting Officer intends to make multiple awards from this solicitation to at least three (3) individual IDIQ contracts using Best Value – Tradeoffs evaluation factors (See Section M).
C3 LOCATION OF PROJECTS
The elevation could range from approximately 3,500 to 11,000 feet. Terrain can vary from relatively flat to steep and rocky (both loose and solid above and below ground with some areas of bedrock). Weather conditions can change quickly, particularly during the summer rain period of July, August and September when strong thunder and lightning storms occur.
Heavy snowfall is common in the late fall throughout the winter. Additionally there is the potential for contractors to have to work around timing restrictions for Threatened, Endangered, & Sensitive species and during the Spring, Summer, or Fall seasons.
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
The project areas for Task Orders under the contracts awarded from this solicitation will primarily be located under the area covered by the Wage Determination:
For mobilization and pricing factor purposes, the central location for Task Orders awarded under this contract for transports, hauling, or concrete delivery haul surcharge, shall be the:
Black Mesa RD: U.S. Post Office, 3410 Buckskin Canyon Road, Heber, AZ 85928.
The Transport rate will be used to move equipment to a project site (from the central location identified in this solicitation). The Transport rate captures mobilization costs to project sites.
C4 TECHNICAL SPECIFICATIONS
AGAR 452.211-72 Statement Of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS, FP-03, U.S.
Customary Units The specifications are included by reference only. The requirements contained in these Standard Specifications are hereby made a part of this solicitation and any resulting work.
These specifications can be ordered from FHWA. For information on how to order books, go to the FHWA’s website, http://www.wfl.fha.dot.gov/design/specs/fp03.htm.
The following specifications are applicable:
DIVISION TITLE
100 General Requirements 150 Project Requirements 200 Earthwork 250 Slope Reinforcement and Retaining Walls 300 Aggregate Courses 400 Asphalt Pavements and Surface treatments 550 Bridge Construction 600 Incidental Construction 700 Material
Special Project Specifications Listings
Special Project Specification (SPS) may add to, delete from, or modify the FP-03. Those specifications are included in full text.
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
SECTION D - PACKAGING AND MARKING
The government will use the FAIR Opportunity process (FAR 16.505 – Ordering) to award task orders under the
IDIQ:
(b) Orders under multiple-award contracts--
(1) Fair opportunity.
(i) The contracting officer must provide each awardee a fair opportunity to be considered for each order exceeding $3,500 issued under multiple delivery-order contracts or multiple task-order contracts, except as provided for in paragraph (b)(2) of this section.
(ii) The contracting officer may exercise broad discretion in developing appropriate order placement procedures. The contracting officer should keep submission requirements to a minimum. Contracting officers may use streamlined procedures, including oral presentations. If the order does not exceed the simplified acquisition threshold, the contracting officer need not contact each of the multiple awardees under the contract before selecting an order awardee if the contracting officer has information available to ensure that each awardee is provided a fair opportunity to be considered for each order. The competition requirements in Part 6 and the policies in Subpart 15.3 do not apply to the ordering process.
However, the contracting officer must--
(A) Develop placement procedures that will provide each awardee a fair opportunity to be considered for each order and that reflect the requirement and other aspects of the contracting environment;
(B) Not use any method (such as allocation or designation of any preferred awardee) that would not result in fair consideration being given to all awardees prior to placing each order;
(C) Tailor the procedures to each acquisition;
(D) Include the procedures in the solicitation and the contract; and
(E) Consider price or cost under each order as one of the factors in the selection decision.
(iii) Orders exceeding the simplified acquisition threshold.
(A) Each order exceeding the simplified acquisition threshold shall be placed on a competitive basis in accordance with paragraph (b)(1)(iii)(B) of this section, unless supported by a written determination that one of the circumstances described at 16.505(b)(2)(i) applies to the order and the requirement is waived on the basis of a justification that is prepared in accordance with 16.505(b)(2)(ii)(B);
(B) The contracting officer shall—
(1) Provide a fair notice of the intent to make a purchase, including a clear description of the supplies to be delivered or the services to be performed and the basis upon which the selection will be made to all contractors offering the required supplies or services under the multiple-award contract; and
(2) Afford all contractors responding to the notice a fair opportunity to submit an offer and have that offer fairly considered.
(iv) Orders exceeding $5.5 million. (Does not apply to this solicitation)
(v) The contracting officer should consider the following when developing the procedures:
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/15.htm#P221_36054 http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/16.htm#P467_78770
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
(A)
(1) Past performance on earlier orders under the contract, including quality, timeliness and cost control.
(2) Potential impact on other orders placed with the contractor.
(3) Minimum order requirements.
(4) The amount of time contractors need to make informed business decisions on whether to respond to potential orders.
(5) Whether contractors could be encouraged to respond to potential orders by outreach efforts to promote exchanges of information, such as—
(i) Seeking comments from two or more contractors on draft statements of work;
(ii) Using a multiphased approach when effort required to respond to a potential order may be resource intensive (e.g., requirements are complex or need continued development), where all contractors are initially considered on price considerations (e.g., rough estimates), and other considerations as appropriate (e.g., proposed conceptual approach, past performance). The contractors most likely to submit the highest value solutions are then selected for one-on-one sessions with the Government to increase their understanding of the requirements, provide suggestions for refining requirements, and discuss risk reduction measures.
(B) Formal evaluation plans or scoring of quotes or offers are not required.
(2) Exceptions to the fair opportunity process.
(i) The contracting officer shall give every awardee a fair opportunity to be considered for a delivery-order or task-order exceeding $3,500 unless one of the following statutory exceptions applies:
(A) The agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays.
(B) Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized.
(C) The order must be issued on a sole-source basis in the interest of economy and efficiency because it is a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.
(D) It is necessary to place an order to satisfy a minimum guarantee.
(E) For orders exceeding the simplified acquisition threshold, a statute expressly authorizes or requires that the purchase be made from a specified source.
(F) In accordance with section 1331 of Public Law 111-240 (15 U.S.C. 644(r)), contracting officers may, at their discretion, set aside orders for any of the small business concerns identified in 19.000(a)(3). When setting aside orders for small business concerns, the specific small business program eligibility requirements identified in part 19 apply.
(ii) The justification for an exception to fair opportunity shall be in writing as specified in paragraphs (b)(2)(ii)(A) or
(B) of this section. No justification is needed for the exception described in paragraph (b)(2)(i)(F) of this section.
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/19.htm#P6_156
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
(A) Orders exceeding $3,500, but not exceeding the simplified acquisition threshold. The contracting officer shall document the basis for using an exception to the fair opportunity process. If the contracting officer uses the logical follow-on exception, the rationale shall describe why the relationship between the initial order and the follow-on is logical (e.g., in terms of scope, period of performance, or value).
(B) Orders exceeding the simplified acquisition threshold. As a minimum, each justification shall include the following information and be approved in accordance with paragraph (b)(2)(ii)(C) of this section:
(1) Identification of the agency and the contracting activity, and specific identification of the document as a “Justification for an Exception to Fair Opportunity.”
(2) Nature and/or description of the action being approved.
(3) A description of the supplies or services required to meet the agency’s needs (including the estimated value).
(4) Identification of the exception to fair opportunity (see 16.505(b)(2)) and the supporting rationale, including a demonstration that the proposed contractor’s unique qualifications or the nature of the acquisition requires use of the exception cited. If the contracting officer uses the logical follow-on exception, the rationale shall describe why the relationship between the initial order and the follow-on is logical (e.g., in terms of scope, period of performance, or value).
(5) A determination by the contracting officer that the anticipated cost to the Government will be fair and reasonable.
(6) Any other facts supporting the justification.
(7) A statement of the actions, if any, the agency may take to remove or overcome any barriers that led to the exception to fair opportunity before any subsequent acquisition for the supplies or services is made.
(8) The contracting officer’s certification that the justification is accurate and complete to the best of the contracting officer’s knowledge and belief.
(9) Evidence that any supporting data that is the responsibility of technical or requirements personnel (e.g., verifying the Government’s minimum needs or requirements or other rationale for an exception to fair opportunity) and which form a basis for the justification have been certified as complete and accurate by the technical or requirements personnel.
(10) A written determination by the approving official that one of the circumstances in (b)(2)(i)(A) through (E) of this section applies to the order.
(C) Approval.
(1) For proposed orders exceeding the simplified acquisition threshold, but not exceeding $700,000, the ordering activity contracting officer’s certification that the justification is accurate and complete to the best of the ordering activity contracting officer’s knowledge and belief will serve as approval, unless a higher approval level is established in accordance with agency procedures.
(2) For a proposed order exceeding $700,000, but not exceeding $13.5 million, the justification must be approved by the advocate for competition of the activity placing the order, or by an official named in paragraph (b)(2)(ii)(C)(3) or (4) of this section. This authority is not delegable.
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
(3) For a proposed order exceeding $13.5 million, but not exceeding $68 million (or, for DoD, NASA, and the Coast Guard, not exceeding $93 million), the justification must be approved by—
(i) The head of the procuring activity placing the order;
(ii) A designee who—
(A) If a member of the armed forces, is a general or flag officer;
(B) If a civilian, is serving in a position in a grade above GS-15 under the General Schedule (or in a comparable or higher position under another schedule); or
(iii) An official named in paragraph (b)(2)(ii)(C)(4) of this section.
(4) For a proposed order exceeding $68 million (or, for DoD, NASA, and the Coast Guard, over $93 million), the justification must be approved by the senior procurement executive of the agency placing the order. This authority is not delegable, except in the case of the Under Secretary of Defense for Acquisition, Technology, and Logistics, acting as the senior procurement executive for the Department of Defense.
(D) Posting.
(1) Except as provided in paragraph (b)(2)(ii)(D)(5) of this section, within 14 days after placing an order exceeding the simplified acquisition threshold that does not provide for fair opportunity in accordance with 16.505(b), the contract officer shall—
(i) Publish a notice in accordance with 5.301; and
(ii) Make publicly available the justification required at (b)(2)(ii)(B) of this section.
(2) The justification shall be made publicly available--
(i) At the GPE https://www.fbo.gov;
(ii) On the Web site of the agency, which may provide access to the justifications by linking to the GPE; and
(iii) Must remain posted for a minimum of 30 days.
(3) In the case of an order permitted under paragraph (b)(2)(i)(A) of this subsection, the justification shall be posted within 30 days after award of the order.
(4) Contracting officers shall carefully screen all justifications for contractor proprietary data and remove all such data, and such references and citations as are necessary to protect the proprietary data, before making the justifications available for public inspection. Contracting officers shall also be guided by the exemptions to disclosure of information contained in the Freedom of Information Act (5 U.S.C. 552) and the prohibitions against disclosure in 24.202 in determining whether other data should be removed. Although the submitter notice process set out in Executive Order 12600 “Predisclosure Notification Procedures for Confidential Commercial Information” does not apply, if the justification appears to contain proprietary data, the contracting officer should provide the contractor that submitted the information an opportunity to review the justification for proprietary data before making the justification available for public inspection, redacted as necessary. This process must not prevent or delay the posting of the justification in accordance with the timeframes required in paragraphs (1) and (3).
http://www.fbo.gov/
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
(5) The posting requirement of this section does not apply--
(i) When disclosure would compromise the national security (e.g., would result in disclosure of classified information) or create other security risks; or
(ii) To a small business set-aside under paragraph (b)(2)(i)(F).
SECTION E - INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
PROJ NAME: 2019 REGULAR ROADS IDIQ BLACK MESA
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
52.246-13 INSPECTION—DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS (AUG 1996)
(a) Unless otherwise designated by the specifications, all workmanship performed under the contract is subject to
Government inspection at all times and places where dismantling or demolition work is being performed. The Contractor shall furnish promptly, and at no increase in contract price, all reasonable facilities, labor, and materials necessary for safe and convenient inspection by the Government. The Government shall perform inspections in a manner that will not unduly delay the work.
(b) The Contractor is responsible for damage to property caused by defective workmanship. The Contractor shall promptly segregate and remove from the premises any unsatisfactory facilities, materials, and equipment used in contract performance, and promptly replaces them with satisfactory items. If the Contractor fails to proceed at once in a workmanlike manner with performance of the work or with the correction of defective workmanship, the Government may—
(1) By contract or otherwise, replace the facilities, materials, and equipment or correct the workmanship and charge the cost to the Contractor; and
(2) Terminate for default the Contractor’s right to proceed. The Contractor and any surety shall be liable, to the extent specified in the contract for any damage or cost of repair or replacement.
(End of clause)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of…