Section J Attachment 1 SOW.docx
DOCX document 2 MB Posted
- Attached to
- Remove and Replace Awning/Canopy Federal contract opportunity
- Solicitation number
- 12405B24Q0223
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to remove and replace an awning/canopy at Building 16 of the USDA Agricultural Research Service (ARS) Jamie Whitten Delta States Research Center in Stoneville, Mississippi.
The SOW details the scope of work, which includes removing the existing 24'x8' awning canopy and properly disposing of it, then installing a new metal canopy of the same size along with five new overhead braces and supports. The contractor must obtain all necessary permits, follow safety and quality control requirements, and properly dispose of any hazardous materials. The project is to be completed within 60 calendar days of the Notice to Proceed. Interested vendors are encouraged to conduct a pre-bid site visit. The related federal contract opportunity has the solicitation number 12405B24Q0223 and is being issued by the USDA ARS Southeast Area.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12405B24Q0223_0001 Extension.pdf | ||
| 12405B24Q0223 Awning.pdf | ||
| Section J Attachment 3 ARS-371.pdf | ||
| Section J Attachment 2 WD.pdf | ||
| Section J Attachment 4 ARS-372.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agricultural Research Service
U.S. DEPARTMENT OF AGRICULTURE
12405B24Q0223 – Replace Awning, Stoneville, MS Page 2 of 2
STATEMENT OF WORK
Replace Awning at Building #16
Southeast Area Office Jamie Whitten Delta States Research Center 141 Experiment Station Road Stoneville, Mississippi 38776
Asset ID: 640200B016
1. PROJECT INTRODUCTION
1.1. PROJECT TITLE
Replace Awning at Building #16.
1.2. PROJECT BACKGROUND AND PURPOSE
The USDA, Agricultural Research Service (ARS), Jamie Whitten Delta States Research Center (JWDSRC) is one of the major research establishments of ARS. The Center consists of seven Research Units, with scientists conducting basic and applied research in several areas. The missions and goals of the Center's research are addressed through a multidisciplinary approach.
The awning on the north side of building 16 was damaged by ice and snow build up in January of 2024. The building is farm shop for the ARS located within the Mississippi State compound. The purpose of this project is to remove the damaged awning and replace it with new material in accordance with local, state, and national building code.
1.3. PROJECT CONTACT PERSONS
CONTRACTING OFFICER’S REPRESENTATIVE (COR)
Dwayne Jordan, Utility Systems Operator Supervisor 662-820-8060 dwayne.jordan@usda.gov
CONTRACT SPECIALIST
Amanda Somerville USDA, ARS, ARM, Southeast Area amanda.somerville@usda.gov
CONTRACTING OFFICER (CO)
Shalunda Mix, Contract Specialist USDA, ARS, ARM, Southeast Area 662-686-5346 shalunda.mix@usda.gov
ADMINISTRATIVE OFFICER (AO)
Dr. Phelesia Foster 662-686-3050 phelesia.foster@usda.gov
ENGINEER PROJECT MANAGER (EPM)
Kevin Magee, PE USDA, ARS, SEA Facilities Engineering 662-336-0712 kevin.magee@usda.gov
2. SCOPE AND OBJECTIVES
2.1. DESCRIPTION OF WORK
The Contractor must furnish all personnel, equipment, tools, materials, supervision, and quality control necessary to remove and replace with new material the awning on the north side of Building 16 to include all framing, canopy, arms, and any other material necessary for replacement and adherence to building codes. Contractor services must be performed by a licensed Contractor. The Contractor must:
2.1.1. Remove existing canopy (24’x 8’) and properly dispose of at an off-site location.
2.1.2. Complete installation of new metal canopy (24’ x 8’); to include:
· Five (5) new overhead canopy braces (bolted thru to new metal supports).
· Five (5) new metal supports (behind existing metal sheets).
· Reattach existing lower metal braces at corners (braced to guard rails below).
2.1.3. Clean up and remove all debris.
2.2. The Contractor will verify all dimensions and site conditions prior to beginning work. No Government equipment will be available for use by the Contractor. The Contractor must provide their own restroom facility.
2.3. LOCATION OF WORK
The project is located at 141 Experiment Station Road, Stoneville, Mississippi.
2.4. PRE-BID SITE VISIT
Interested vendors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a quote is submitted. The purpose of a site visit is to observe conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents detail definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.
3. PROJECT SCHEDULE
3.1. The completion of the project must not exceed sixty (60) calendar days from the date of the Notice to Proceed (NTP).
3.2. The Contractor must prepare an overall project schedule including milestone dates for all phases of work and completion date; submit to the COR for approval. This schedule is due fourteen (14) days after contract award. The Contractor must track all work progress to ensure that the project is completed according to the schedule. Include work week schedule with daily starting and stopping time.
3.3. The Contractor must coordinate and confirm the dates for all work with the COR. If necessary, any request for a time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration and provide an updated schedule for completion. No extension of the period of performance may be given without the written authority of the CO.
3.4. Project work hours are 7:00 am and 4:00 pm, local time, Monday through Friday; federal holidays excluded. The contractor is not required to provide services on recognized Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to work schedule must be submitted to CO for written approval prior to any schedule change.
4. GENERAL REQUIREEMENTS
4.1. PERMITS
The Contractor must obtain all building and trade permits necessary to include any drawings, plans, permit and inspection fees, utility location, site surveys, and any other items necessary for compliance with state, local, and federal building authorities.
4.2. SAFETY
The Contractor must submit a Site Safety Specific Plan/Accident Prevention Plan (Plan) in industry recognizable format to the COR within seven (7) days of contract award. The Plan must include phone numbers and maps to local physician offices and the nearest hospital. The Government will review and approve the Plan before issuance of the NTP.
4.3. EXISTING INSTALLATIONS/DEMOLITION
Coordinate removal of existing installations with COR. All disturbances of existing systems must be coordinated with the COR to prevent disconnecting equipment that may jeopardize on-going research.
4.4. QUALITY CONTROL
Provide quality control to ensure that all components of project work meet the requirements of the contract specifications. Ensure that all work not acceptable or compliant with the specifications is corrected prior to inspection or review by the COR. Quality control is the exclusive responsibility of the Contractor.
4.5. PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS
4.5.1. The Contractor must protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property must be repaired at the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.
4.5.2. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor must furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
4.5.3. Open depressions and excavations occurring as part of this work must be adequately barricaded or fenced to prevent vehicle or pedestrian traffic into the work area.
4.5.4. Provide continuous noise and dust abatement as required to prevent disturbance and nuisance to the public and workers and to the occupants of adjacent premises and surrounding areas. Dampen or cover areas affected by demolition operations as necessary to prevent dust nuisance.
4.5.5. The contract documents may not represent all surface conditions at the site and adjoining areas. The known surface conditions are as indicated and must be compared with actual conditions before commencement of work and the cost must be included in the Contractor’s quote.
4.5.6. The Government will not furnish any labor or equipment to unload or move materials or supplies.
5. UTILIZATION OF BIOBASED PRODUCTS
The Contractor must utilize products and material based from bio-based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the Government. All supplies and materials must be of a type and quality that conform to the applicable federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at: www.biopreferred.gov.
6. HAZARDOUS MATERIAL
The JWDSRC is not suspected to contain asbestos containing materials. Existing conditions are reflected correctly to the best of USDA’s knowledge. The USDA makes no representation, warranty, or guaranty that the conditions indicated either are representative of those conditions existing throughout the area, or that unforeseen developments may not occur, or that materials other than, or proportions different from those indicated may not exist. The Contractor must include costs for hazardous materials assessment in the quote. If hazardous materials are found to be present, it must be reported to the CO & COR for further action.
7. DISPOSAL OF REMOVED MATERIALS AND DEBRIS
7.1. The Contractor must dispose of removed, materials, waste, trash, and debris in a safe, acceptable manner, in accordance with applicable laws and ordinances and as prescribed by authorities having jurisdiction.
7.2. Burying of trash and debris on the site is prohibited. Burning of trash and debris at the site is prohibited.
7.3. Remove trash and debris from the site at frequent intervals so that its presence will not delay the progress of the work or cause hazardous conditions for workers and the public.
7.4. Removed materials, trash, and debris must become the property of the Contractor and must be removed from the project site and be disposed of in a legal manner. Location of disposal site and length of haul are the Contractor's responsibility.
7.5. The contractor should make every effort to recycle as much of the construction debris as possible.
7.6. Any waste materials encountered during the demolition that are found to contain lead, asbestos, polychlorinated biphenyls (PCB), fluorescent lamps, or any hazardous substances are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste as well as any specific hazardous waste requirements stated in different sections.
7.7. Comply with hauling and disposal regulations of authorities having jurisdiction, per federal, state, and local requirements.
8. TEMPORARY FACILITIES
Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor must maintain and protect all such utilities during the course of construction and must repair or replace any items damaged through its own negligence. Should the Contractor require any power or utility shutdowns during construction, the Contractor must obtain approval for such shutdown from the COR three (3) working days prior to the need.
9. CLEANUP
The construction site must be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor must remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
10. SUBMITTALS
Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project must be submitted to the EPM, COR, and Contracting Specialist. Electronic submittals are acceptable, otherwise three (3) written submittals are required.
10.1. Project Schedule within fourteen (14) calendar days of award (see Section 3.2).
10.2. Plan within seven (7) days of award (see Section 4.2).
10.3. Any additional material, including shop drawings and specifications, used on this project.
11. INSPECTION AND ACCEPTANCE
A government representative will inspect and approve the work performed on this project. The Contractor must schedule inspection a minimum of three (3) days in advance, in writing, to the COR and CO.
12. FINAL PAYMENT/CONTRACT CLOSEOUT
The following documents are required prior to final payment (other documents may also be required): Release of Liens, Release of Claims, Employee Payroll\Timesheets, and Invoice.
Last Updated 6/3/2024 image1.png image2.jpeg image3.jpeg
File details come from the government source that posted it. Updated .