0920 - GMNF FR10-10.4 Culvert Replacement_SOW.docx
DOCX document 30 KB Posted
- Attached to
- Green Mountain National Forest Culvert Replacement Federal contract opportunity
- Solicitation number
- 12445524R0005
- Issued by
- Department of Agriculture Forest Service
About this file
This document outlines a solicitation for culvert replacement services on the Green Mountain National Forest in Vermont. The United States Department of Agriculture Forest Service is seeking a contractor to replace the culvert on Forest Road 10-10.4, which includes excavation, removal of the existing culvert, installation of a new precast culvert, backfill and embankment construction, guardrail installation, and associated road and site work. The work must be completed between July 1st and September 30th, 2024, with a final completion date of October 31st, 2024. This is a set-aside for small business vendors under NAICS code 237310 with a size standard of $45 million. Vendors must have an active SAM.gov registration to be considered.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12445524R0005_0001.pdf | ||
| 12445524R0005 FR10.docx | DOCX document | |
| 0920 - GMNF FR10-10.4 Culvert Replacement_Plans.pdf | ||
| WDOL_DBA_WD_VT.pdf | ||
| 0920 - GMNF FR10-10.4 Culvert Replacement_Supplemental Specs.docx | DOCX document | |
| 0920 - GMNF FR10-10.4 Culvert Replacement_Schedule of Items.docx | DOCX document | |
| 12445524R0005.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FR10 Culvert Replacement
SECTION C – DESCRIPTION/SPECIFCIATIONS/STATEMENT OF WORK
Scope of Contract The Forest Road 10 – 10.4 Culvert Replacement Contract work shall include, but is not limited to, excavation, removal of existing culvert, layout, furnishing, fabricating, preparing, assembling, and erecting the new precast culvert, associated backfill and embankment construction, guardrail installation, and associated road and site work.
The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Work in accordance with the Specifications referenced below.
Project Schedule Construction shall start after June 1, 2024. All in-stream work shall be between July 1 and September 30, 2024. Final project completion shall be no later than October 31, 2024.
Project Location FR10-10.4 culvert is located on the Green Mountain National Forest in Mt. Tabor, VT in Rutland County.