Contract # GS08P13VEP0011
    PSC Z2AA Repair Or Alteration Of Office...
    Set-Aside 8(a) Sole
    Status Fully Executed
    POP 3/18/13 - 6/16/13 (2 months)
  • $47.2k Dollars Obligated
  • $47.2k Base & Exercised Options
  • $47.2k Base & All Options (Ceiling)
  • Firm Fixed Price Pricing Type
  • Fully Funded Funding Status
  • Not Competed, 1 offer(s) Extent Competed


Amount Date Reason For Modification
$1.2k 6/20/13 Change Order

THE PURPOSE OF THE MODIFICATION IS TO CLEAN UP THE REBAR THAT WAS EXPOSED FROM CORE DRILLING. THIS WILL HELP KEEP STRUCTURAL INTEGRITY WITH THE CONCRETE BEAM. ALSO, IT IS REQUIRED THAT STRUCTUAL SUPPORT BE ADDED TO THE CONCRET BEAM AFTER CORE DRILL WHEN THROUGH THE REBAR. .

$45.9k 3/18/13 Not Listed

REMODEL AND UPDATE THE MEN'S AND WOMEN'S RESTROOMS LOCATED ON THE 2ND FLOOR OF THE J. WILL ROBINSON FEDERAL BUILDING, SALT LAKE CITY, UTAH. THE COMPLETED PROJECT SHALL PRODUCE RESTROOMS THAT ARE ABAAS COMPLIANT AS WELL AS INSTALL PLUMBING FIXTURES THAT REDUCE WATER CONSUMPTION.