Amendment_One_Trail_Bridges.pdf

PDF 211 KB Posted

Attached to
Fern Creek & High Trail Bridge Replacements Federal contract opportunity
Solicitation number
12046W19R0006
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

Amendment One

View the file

Other files for this federal contract opportunity

Other files attached to Fern Creek & High Trail Bridge Replacements, newest first.
File Type Posted
Forest_Service_Fire_Protection_R6-FS-6300-52.docx DOCX document
Drawings.pdf PDF
OR59.txt TXT text file
Specifications_-_Fern__High_Specifications.pdf PDF
Trail_Bridges_Solicitation.pdf PDF
Evaluation_Criteria.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION 1. CONTRACT ID CODE Page of Pages

1 3

2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req. No. 5. Project No.

ONE 06/06/2019

6. Issued By: Code 7. Administered By: Code

USDA Forest Service-Mt. Hood National Forest

16400 Champion Way

Sandy, Oregon 97055

See Block 6

8. Name and Address of Contractor

(X) 9A. Amendment of Solicitation No.

12046W19R0006 (Fern Creek & High

Trail Bridge Replacements)

9B. Dated (See Item 11)

05/16/2019

10A. Modification of Contract No.

10B. Date Issued (See Item 13)

Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning ___1___ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE

RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE

CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. This Change Order is issued pursuant to: (specify authority) The changes set forth in item 14 are made in the Contract

Order No. in item 10A.

B. The above numbered contract/order is modified to reflect the administrative changes set forth in Item 14 pursuant to the authority of FAR 43.103(b).

C. This supplemental agreement is entered into pursuant to authority of:

D. Other (specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return ___ copies to the issuing office.

14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See the attached site visit sign in sheet.

See the attached current Q&A for this project.

Return or acknowledge this amendment on page two of the solicitation with your proposal.

By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name and Title of Signer 16A. Name and Title of Contracting Officer

Leslie Solberg 15B. Contractor/Offeror Date Signed 16B. United States of America Date Signed

(Authorized Signature) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (REV.10-83)

PRESCRIBED BY GSA

FAR (48CFR) 53.243

CURRENT QUESTIONS & ANSWERS (Q&A) FOR THIS TRAIL BRIDGES CONTRACT

1. (Q) Does the FS have any estimates on the weight of the damaged, existing bridges to take out?

(A) The Forest Service does not have an actual weight estimate, but based on material, width, and span length, these structures would be in the 6000 to 8000 pound range in whole.

2. (Q) Will the use of any mechanized equipment on the trail be authorized?

(A) The contractor may use mechanized equipment that they feel comfortable getting up the trail. There is a narrow cut out portion of the trail in a steep cliff section that severely limits the size of any trail equipment to be used.

3. (Q) Can the proposals be emailed instead of hard copy mailed?

(A) No, due to fact the bid bond received must be an original.