Project Grant R23AP00537
- This $224,767 Project Grant award from the U.S. Bureau of Reclamation's WaterSMART (Sustain and Manage America's Resources for Tomorrow) program will fund the Headgate Automation and Irrigation Flow Measurement Projects for the Idaho Irrigation District in Bonneville County, Idaho. The key activities include automating three existing headgates, building and automating one additional headgate, adding five Supervisory Control and Data Acquisition (SCADA) measuring and logging stations to...
- The Bureau of Reclamation awarded a $4,084,852 grant to the Enterprize Canal Company, Ltd. under the WaterSMART (Sustain and Manage America's Resources for Tomorrow) program (CFDA 15.507). Through this Project Grant, the Enterprize Canal Company will convert 3,613 linear feet of two 63-inch pipes along a historical canal alignment and install solar-powered automated headgates and measurement devices. This project is expected to result in annual water savings of 7,721 acre-feet by reducing...
- The U.S. Department of the Interior's Bureau of Reclamation awarded a $648,000 Project Grant under the WaterSMART (Sustain and Manage America's Resources for Tomorrow) federal grant program (CFDA 15.507) to the Last Chance Canal Company in Grace, ID. The funding will support the implementation of a modernized Supervisory Control and Data Acquisition (SCADA) system, including the installation of 11 SCADA sites with telemetry, flumes, and automated gates, as well as a software program to manage...
- This federal Project Grant award, provided by the U.S. Department of the Interior's Bureau of Reclamation under the WaterSMART (Sustain and Manage America's Resources for Tomorrow) program (CFDA 15.507), will fund the replacement of 11 outdated manual headgates along two irrigation canals in central Nebraska with automated turnout gates and a supervisory control and data acquisition (SCADA) system. The $724,425 award, made on December 12, 2024, will enable the Central Platte Natural Resources...
- The Pondera County Canal and Reservoir Company in northern Montana was awarded a $496,755 Project Grant from the U.S. Department of the Interior's Bureau of Reclamation under the WaterSMART (Sustain and Manage America's Resources for Tomorrow) program (CFDA 15.507) on August 30, 2023. This funding will enable the company to install a Supervisory Control and Data Acquisition (SCADA) system and flow measurement weirs at two canal headworks locations. It will also automate three gates at the...
- The Fremont Madison Irrigation District (the District) received a $201,777 Project Grant award from the U.S. Department of the Interior's Bureau of Reclamation under the WaterSMART (Sustain and Manage America's Resources for Tomorrow) program (CFDA 15.507). This funding will support the District's efforts to automate six water control structures and install remote operation and data collection equipment. The project will enable the District to automatically maintain desired water levels in the...
- The Department of the Interior Bureau of Reclamation awarded a $5 million cooperative agreement to Farmers Conservation Alliance under the Upper Klamath Basin Water Supply Alignment federal grant program (CFDA 15.566) from February 2023 through February 2028. The award will support identifying sites in Klamath Project irrigation districts and other locations for installing supervisory control and data acquisition (SCADA), telemetry, and automation equipment to improve real-time water quantity...
- The North Side Pumping Company received a $4,024,566 Project Grant award from the Department of the Interior Bureau of Reclamation under the WaterSMART (Sustain and Manage America’s Resources for Tomorrow) federal grant program (CFDA #15.507). The grant funds will support decommissioning two outdated pumping plants from the 1920s and installing approximately 25 new high-efficiency pump stations equipped with variable frequency drives and flow meters connected to existing on-farm irrigation...
- The U.S. Department of the Interior's Bureau of Reclamation awarded the Salmon River Canal Co LTD a $244,790.02 Project Grant under the WaterSMART (Sustain and Manage America's Resources for Tomorrow) program (CFDA 15.507). The grant funds will be used to convert 9,170 linear feet of open earthen canal to a buried polyvinyl chloride (PVC) pipeline on Lateral 1723 and install headgate automation on Lateral 12. The new pipeline will be equipped with electromagnetic meters to reduce water...
- The U.S. Department of the Interior's Bureau of Reclamation awarded a $4,017,835 WaterSMART (CFDA 15.507) Project Grant to the Paloma Irrigation and Drainage District (PIDD) located in Maricopa County, Arizona. The grant will fund the replacement of 16 manually controlled jack lift gates and 24 manually controlled slide gates along Lateral D with new automated gates, as well as the installation of an automated solar-powered Supervisory Control and Data Acquisition (SCADA) system. This project is...
AWARD PURPOSE: PHASE I IS TO INSTALL SCADA PROGRAMS, HEADGATES, OVERSHOT GATES, AND TRASH DIVERTERS AT THE END OF THE NORTH BRANCH LATERALS OF THE PARKS AND LEWISVILLE CANAL TO EFFICIENTLY MANAGE THE ENTIRE SYSTEM. INSTALLATION OF THE HEADGATES AND OVERSHOT GATES AT THE ENDS OF THE LATERALS WILL PROVIDE THE WATER MASTER THE ABILITY TO ADJUST THE FLOW AT THE BOTTOM OF THE LATERALS.ACTIVITIES TO BE PERFORMED: REAL-TIME DATA MONITORING AND CONTROL OF WATER FLOW AT THE ENDS OF LATERALS TO IMPROVE SHAREHOLDER ACCESS TO WATER AND ALLOW THE WATER MASTER TO MANAGE THE WATER IN THE SYSTEM MORE EFFICIENTLY. EXPECTED DELIVERABLES OR OUTCOMES: THESE SIMPLE BUT IMPORTANT BENEFITS WILL IMPROVE THE SHAREHOLDERS ACCESS TO WATER AND ALLOW THE WATER MASTER TO MANAGE THE WATER IN THE SYSTEM MORE EFFICIENTLY. OUR EFFORTS TO CONSERVE AND MORE EFFICIENTLY MANAGE WATER FROM THE SNAKE RIVER, PALISADES RESERVOIR, AND JACKSON LAKE, TWO RECLAMATION FACILITIES, WILL ALL CONTRIBUTE TO A HEALTHIER SNAKE RIVER BASIN.INTENDED BENEFICIARIES: THESE PROJECTS WILL STRENGTHEN WATER SUPPLY SUSTAINABILITY BY IMPROVING THE MANAGEMENT AND DIRECTION OF THE WATER THAT IS DIVERTED BY THE PARKS AND LEWISVILLE IRRIGATION COMPANY FROM THE DRY BED, A TRIBUTARY OF THE SNAKE RIVER. THIS INCREASED MANAGEMENT WILL ALLOW US TO CONSERVE WATER BY MEASURING HOW MUCH IS FLOWING THROUGH OUR SYSTEM AND REDIRECTING IT WHERE IT IS NEEDED MOST.SUBRECIPIENT ACTIVITIES (IF KNOWN OR SPECIFIED AT TIME OF AWARD): N A
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | $36.4k | 2/20/24 |