Statement_of_Work_Specs.pdf

PDF 170 KB Posted

Attached to
Hoonah Road Grading Services Federal contract opportunity
Solicitation number
12010919Q0069
Issued by
Department of Agriculture Forest Service R10-Alaska Region

About this file

Statement of Work/Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Hoonah Road Grading Services, newest first.
File Type Posted
12010919Q0069_RFQ.pdf PDF
SCA_Wage_Determination.pdf PDF
Daily_Activity_Report.pdf PDF
Forest_Service_Supplemental_Specifications.pdf PDF
Map.pdf PDF
Road_Grading_Worklist.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK/SPECIFICATIONS

Scope of Contract

The Contractor shall assume all risk, loss, damage, or expense arising out of prosecution of the work, except as otherwise provided in the contract.

The road maintenance worklist is attached to this solicitation. Segments to be maintained, and type of maintenance, shall be staked by the Engineer prior to commencement of work.

Description and Location The specified roads to be maintained are located on Chichagof Island near Hoonah, AK. Hoonah is a full service community, with daily air taxi services and regularly scheduled ferry and commercial barge services.

Contractor’s Quality Control Plan The Contractor shall provide a quality control plan, which is mutually agreed upon with the Contracting Officer. This plan shall describe the Contractor’s method for ensuring all work meets the contract requirements. At minimum, the Quality Control Plan shall outline how the quality of work will be monitored, how the crew will be supervised, and who will perform the quality control function.

Contractor shall provide the Contracting Officer with documentation of quality control inspections. The Contractor shall, within 5 days from receipt of a request from the Contracting Officer, submit a progress schedule to complete all work ordered within the time stated in the Delivery Order. If the Contractor falls behind schedule, the Contractor shall take such action as necessary to recover. The Contracting Officer may require the Contractor to submit a revised schedule and proposed plan of work to ensure completion of the work within the time stated in the Delivery Order.

Signing and Safety

(a) A reflectorized SLOW MOVING VEHICLE emblem shall be attached to any equipment not designed to maintain a safe travel rate or that will be moving at a slow rate while performing maintenance.

(b) It shall be the Contractor’s responsibility to furnish black and orange reflectorized maintenance warning signs to alert motorists of maintenance operations. A minimum of (1) sign at each end of the road sections being maintained shall be kept in place at all times and shall be moved as work progresses.

(c) If a berm is left in the roadway overnight or weekends due to weather conditions or breakdowns, it shall be properly signed as a hazard and visibly illuminated at night by Type B High-Intensity Flashing Warning Lights with a minimum mounting height of 36 inches to bottom of lens as required by the Manual of Uniform Traffic Control Devices.

Damage to Structures The Contractor shall be held liable and is responsible for any damage caused by Contractor’s personnel or equipment to any bridges, guardrails, culverts, signs, and riprap-protecting culvert inverts. Repair to these structures shall be at the Contractor’s expense and at no additional cost to the Government.

Technical Specifications:

(a) STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS, FP-14, U.S. Customary Units

(b) The specifications are included by reference only. The requirements contained in these Standard

Specifications are hereby made a part of this solicitation and any resulting work.

(c) These specifications can be ordered from FHWA. For information on how to order books, go to the FHWA’s website, https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf

(d) Forest Service Supplemental Specifications for Road Projects are included as an attachment.

(e) BEST MANAGEMENT PRACTICES BMP’S Soil and Water Conservation Handbook FSH

2509.22 The BMP Soil and Water Conservation Handbook, FSH 2509.22 can be found at:

http://www.fs.fed.us/biology/resources/pubs/watershed/FS_National_Core_BMPs_April2012.pdf

Abbreviations Whenever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows: (Reference to a specific standard or specification shall mean the latest addition or amendment thereto in effect on date of Requests for Quote(s).

(a) AASHTO – American Association of State Highway and Transportation Officials.

(b) CS – Commercial Standard Issued by U.S. Department of Commerce.

(c) EPA – Environmental Protection Agency.

(d) FAR – Federal Acquisition Regulation System.

(e) FED SPEC – Federal Specifications.

(f) FSS – Federal Specifications and Standards.

(g) MSHA – Mine Safety Health Administration.

(h) MUTCD – Manual of Uniform Traffic Control Devices.\

(i) NBS – National Bureau of Standards.

(j) OSHA – Occupational Safety and Health Act.

(k) PS – Product Standard issued by the U.S. Department of Commerce.

(l) UL – Underwriter’s Laboratories, Inc.

Quantity Measurement Terms

(a) Measurement under the contract shall be according to the United States standard measure.

(b) The methods of measurement and computation will be those necessary to accurately determine the quantities of materials furnished and work performed.

(c) Miles will, in the absence of known distances from existing plans or surveys, be determined by the Government using calibrated survey odometer or equal substitute operated on the traveled way at or parallel to road centerline.

(d) Linear mile measurement will mean the sum of the road length parallel to the centerline.

(e) Measurement will be made of each item or unit of work, as shown in the Schedule of Items, completed and accepted in accordance with the contract.

(f) Ditch cleaning, pay item D, is paid by the mile. This consists of cleaning ditches on both sides of the road.

https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf

AGAR 452.215-73 Post Award Conference (Nov 1996) A post award conference with the successful offeror(s) will be scheduled if required by the Contracting Officer or requested by the Awardee. It will be scheduled as soon as possible after the date of contract award. Dates and locations of the conferences will be mutually agreed upon.

Landscape Preservation

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which fall outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the clearing limits shall be repaired as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(c) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be dischargeed of into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce sediment content to not more than that of the stream into which it is discharged. Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

(d) Prevention of Oil Spills – If the Contractor maintains storage facilities for oil or oil products on Project Area, appropriate preventive measure shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States.

(e) If the total oil or oil products storage exceeds 1320 gallons or if any single container exceed a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Use of Premises (this supplements AGAR 452.36-72)

(a) Obtain written approval from the Contracting Officer before opening or operating on National Forest land or lands administered by the Forest Service any camp, quarry, borrow pit, storage area, detour, or bypass site, other than SHOWN ON THE DRAWINGS. A camp is interpreted to include the camp site or trailer parking area of any employee working on the project for the Contractor. Such approval, if granted, will be without charge to the Contractor.

(b) Sanitation Facilities: Provide and maintain the following facilities for the work force at the camp, unless provided otherwise:

1. Meet State of Alaska drinking water regulations 18 AAC 80 regarding potable water supplies for drinking, washing and cooking.

2. Comply with State of Alaska wastewater disposal regulations 18 AAC 72 for domestic sewage.

3. Ensure that the design, operation, and maintenance of all solid waste systems under Forest Service jurisdiction meet all Federal, State, and local requirements. Meet State of Alaska solid waste management regulations (18 AAC 60) and Federal regulations contained in 40 CFR 243, 40 CFR 245, 40 CFR 257, and 40 CFR 258. Remove solid wastes and/or residues and dispose of in approved commercial landfills.

4. Meet the requirements of 40 CFR 112 (Oil Pollution Prevention) for fuel storage.

Meet the requirements of 33 CFR 150 and 33 CFR 154 for facilities transferring oil or hazardous materials in bulk.

(c) Do not begin any camp development, either land based or floating, until a plan for development, occupation, and cleanup is submitted and approved by the Contracting Officer.

Include the following information on this plan:

1. Location and size of the proposed camp development, including a map.

2. Wastewater system.

3. Number of people who will use the site and proposed dates of occupancy.

4. Power supply system.

5. Water supply system.

6. Building layout, shop area, living quarters.

7. Road and trail layout.

8. Clearing limits and slash disposal locations.

9. Borrow areas.

10. Dock and access location.

11. Equipment and fuel storage area and Spill Prevention Control and Countermeasure (SPCC) plan.

12. Incinerator location and ash disposal plan.

Forest Service will review plan as submitted for completeness and applicability. Proposed modifications of Contractor's plans will be discussed with the Contractor prior to approval. Any modifications agreed upon will be incorporated in a revised set of plans.

Contractor’s Use and Maintenance of Existing Roads The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. Such roads are those which are necessary for direct access to designated borrow sites, quarries, stockpile sites, waste areas, campsites, equipment unloading ramps, and other approved work areas. The roads authorized for use will be subject to the following general conditions:

(a) Federal Regulations contained in 36 CFR 261.12; except vehicle weight will not exceed that of AASHTO HS20-44 and/or U80 Loading. Submit written requests to the CO for approval to use L90 and U102 overload Loadings on roads authorized for use. Regulations prohibit damaging a road or blocking a road open to use by others, except as otherwise provided in Special Project Specification 104.

(b) The Government will not snowplow roads for the Contractor's use. The Contractor may snowplow any road designated for his use. A permit defining snowplowing requirements is required and will be issued by the District Ranger, upon request by the Contractor. Repair any damage to the road structure caused by snow removal operations. Vehicles, other than conventional over-the-snow vehicles (snowmobiles), will not be permitted to use roads when there is an average of more than 4” of snow unless the road has been snowplowed.

(c) The Contractor is responsible for and will perform road maintenance on Forest Service roads in the construction area commensurate with his use. Perform road maintenance at such intervals that prevent deterioration of the roadway, or as directed by the Contracting Officer.

Road Maintenance Requirements Perform road maintenance work on the required roads in accordance with the following:

(a) Maintain existing roadbed by blading and shaping the traveled way and shoulders. Do not undercut banks. Maintain established drainage structures and/or berms, and place additional drainage structures/berms where necessary to protect embankments.

(b) Perform all seasonal weather cleanup, including removal of bank sloughs, minor slides and fallen timber, which can be accomplished by a motor patrol grader equipped with a front end blade, or comparable equipment, and by the use of hand tools. Replace material eroded from fill slopes and clean out drainage ditches and culverts subject to the above equipment limitations.

(c) Deposit the material removed from slides or other sources in locations approved by the Contracting Officer.

Emergency Control Immediately extinguish without expense to the Government all fires on or in the vicinity of the project which are caused by the Contractor's employees, whether set directly or indirectly as a result of construction operations, with or without direction by the Forest Service. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government resulting from fires set or caused by Contractor's employees or resulting from construction operations.

Contractor's Responsibility for Controlling Other Emergencies - When requested by the Contracting Officer, allow the Forest Service to temporarily use employees and equipment for emergency control work. Payment will be made at not less than the current area rate established by the Forest Service.

Firefighting equipment will be required during the fire season from May 10 to August 31, and during any other period of fire danger designated by the Contracting Officer.

Furnish rust-free fire tools to equip all workers employed in Contractor's operations at each separate work site. Maintain tools in serviceable condition and keep tools in one or more weather-tight fire tools boxes. Paint fire tools boxes red, mark "tools for Fire Only" with letters at least 3” high, and keep sealed. Post a list of the contents inside each fire tool box so as to be visible when opened.

Kind of Tool No. of People Working in Area 1-4 5-9 10-15 16-20 Axe, d.b chopping, 32-inch min. handle 1 1 2 3 Shovels, L.H. R.P., No. 0 or larger 1 3 6 7 Pulaski, 32-inch min. handle 2 3 7 10 File, 10-inch mill bastard 1 1 1 2 Pumps, backpack cans, 5-gal filled with water 1 2 2 3

Equip each internal combustion engine with a spark arrester qualified and rated USDA-Forest Service, Standard 5100-1, unless it is:

(a) Equipped with a turbine-driven exhaust supercharger such as the turbocharger. There shall be no exhaust bypass.

(b) A multi-position engine, such as on a chain saw, which is equipped with screen arrester, as described in the Forest Service Spark Arrester guide.

A spark arrester, which does not meet the requirements in this guide may be approved upon submission of acceptable proof that the arrester is at least 80 percent efficient in retention, attrition, or destruction of carbon particles. Such arrester may be required to meet higher standards as improvements in design and efficiency are discovered.

(c) A passenger-carrying vehicle or light truck intended primarily for use on roads, and equipped with a factory designed muffler and exhaust system.

(d) A heavy duty truck, such as a dump or log truck, or other vehicle used for commercial hauling, used only on roads and equipped with a factory designed muffler and with a vertical stack exhaust system extending above the cab.

Properly install and constantly maintain in serviceable condition all exhaust equipment described in this Subsection, including spark arresters and mufflers.

Equip each unit of mobile or stationary power equipment, including trucks, with one shovel, and at least one fire extinguisher meeting one of the following specifications:

1. 2-1/2 pound size or larger dry chemical type.

2. 4-pound size or larger carbon dioxide type.

Test or check each extinguisher for proper functioning prior to the beginning of fire precautionary period. Provide each gasoline power saw with one chemical-pressurized fire extinguisher of not less than 8-ounce capacity by weight. Maintain the extinguisher in good working order at all times.

Do not burn camp refuse, brush, slash, or debris such as that resulting from clearing around camps or on rights-of-way, without the written approval of the Contracting Officer. Submit written requests for burning to the Contracting Officer at least 48 hours in advance of intended burning. The Contracting Officer will approve routine camp refuse disposal incineration in the camp development proposal.

Prosecution of Work Areas of weak ground are crossed on this project. The initial embankment depth shall be as SHOWN ON THE DRAWINGS or determined by the Contracting Officer. Reestablish design centerline grade and alignment in accordance with Section 152 as construction progresses, and prior to the placement of borrow excavation. Reestablished design grades may be re-staked by the Contracting Officer to meet local conditions. Final grades may be at elevations other than those SHOWN ON THE DRAWINGS, but in no instance will they be lower than that of the surrounding ground elevations. When directed by the CO, return to previously constructed road or trail embankments and place additional borrow material where subsidence has occurred as a result of construction traffic displacing unstable or weak soil underlying the roadway.

Disposal of Merchentable Timber

(a) All timber meeting Forest Service merchantability standards logged during prosecution of this contract, remains the property of the Government. Deck logs in the immediate vicinity in accordance with Section 201 of the specifications.

(b) Buck trees in various lengths to obtain the greatest utilization of material meeting the following utilization standards. The Minimum merchantable piece shall be 6” in diameter inside bark at small end, 12 feet in length, have a net scale of 33 1/3 percent of its gross scale for a sawlog or produce not less than 50 percent of its gross volume in firm usable pulp chips.

(c) Trim allowance shall be a maximum of 12” for log lengths up to 40 foot. An additional 2” of trim shall be allowed for each 10 foot of log length over 40 foot.

(d) Use humbolt undercut in felling merchantable timber. Buck all limbs flush with merchantable logs.

(e) All dead trees which are sufficiently tall to reach the roadbed are designated for cutting. Fell other fire-dangerous dead trees or unstable live trees within 200 foot slope distance of the center line of the road, when marked by the Forest Service. Treat all timber under this subsection meeting utilization standards in accordance with Specification 201 Subsection 201.04, unless relieved in writing.

(f) Cut and use timber designated by the Contracting Officer for construction, without charge.

Other Contracts The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work on this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.

Contractor Responsibility to Notify Government The Contractor will notify the COR when leaving the project area of any task orders for 3 or more days and within 24 hours before returning to the project area.