Contract # GS02P06DTD0054-GSP0209PC5043
    PSC C211 Architect And Engineering- Gen...
    Set-Aside None
    Status Fully Executed
    POP 7/13/09 - 5/14/15 (5 years)
  • $787.3k Dollars Obligated
  • $787.3k Base & Exercised Options
  • $787.3k Base & All Options (Ceiling)
  • Firm Fixed Price Pricing Type
  • Partially Funded Funding Status
  • Full and Open Competition, 3 offer(s) Extent Competed


Amount Date Reason For Modification
-- 3/17/15 Other Administrative Action

MODIFICATION NO.PA10 EXTENDS END DATE TO MAY 15, 2015 TO ALLOW FOR FINAL PAYMENT AND FINAL REPORT. GRUSN SAMTON - DHS OFFICE ALTERATION, CENTRAL ISLIP, NY.

-- 4/22/14 Other Administrative Action

MODIFICATION PA09 IS ISSUED TO COVER ADDITIONAL PCCS AND CIS SERVICES FOR THE DHS/ICE OFFICE ALTERATIONS. COST FOR PCCS AND CIS EQUALS SERVICES CITED IN MOD PC05 NO LONGER NEEDED. NO COST MOD.

$25.3k 10/27/13 Change Order

MODIFICATION PC08 IS ISSUED TO COVER COSTS OF ADDITIONAL CIS SERVICES ON THE DHS OFFICE RENOVATION AT THE ALFONSE D'AMATO COURTHOUSE IN CENTRAL ISLIP.

$53.4k 8/3/13 Definitize Change Order

MOD PC07 ISSUED TO COVER ADDITIONAL PCCS AND CIS SERVICES RELATED TO THE USMS ELEVATOR TO BE USED TO TRANSPORT DETAINEES.

$3.2k 4/22/13 Definitize Change Order

A/E SERVICES FOR ADDTIONAL REQUIREMENTS REQUESTED BY DHS.

$270.7k 10/16/12 Change Order

MODIFICATION PC05 IS ISSUED TO COVER DESIGN REVISIONS, CONDENSER PUMP SURVEY, DESIGN, AND ADDITIONAL PCCS AND CIS CONSTRUCTION PHASE SERVICES. THIS INCLUDES OPTION 1,2, AND 3 AND AS-BUILTS.

$113.3k 12/7/11 Change Order

BUILD OUT PROJECT

-- 7/11/11 Other Administrative Action

N/A

-- 2/2/11 Other Administrative Action

A/E DESIGN SERVICES

-- 9/22/10 Other Administrative Action

N/A