Questions and Answers 09152021.docx

DOCX document 15 KB Posted

Attached to
Construct FSR 4 Road Project - Tonto National Forest Federal contract opportunity
Solicitation number
127EAX21Q0031
Issued by
Department of Agriculture Forest Service R3-Southwestern Region

View the file

Other files for this federal contract opportunity

Other files attached to Construct FSR 4 Road Project - Tonto National Forest, newest first.
File Type Posted
127EAX21Q0031 0002.pdf PDF
FR4_StakingPlan_20210914.pdf PDF
StakingPoints_20210914 (002).pdf PDF
127EAX21Q0031 0001.pdf PDF
Attach 2 - Forest Service Spplemental Specifications_20200813.pdf PDF
Attach 1 - Schedule of Items.pdf PDF
Attach 4 - WD AZ20210008.pdf PDF
Attach 3 - Drawings.pdf PDF
127EAX21Q0031.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 127EAX21Q0031 Amendment 02 FSR 4 Construction – Tonto National Forest

Questions & Answers

1. What is the depth of any blasting?

For blasting requirements, refer to Section 205 – Rock Blasting of the FP-14 Standard Specifications and the Forest Service Supplemental specifications attached to the solicitation.

Blasting should be sufficient to create a single lane road with elevations that conform to project drawings and with proper drainage and stability that prevents unacceptable environmental and resource damage while maintaining safe passage for high clearance vehicles.

2. Can a hammer attached to an excavator or other heavy equipment be used in lieu of rock blasting?

A hammer attached to heavy equipment may be used in lieu of rock blasting if the Contractor determines this alternative method is effective in re-routing the road such that it is compliant with the project standards, specifications, and drawings. In lieu of a rock blasting plan, another plan for an alternative method must be submitted to the CO for approval prior to beginning construction. Additionally, if the Contractor later determines that rock blasting is necessary, a rock blasting plan must be submitted to the CO for approval prior to rock blasting. The Government will not be held financially responsible for additional costs associated with switching methods from hammering to blasting if the need arises.

3. Is all excavated material to be removed from FS land?

All excavated material not used within the road bed or road prism shall be removed from FS land. An exception is “Selective Clearing” material (FP-14, Section 202.01), which may be scattered outside of construction limits (per the Schedule of Items).

4. Is there an AutoCAD file for the topography that can be made available to the contractor?

Topographic files that are available to the Contractor can be found at the following link: USDA Forest Service FSGeodata Clearinghouse - FSTopo Map Products Click on the map, and zoom into the project area. The topo quads for the project area are called “Superior” and “Picketpost Mountain”