Purchase Order 69056722P000017
Award Date 4/14/22
Potential Completion Date 8/15/24
Potential Value $39K
Federal Agency
Ultimate Awardee
Not listed PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Not Available for Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Gakona, AK, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Federal Highway Administration awarded a $3.38 million firm fixed-price definitive contract to D & L Construction Co Inc. on March 3, 2023, for the Sourdough Campground Bridge replacement project located approximately 25 miles north of Glennallen in the Gakona, Alaska area. The project involves replacing the existing Sourdough Creek Campground Bridge with a new approximately 100-foot precast concrete bridge, reconstructing bridge approaches, and installing a temporary bypass bridge to...
- The Department of Transportation Federal Highway Administration awarded a $42,304 firm fixed price blanket purchase agreement call contract to Geotill Inc. to construct a bridge at the Sourdough Campground in Gakona, Alaska. The contract is set aside for total small businesses and has a completion date of September 30, 2020. Under this contract, Geotill Inc. will deliver the requested products and services to build a new bridge as part of the Bureau of Land Management's infrastructure...
- This $80,000 firm fixed-price purchase order was awarded by the Federal Highway Administration, a civilian agency, to Geotek Alaska Inc., a small business subchapter S corporation based in Anchorage, Alaska. The contract is for the AKDOT 135(6) Glenn Highway - Kings River Bridge Replacement project, which involves services such as environmental site assessment surveys, subsurface analysis, and hazardous waste site cleanup. Geotek Alaska Inc. has received previous awards from the Army Corps of...
- This is a $86,343.62 firm fixed-price purchase order awarded by the Federal Highway Administration, a civilian agency, to Ahtna Construction & Primary Products Company, LLC (AC&P), an Alaskan Native Corporation-owned construction firm. The contract is for the Herman Leirer Road (Exit Glacier Road) Flood Mitigation project, reference number DTFH7016C00011, with a completion date of July 31, 2019. AC&P is known to have experience providing construction, infrastructure maintenance,...
- This is a $300,030.28 firm fixed price delivery order contract awarded by the Federal Highway Administration (FHWA), a civilian agency, to Mackay & Sposito, Inc., a small business contractor. The contract is for construction inspection services related to the AK NPS KEFJ 10(4), Herman Leirer Road (Exit Glacier Road) project in Seward, Alaska. The work involves tasks such as sub-excavation, pavement reclamation, paving, drainage, and striping. This delivery order was issued under the FHWA...
- This is a $22,527,340.50 definitive, firm-fixed-price federal contract awarded by the U.S. Department of Transportation's Federal Highway Administration to Glacier Construction Inc. (doing business as Southeast Road Builders) for the AK PFH 58(1), Neck Lake Road Reconstruction project on Prince of Wales Island, Alaska. The work includes roadway excavation, rock blasting, embankment, grading, drainage, retaining wall, and guardrail installation. This contract was competitively awarded on an...
- The Federal Highway Administration awarded a $546,872.64 firm fixed-price delivery order to Prohns LLC for the Glenn Highway Rehabilitation project in Alaska, specifically addressing the Kings River Bridge section from milepost 66.0 to 67.2 near Palmer. This delivery order was issued on April 1, 2024, with an ultimate completion date of August 26, 2025, and represents work performed under Prohns LLC's larger $80 million Indefinite Delivery/Indefinite Quantity contract with FHWA that spans...
- This is a Firm Fixed Price Delivery Order contract awarded by the Federal Highway Administration (FHWA) to HDR Engineering, Inc. (doing business as HDR) for $88,179.21. The contract is for construction engineering, inspection, and miscellaneous support services for the AK FS CNF 1015(2) project, which involves the Russian River Campground Access Phase 2 CI-II Services in Cooper Landing, Alaska. The contract has a completion date of July 15, 2024. HDR is a large engineering firm that...
- The Department of Transportation Federal Highway Administration awarded a $930,350.74 firm fixed-price definitive contract to C I C Inc., a self-certified small disadvantaged business, for the AK DOT 110(4), Community - Refuge Trail Project in Soldotna, Alaska. The contract was set aside for small businesses and includes subcontract work by McLane Consulting to provide stormwater pollution prevention plan (SWPPP) and surveying services. This contract was awarded on November 22, 2019 and has a...
- This is a $582,657.06 firm fixed-price definitive contract awarded by the U.S. Department of Agriculture's (USDA) Region 10 - Alaska Region to Central Environmental Inc., a minority-owned, Alaska Native Corporation, and self-certified small disadvantaged business. The contract is for the construction of five snow machine bridges and the replacement of a pedestrian bridge over Winner Creek Gorge along the Iditarod National Historic Trail. This project is part of the USDA's efforts to recover...
The U.S. Federal Highway Administration awarded a $38,557 firm fixed price purchase order to the Copper Valley Electric Association, Inc. (CVEA) to perform temporary utility relocation work for the AK BLM GFO 2019(1) Sourdough Bridge project in Gakona, Alaska. The award does not include a set-aside designation. The contract has an ultimate completion date of August 15, 2024.
Generated 9/10/24, 11:19 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00005 | Close Out | $0 | 9/9/24 | |
| P00004 | Supplemental Agreement for work within scope | $0 | 2/15/24 | |
| P00003 | Supplemental Agreement for work within scope | $0 | 7/21/23 | |
| P00002 | Supplemental Agreement for work within scope | $0 | 6/28/23 | |
| P00001 | Funding Only Action | $0 | 5/5/22 |