This document contains an amendment to a solicitation for construction services to replace a bridge. The amendment provides answers to questions from potential offerors regarding requirements for the project. Key details include: the period of performance is amended to 150 days to allow sufficient time for submittals, procurement, and manufacturing of precast concrete members; there are no restrictions on work hours but major holiday weekends should be avoided; an accessible staging area and borrow pit are available near the project site. Alternate designs for precast concrete span sections and piles may be considered if the specified options cannot be provided by a single certified plant.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12445221B0004 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ATLANTA GA 30309-2449

STE 876S

1720 PEACHTREE ST NW

USDA-FS CSA EAST 12

GAOA06/10/20210003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/25/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to 1) Publish RFI's Q&A.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

JAMES M. HUNT

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

06/10/2021

100-1.7 Black Creek Bridge Replacement Solicitation # 12445221B0004

Questions from site visit:

Q1: Does the existing bridge have a load restriction?

A1: Yes, 10 tons.

Q2: The period of performance is listed as 90 days. This does not allow enough time for submittals, procurement & manufacture of the voided slabs. Will the Notice to proceed be negotiated?

A2:

1. The period of performance will cover the actual “on the ground” work & the start date will be agreed upon by the Contracting officer & Contractor. Submittals for shop drawings from vendors can be made and approved prior to “starting the clock” with the

NTP.

2. The period of performance will be amended to 150 days.

Q3: Are there any restrictions on work hours?

A3: No, but would advise against working on any major holiday weekends due to increased public use.

Q4: Are there any load restricted bridges on access road from other side of bridge (not off Highway 65)?

A4: Yes, there is a 10 TON posted bridge 1.2 miles away.

Q5: Is there a staging area available?

A5: Yes, located on west side of bridge (towards Hwy 65).

Q6: Is there a borrow pit available if needed?

A6: There is a FS borrow pit less than 20 miles away from project site. However, Schedule of Items call for Structural Backfill to be provided from a Commercial Source.

Questions submitted online:

Q7: The following note is shown on Dwg. Sheet #11: “All precast concrete abutment members must be manufactured by the same PCI/NPCA certified plant that manufactures the prestressed concrete members on this project”. Are the concrete piles required to be supplied by the same manufacturer as the slab units and abutment caps? There is a possibility that many manufacturers will not have the capability to produce all of the members as a package.

A7: It is the intent to have all precast members to be manufactured by same certified plant and should be bid as noted in plans. If this requirement cannot be met due to manufacturer limitations, the contractor shall submit request to waive that requirement with justification during the submittal process after award.

Q8: Will alternate span sections be considered for use?

A8: Yes, see Sheet 16 of the Drawings.

Q9: I have spoken with several prestressed concrete plants that manufacture bridge beams and none have the capability to produce a 1’9” voided slab girder as shown on plans sheet 16. When asked if they know of anyone who does, they state they’ve never even heard of a 21” thick hollow core beam and have no idea who to refer me to. Does the engineer have a manufacturer in mind?

A9: Alternate span sections may be submitted – see “Alternate Superstructure Section”, Sheet 16 of the Plans

Q10: There is a note on sheet 11 which states all precast concrete must come from the same plant.

I have been told by several in the industry that if I am somehow able to find a plant that can make the voided slab girders in the specified size, they will be a specialty manufacturer doing hollow core slabs exclusively and it’s extremely unlikely that they can also manufacture the piles, pile caps, backing plates, etc. If the engineer of record knows of a certified pre-cast plant with the capability to make the 21” girders and willingness to make all the precast members, we would be interested in that information.

A10: See Q7.

Q11: Prestressed beam notes state:

Final design & shop drawings will likely take 30 days minimum, then must be submitted 30 days prior to casting, say another 30 days for manufacture & delivery. That takes up the whole 90 day Period of Performance before any new materials hit the jobsite. Please clarify if time extensions will be allowed for this.

A11: See Q2

12445221B0004 - SF 30
100-1.7 Black Creek Replacement QA-Final (002)
100-1.7 Black Creek Bridge Replacement
Solicitation # 12445221B0004

File details come from the government source that posted it. Updated .